Академический Документы
Профессиональный Документы
Культура Документы
Eng.Mukhlis Mirghani
Project Time Management
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
6.1 Plan Time Managements
Eng.Mukhlis Mirghani
.1 Project mgt
plan
.2 Project 1 Expert judgment
charter 2 Meetings 1 Schedule mgt
.3 EEF 3 Analytical plan
.4 OPA Techniques
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
INPUTS T&T
Eng.Mukhlis Mirghani
OUTPUTS
1 Schedule management plan • Project schedule model
• Project schedule model maintenance
development to update the status and record
The scheduling methodology and the progress of the project in the
schedule model during the
scheduling tool to be used) execution
• Level of accuracy • Control thresholds
• Units of measure (such as staff Variance thresholds for monitoring
hours, staff days, or weeks for schedule performance % deviations
time measures, or meters, liters, from the parameters established in
tons, kilometers) the baseline plan
• Process descriptions
• Reporting formats
Eng.Mukhlis Mirghani
6.2 Define Activities
Eng.Mukhlis Mirghani
.1 Schedule mgt plan
.2 Scope baseline .1 Decomposition
.1 Activity list
.3 EEF .2 Rolling wave
.2 Activity attributes
.4 OPA planning
.3 Milestone list
.3 Expert judgment
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
INPUTS
.1 Schedule mgt plan (Guidance, process description)
.2 Scope baseline
• The project WBS, deliverables, (what will be
decomposed )
.4 OPA
• activity lists used by previous similar projects,
• Standardized processes,
• Templates that contain a standard activity list
Eng.Mukhlis Mirghani
Tools & Techniques
.1 Decomposition
• A technique used for dividing and subdividing the work package into
activities
• The Define Activities process defines the final outputs as activities
rather than deliverables, as done in the Create WBS process
.2 Rolling wave planning
Plan in detail what in near tem It is a form of progressive elaboration
Eng.Mukhlis Mirghani
OUTPUTS
.1 Activity list
oa comprehensive list that includes all schedule activities required on the
project
oincludes the activity identifier and a scope of work description for each
activity in sufficient detail
oActivity begin with verb, has object (may has subject)
.2 Activity attributes (evolve over time)
oactivity identifier (ID), WBS ID, and activity label or name, and when
completed, activity description, predecessor, successor, logical
relationships, leads and lags, resource requirements, constraints, and
assumptions
.3 Milestone list (zero duration)
oA milestone is a significant pointEng.Mukhlis
or event Mirghani in a project
6.3 Sequence Activities
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
.1 Schedule mgt plan
.2 Activity list
.3 Activity attributes .1 Precedence
.4 Milestone list 1 Project schedule
diagramming method
.5 Project scope network diagrams
(PDM)
statement .2 Project
.2 Dependency
.6 EEF documents updates
determination
.7 OPA .3 Leads and lags
Eng.Mukhlis Mirghani
INPUTS
1 Schedule mgt plan guidance how the activities may be sequenced.
.2 Activity list all activities which are to be sequenced
.3 Activity attributes describe a necessary sequence of events
.4 Milestone list
scheduled dates for specific milestones, which may influence the way
activities are sequenced
.5 Project scope statement
product scope description, which includes product characteristics may
affect activity sequencing, such as the physical layout of a plant to be
constructed
.6 EEF (scheduling tool)
Eng.Mukhlis Mirghani
T&T
1 Precedence Diagramming Method
• activities are represented by nodes and are graphically linked by one
or more logical relationships to show the sequence in which the
activities are to be performed
• Used 4 Relationship Types:
oFinish-to-start (FS).
oFinish-to-finish (FF).
oStart-to-start (SS).
oStart-to-finish (SF).
