0 оценок0% нашли этот документ полезным (0 голосов)
1K просмотров4 страницы
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
UAP DOCUMENT 301
GENERAL CONDITIONS
GENERAL CONDITIONS delivered to jobsite 18. Install – mount, connect or apply in Art 1: Definitions and Documents position. 1. Contract Documents 19. Provide – “furnish + install”. - Agreement - Gen. Conditions Art. 2: Execution, Correlation and Intent of - Special Provisions Documents - Specifications 1. Contract Documents - Drawings - 5 sets – signed by the Owner and the 2. Project Representative – full time Contractor. construction inspector – hired by the - Complementary owner. - Binding 3. Sub-Contractor – direct contact to the 2. Borne by the Owner – responsibility for Contractor – executing “any part” of the adequacy of the design & sufficiency of contract. Drawings and Specifications. 4. Surety – provides the guarantee for the 3. Contractor shall have 1 copy of all Contractor’s Bonds Drawings, Specs., Breakdown of Work 5. Proposal Bond – cashier’s check/surety and Sched. Of Const’n Work at the site. bond with the proposal submitted by 4. Owner – furnish 3 sets of Drawings and the Bidder. Specifications to the Contractor. 6. Performance Bond – furnished by the Contractor – guarantee of good faith in Art. 5: Shop Drawings the work. 1. Contactor – prepares 2 copies of shop 7. Payment Bond – furnished by the drawings. Contractor – guarantee of good faith to 2. Submission of shop drawings – pay all obligations. accompanied by a Letter of Transmittal. 8. Guarantee Bond – furnished by the 3. Corrections, changes and variations – Contractor – guarantee to the quality of contractor – prepares 3 sets of shop materials, equipment and workmanship. drawings. 9. Bid Bulletin – additional information issued to bidders before the date of Art. 7: Permit, Taxes and Surveys bidding. 1. All construction permits and licenses – 10. General Conditions – procedural and to be paid for by the Contractor. the administrative aspect of the 2. Contractor – shall secure Final contract. Occupancy Permit – but not responsible 11. Special Provisions – supplementary or for the delay in the issuance. modified instructions issued prior to the 3. Owner – responsible for the bidding. establishment of lot lines, boundary 12. Supplementary Specifications – added lines, easements and benchmarks. or amended information issued to the 4. Contractor – shall pay for the Surveyor Specifications. for confirmation of location of columns, 13. Schedule of Material and Finishes – piers, walls, etc. outline specification. 5. Any deviation form the drawings shall be 14. Breakdown of Work and Corresponding certified to the Architect within 24 Value – listing – different parts of the hours of the discovery of the same. work. 15. Written Notice – information, advice or Art. 9: Equipment notifications delivered in person or by 1. Contractor – furnish 3 copies of mail. complete catalog data – manufactured 16. Time Limits – duration of time allowed item of equipment. by the Contractor. Art. 10: Materials, Fixtures, Appliances and - Estimate – lump sum Fitting Furnished by the Contractor - Unit prices – but not exceeding 25 1. Unless otherwise specified – 3 samples percent in the original Contract. shall be submitted by the Contactor. - Actual direct cost + 15 percent - 2. Contractor – submit samples as many as Contractor’s profit, overhead and may be needed for the purpose of tax. testing – all cost shall be paid for by the 6. Any claim for adjustment – must be Contractor. asserted within 15 days from the date of the change. Art. 11: Materials, Fixtures, Appliances and 7. The Architect can order minor changes – Fitting Furnished by the Owner but not involving extra cost. 1. Contractor discovers any defect 8. Owner – reserves the right – have extra furnished – notify the Architect. work to other person, firm or corporation. Art. 12: Royalties and Patents 9. Contractor – give written notice to the 1. Contractor – pay all royalties and license Architect within 15 days after receipt of fees on all patented material furnished such instruction involving extra cost. by Him. 10. Contractor – give written notice to the Architect within 15 days after Art. 15: Temporary Structures and Facilities recognition of such delay (due to the 1. Contractor – provide temporary office Owner) and proceed to the claim of with water, light, telephone and toilet extra cost. facilities and Architects office of approx. 11. Substantial Completion – not less than 12sq.m. 98% of the Contract amount. 2. Nobody is allowed to sleep or cook 12. Architect – shall issue Certificate of inside the building line of the project Completion – if substantial completion under construction. passed any final test of materials. 