2 Leads and lags
Lead: to accelerate the successor
Lag: to delay the successor
Eng.Mukhlis Mirghani
T&T
3 Dependency determination
Eng.Mukhlis Mirghani
OUTPUTS
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
6.4 Estimate Activities Resources
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
.1 Schedule mgt
plan
.2 Activity list
.3 Activity .1 Expert .1 Activity
attributes judgment resource
.4 Resource .2 Alternative requirements
calendars analysis .2 RBS
.5 Risk register .3 Published .3 Project
.6 Activity cost estimating data documents
estimates .4 Bottom-up updates
.7 EEF estimating
.8 OPA .5 Project mgt
software
Eng.Mukhlis Mirghani
INPUTS
.1 Schedule management plan 6 Activity cost estimates
• the units of measure for the The cost of resources may impact
resources to be estimated resource selection
.2 Activity list .7 EEF
.4 Resource calendars resource location, availability, and
skills (AFFECT)
WHEN and HOW LONG the
resources are available .8 OPA
.5 Risk register Historical information regarding
types of resources used for
Risk events may impact resource similar previous projects
selection and availability
Policies and procedures regarding
staffing AND rental and purchase
of supplies and equipment
Eng.Mukhlis Mirghani
Tools & Techniques
.4 Bottom-up estimating
.2 Alternative analysis
• When an activity cannot be
• Hand versus automated estimated with a reasonable degree
• make- or-buy decisions of confidence,
.3 Published estimating data • the work within the activity is
decomposed into more detail.
• production rates and unit costs
of resources • then aggregated into a total
quantity for each of the activity’s
• Cost of labor, material, and resources
equipment
.5 Project mgt software.
• e.g. scheduling software tool to
plan, organize, and manage
resource pools and develop
Eng.Mukhlis Mirghani
OUTPUTS
Software Product
Release 5.0
User User
Meeting
documentation documentation
Eng.Mukhlis Mirghani
6.5 Estimate Activity Durations
Eng.Mukhlis Mirghani
.1 Schedule mgt plan .1 Expert
.2 Activity list judgment
.3 Activity attributes .2 Analogous .1 Activity duration
.4 Activity resource estimating estimates
req .3 Parametric .2 Project
.5 Resource calendars estimating documents
.6 Project scope .4 Three-point updates
statement estimating
.7 Risk register .5 Group decision-
.8 RBS making techniques
.9 EEF .6 Reserve analysis
.10 OPA
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
INPUTS
.1 Schedule mgt plan .7 Risk register
• defines the method used .8 Resource breakdown structure
• the level of accuracy .9 EEF
.4 Activity resource requirements • Productivity metrics,
• The LEVEL of resources assigned • Published commercial information,
IMPACT the duration of the activity and
(Senior or Junior, machinery or • Location of team members
manual)
.5 Resource calendars .10 OPA
availability of specific resources e.g. • Historical duration information,
full-time basis or partial take LONGER • Project calendars,
or LESS • Scheduling methodology, and
.6 Project scope statement • Lessons learned
(assumptions / constraints)
Existing conditions / contract terms
Eng.Mukhlis Mirghani
Tools & Techniques
2 Analogous estimating
• Experts using Historical information for similar activities
• When no sufficient info.
• Accurate
• Time consuming LESS
• Cost
• Applied for total project or to segments
.3 Parametric estimating
• More accurate depend on the sophistication of the model.
• Use statistical relationships between hist. info. and other variable (equation).
.5 Group decision-making techniques
• Involvement of the project team in estimating process increases enhances
BUY-IN CONCEPT
Eng.Mukhlis Mirghani
Tools & Techniques
.4 Three-point estimating
• considering estimation uncertainty and risk
• PERT uses Most likely (tM), Optimistic (tO), Pessimistic (tP)
• Triangular Distribution. tE = (tO + tM + tP) / 3
• Beta Distribution (from the traditional PERT technique). tE = (tO + 4tM + tP) / 6
.6 Reserve analysis
means adding extra time to the schedule (called a contingency reserve or a
buffer) to account for extra risk
• Contingency reserves are the estimated duration within the schedule baseline
to address the “known-unknowns”
• Management reserve is not included in the schedule baseline, but it is part
of the overall project duration requirements to address the “unknown unknowns”
Eng.Mukhlis Mirghani
OUTPUTS
Eng.Mukhlis Mirghani
Develop schedule Brings
everything you’ve done so far
together into one final
schedule.
All of the outputs from the
other Time Management
processes are inputs to
Develop Schedule.
Eng.Mukhlis Mirghani
6.6 Develop Schedule
Eng.Mukhlis Mirghani
Tools & Techniques
Eng.Mukhlis Mirghani
4.Resource
Optimization tech.
• when shared or critically
required resources are only
available at certain times, or in
limited quantities,
• over-allocation, ONE (R)
assigned to two or more
activities @ same time
• cause the original critical path
to change, usually to increase
• Resource smoothing ( CP not
changed)
• Resource leveling,(CP changed)
Eng.Mukhlis Mirghani
T & T cont.
.6 Applying Leads and lags Fast tracking
which activities or phases normally
done in sequence are performed in
parallel for at least a portion of
their duration
only works if activities can be
.7 Schedule compression overlapped to shorten the project
duration
Crashing
may result in rework and increased
• shorten the schedule duration for risk
the least incremental cost
.8 Scheduling tool
• Applied on the critical path where
additional resources will shorten the Automated scheduling tools contain
activity’s duration the schedule model and expedite
the scheduling process
• may result in increased risk and/or
cost
Eng.Mukhlis Mirghani
Important Terms
• Total Float the amount of time that a schedule activity
can be delayed or extended from its early start date
without delaying the project finish date.
• Free Float the amount of time that a schedule activity
can be delayed without delaying the early start date of
any successor
• CP normally characterized by zero total float on the
critical path
• CP is the longest path through a project (The shortest
possible project duration.)
Eng.Mukhlis Mirghani
OUTPUTS
.1 Schedule baseline
.3 Schedule data
• the approved version of a schedule
model .4 Project calendars
• used as a basis for comparison to actual working days and shifts that are
results available for scheduled activities
• a component of the project mgt plan may require more than one project
calendar
.2 Project schedule
.5 Project mgt plan updates (schedule
an output of a schedule model that mgt plan, schedule baseline)
presents linked activities with planned
dates, durations, milestones, and .6 Project documents updates
resources activity attributes,
Bar charts (Gantt charts) activity resource requirements
Milestone chart (completion of major (Resource leveling effect estimates or
deliverables and key external interfaces) the types and quantities of resources
required)
Project schedule network diagram Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
6.7 Control Schedule
Eng.Mukhlis Mirghani
.1 Performance
reviews
.2 Project mgt .1 WPI
software .2 Schedule
.3 Resource forecasts
1 Project mgt plan optimization .3 Change requests
.2 Project schedule techniques .4 Project mgt plan
.3 WPD .4 Modeling updates
.4 Project techniques .5 Project
calendars .5 Leads and lags documents
.5 Schedule data .6 Schedule updates
.6 OPA compression .6 OPA updates
.7 Scheduling tool
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani
INPUTS
.1 Project mgt plan
oSchedule mgt Plan how project schedule will be manage and control
(GUIDE)
oSchedule Baseline to be compared to the actual results
.2 Project schedule (Most Recent Version)
.3 WPD
• information about project progress such as which activities have
started and which activities have finished
• *update project progress “main function of control schedule”
.5 Schedule data
will be reviewed and updated
Eng.Mukhlis Mirghani
Tools & Techniques
.1 Performance reviews .4 Modeling tech.
• measure, compare, and analyze • used to review various scenarios
schedule performance such as actual guided by risk monitoring to bring the
start and finish dates, percent schedule model into alignment with
complete..techniques used: the project management plan and
Trend analysis approved baseline
Critical path method (CP) .5 Leads and lags (adjusting)
Critical chain method (BUFFERS) • to bring project activities that are
behind into alignment with the plan
Earned value management
.6 Schedule compression
.2 Project mgt software
.7 Scheduling tool
• to track planned dates versus actual
dates and to forecast the effects of manual methods or other project
changes to the project schedule model management software
Eng.Mukhlis Mirghani
OUTPUTS
.1 WPI oSchedule Baseline Updates. (caused by
SV and SPI for WBS components, in change)
particular the work packages and oSchedule management plan
control accounts, are documented and o Cost Baseline
communicated to stakeholders
reflect approved change requests or
.2 Schedule forecast changes caused by compression
Forecasts are updated and reissued techniques)
based on work performance .5 Project documents updates
information provided as the project is
executed (includes earned value Risk register
performance indicators) .6 OPA updates
.3Change requests Causes of variances, lessons learned
Schedule variance Analysis can result in
a change request
.4 Project mgt plan updates
Eng.Mukhlis Mirghani
ANY
Questions !!
Eng.Mukhlis Mirghani
Thanks for your
attention!!
Eng.Mukhlis Mirghani
Eng.Mukhlis Mirghani