13. Contractor – written application of Art. 16: Protection of Work and Owner’s Certificate of Completion if substantial Property part of the work has been used or 1. Smoking is prohibited unless in occupied by the Owner. designated places. 14. “Period of Making Good of Known 2. Transplanting elsewhere within 50m Defects or Faults” – not more than 60 from the building line – by the calendar days after the issuance of the Contractor. Certificate of Completion or within 15 days after its expiration. Art. 20: Work 15. Search for Causes of Defects or Faults – 1. Modification of Contract Prices – written requirement of the Architect – resulting overruns or underruns – not the cost of the work of the Contractor – exceeding 5 percent. borne by the Owner. Unless if such 2. Owner – at any time can order changes defect or fault is the liability of the or alteration – in a written instruction. Contractor. 3. Change of Sub-surface Condition – the Architect make such changes in the Drawing and Specifications – with the Owner’s approval. Art. 21: Time of Completion of Work 4. Adjustment of Contract – equitable 1. Owner – shall give the Contractor a adjustments from the original Contract – written Notice to Proceed. and if the work involved increased – 2. Contract Time – commence on the 7th Contractor shall furnish proportionate day from the receipt of the Notice to additional Performance Bond. Proceed. Every calendar day – working 5. Value of Extra Work day. 3. Extension of Time – if the delay is not such condemned work or material caused by the Contractor – he may file a used, the Owner may auction or request for extension within 15 days privately sell the said material. from the occurrence of the delay. 9. Other requirements before Final 4. Written Consent of the Bondsmen – Payment: attached to any request for an extension - Certificate of Final Building of time – submitted to the Owner. Occupancy 5. Contractor – give written notice to the - Certificate of Final Inspection (of Architect – at least 10 days prior to utilities). beginning – in suspending or resuming - 3 sets of As-built Drawings the work. *As-Built Drawings – working 6. Liquidated Damages – a payment drawings showing the system and actual required due the Contractor to the locations of the outlets, fixtures, Owner for failure to complete the services and equipment that were installed. Contract within the Contract Time. - 3 copies of Directory of Panel Boards Art. 22: Payments - 3 copies of Instruction and Manual 1. Contractor – shall submit within 15 days of operation from the receipt of Notice to Proceed a - 3 copies of Keying Schedule complete Breakdown of Work and - Guarantee Bond (30% of the Corresponding Value of the Contract Contract Price) – period of 1 year Amount. after the Final Acceptance of the 2. Contractor – may submit a Request for work – guaranteeing the quality of Payment for work done – periodically work and materials. Guarantee Bond but not more than once a month. required only if the Owner releases 3. When 50% of the Contract has been the Performance Bond and Payment accomplished, no further retention Bond. shall be made on the balance of the 10. Release of Retention – 3 months after Contract. the date of the Final Payment. 4. Progress Photograph to Accompany Request for Payment. Art. 25: Sub-Contracts - Photos shall be 6” x 8”. 1. At least 15 days prior to the date of - 4 photos at each side of the bidding – the Contractor shall seek the building. Architects clarification for the need of - 2 copies for each photo shall be Sub-Contracts in some particular areas delivered to the Architect. of the work. - All negatives shall bear a date of exposure (date taken). 5. Within 15 days after receipt of Request for Payment, the Architect shall either issue a Certificate of Payment of withhold the Request for Payment. Art. 27: Contractor’s Right to Suspend Work or 6. Within 15 days from the date of Terminate Contract approval of the Request for Payment or 1. The Contractor may suspend or of issuance of Certificate of Payment – terminate the Contract upon 15 day’s the Owner shall pay the amount as written notice to the Owner and certified by the Architect. Architect for the following reasons: 7. No payments shall be made on - Suspension of work by any court or Contracts in excess of 65% of the public authority for 90 days with no Contract Price (conditional). fault of the Contractor. 8. Upon 10 day’s written notice by the Owner, if the Contractor fails to remove - Failure of the Architect to act upon the Request for Payment within 15 days. - Failure of the Owner to act within 15 days upon any Request for Payment or Certification of Payment issued by the Architect. - Failure of the Owner to pay the Contractor any sum within 30 days after its award.
Art. 28: Owner’s Right to Terminate Contract
1. Sufficient cause to justify termination of the Contract if the Contractor does any of the following: - Declare bankruptcy, insolvent or assigned his assets to his creditors. - Violate provisions of the Contract Documents and fail to comply with the agreed Schedule of Completion including extensions. - Failure in superintendence, workmanship, sub-contracts and proper materials. - Failure to make prompt payments.
Art. 31: Contractor’s Insurance and Bonds
1. Performance Bond – 15% of the Contract amount – faithful performance of His work. 2. Payment Bond – 15% of the Contract amount – payments and obligations arising from His contract. 3. Such bonds shall be in the form of Sureties and will remain in effect until replaced by the Contractor’s Guarantee Bond. 4. Performance and Payment Bonds – will be released after 2 months from the Final Acceptance of the work and only after the Contractor furnished to the Owner a Guarantee Bond (30% of the Contract cost). 5. For the Contractor’s guarantee and warranty, such repairs and corrective works shall be done within 5 days after written notice to the Contractor.
Pakistan Brief History"There is nothing that goes through that I don't run by him," Lively says of her husband of nearly two years. "On the site, when I'm doing photo kills I'll say, 'What photos do you think? This one or do you think that one?' And I love that he challenges me. He's someone that I trust when he challenges me. And sometimes I do what I like more anyway and sometimes I feel that was the right way and then other times I think, 'Oh, shoot I should have gone with those photos or I should have gone with that writer.' "That's nice," she added. "It's nice to have a partner in everything." That feeling looks to have inspired Lively's decision to include a $25 set of two vintages spoons engraved with Mr. and Mrs., Mr. and Mr. or Mrs. and Mrs. Lively said, "It's important for us to have a space that really feels like it represents everyone and anyone in the most loving way possible." And what will the twosome be giving each other for their second wedding anniversary next month?
A History of Phil PlanningvA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History of Phil PlanningA History o
Biogas,wikiWhen Ethan Kemp proposed to Hannah, the whole world was shocked including Hannah! She was out of his league, everyone said so. Ethan was a man of the world, and she was his unsophisticated nanny....
But Ethan knew that practical Hannah would be a most convenient wife until he discovered that his shy bride had hidden passions. Intrigued, he wanted their wedding agreement to
...more
When Ethan Kemp proposed to Hannah, the whole world was shocked including Hannah! She was out of his league, everyone said so. Ethan was a man of the world, and she was his unsophisticated nanny....
But Ethan knew that practical Hannah would be a most convenient wife until he discovered that his shy bride had hidden passions. Intrigued, he wanted their wedding agreement to
...moreWhen Ethan Kemp proposed to Hannah, the whole world was shocked including Hannah! She was out of his league, everyone said so. Ethan was a man of the world, and she was his unsophisticated nanny....
But Ethan knew that practical Hannah would be a most convenient wife until he discovered that his shy bride had hidden passions. Intrigued, he wanted their wedding agreement to
...moreWhen Ethan Kemp proposed to Hannah, the whole world was shocked including Hannah! She was out of his league, everyone said so. Ethan was a man of the world, and she was his unsophisticated nanny....
But Ethan knew th