Академический Документы
Профессиональный Документы
Культура Документы
Table of Figures
Photographs 1: Soil sampling and testing activities for KIBP ............................................................. 6
Photographs 2: Site Conditions on Arapai Katakwi road section at the time of the audit ....................... 8
Photographs 3: Progress photographs taken during the contractor’s performance of the planned
Photographs 5: Some of the Unbundled Assets in Lephalale Municipality and Thaba Chew Municipality.
.................................................................................................................................................. 14
Photographs 6: Progress photographs during site condition audit on Ndeeba- Lwanga-Katatenga Road
(39km) road in Rakai ................................................................................................................... 16
Photographs 7: Progress photographs taken during periodic maintenance works for katunguru to
Ishasha road............................................................................................................................... 18
Photographs 8: Progress photographs taken of some of the roads’ condition at the auditing time. ...... 20
Photographs 10: Progress photographs taken during supervision of the road maintenance activities. . 24
Photographs 11: Progress photographs taken during the road works progress. ................................ 26
Photographs 12: Progress photographs taken during the roads condition surveys progress. .............. 27
Photographs 13: Progress photographs taken during the respective roads construction activities. ...... 29
2
1.0 INTRODUCTION
Uganda Institute of Professional Engineers (UIPE) Constitution requires that applicants for corporate
membership among other things have at least two (2) years training as a pupil engineer after
graduation, under the supervision of a Registered Engineer; and a further two (2) years of working
experience in a position or positions of responsibility, again under the supervision of a Registered
Engineer ( UIPE guidelines to applicants for membership of Uganda institution of professional
engineers). Thereafter, candidates are required to submit a 2000 word typed Career Report on such
training and responsible experience. In addition, candidates are further required to submit 4000 word
typed Technical Report on a particular project or projects the candidate has played a major role.
Therefore, I have written this career report as part of fulfillment of the above-mentioned requirements.
In the report, I have described the tasks on which I have been employed in Planning, Designing,
Documentation, Construction, operation and Maintenance of infrastructural projects specially roads’
projects all as discussed in the following sections.
I started on my Post Pupillage experience from April 2011 to date. Throughout the experience, I have
been working under the supervision of Engineer Kato Kagga, the Managing Director of KKATT Consult
Ltd (KKATT), which is an operating engineering consultancy firm based in Uganda.
The accounts in this report section set out my pupillage engineering training and post pupillage
engineering experience in the development of my career to date and explain clearly the precise position
I have occupied, together with the degree of responsibilities assigned. In the report, I have also
enlarged on the special problems met and on the areas where I have obtained extensive experience. I
have also indicated the size and costs of each of the projects involved in where appropriate. In
accordance with UIPE guidelines, I have emphasized my personal experience, bringing out the
principle lessons as well as the challenges met for each of the project. Finally, I have also indicated for
each of the project, the progress photographs taken during and/or after execution of respective project
works.
3
Assistant Team Leader/Highway Engineer, Consultancy Services to
Design Parking areas, walkways, Landscaping and fencing of four weighbridges at
08/2015
Malaba, Busia, Mutukula and Elegu. The purpose of these consultancy services is to
to Date
design parking areas, cargo storage rooms, walkways, landscaping and fencing of
the four weighbridges at Malaba, Busia, Mutukula and Elegu so as to have complete
weighbridge facilities. The Client is Uganda National Roads Authority (UNRA);The
Scope of Work comprises of Inspection and evaluation of the four sites; Carry out all
the required site investigations (including cadastral and topographic surveys and
geotechnical investigations where required); Production of preliminary designs;
Production of detailed Architectural and Engineering designs; Production of Tender
Documents all as described in the Terms of Reference (ToRs).
Task undertaken during employment, Challenges met and lessons learnt
4
Assistant Team Leader/Highway Engineer, Consultancy Services for the
Engineering Design and Tender Documentation of Access Roads at Kasese Industrial
10/2014
to Business Park (7.8km). The client is Uganda Investment Authority (UIA)
10/2015
The Scope of Work comprises of Engineering, Environmental, Social, Economic and
Environmental analysis described in the Terms of Reference (ToRs) to achieve the
project objectives of conduction of a Feasibility Study including Preliminary design;
Preparation of Detailed Engineering Design for the approved park roads alignments;
and Preparation of Bidding Documents based on the approved detailed design. I
was rresponsible for preparation of preliminary and detailed engineering design as
well as Tender documents.
Task undertaken during employment, Challenges met and lessons learnt
5
Task undertaken during employment, Challenges met and lessons learnt
experts who had never worked together which called for a great deal of being a team builder
and a team player in my position doubling as assistant team leader and highway engineer.
6
Highway Engineer, Consultancy Services for Technical and Procurement Audit of
Selected Term and Periodic Maintenance contracts (Lot 4 Eastern Region) of roads
03/2015
to under UNRA implemented in the financial year 2013/2014 in the stations of Jinja
09/2015 (95.2km), Tororo (93.3Km), Moroto (84Km), and Mbale (217.9Km).
The Scope of Work comprised of, review of the existing works contract and
procurement documentation as well as the contract management documentation like;
Drawings, and Bills of Quantities (BoQ), Material Reports and Conditions of Contract,
conduction of site visits to the project roads to verify the findings from the document
review for the scheduled roads in the respective districts.
Responsible for collecting, analyzing, interpreting, and documenting Technical
information to meet the goals of UNRA as the client.
Service contract price is Ugx 153, 000,000.
Task undertaken during employment, Challenges met and lessons learnt
7
Task undertaken during employment, Challenges met and lessons learnt
8
Highway Engineer, Consultancy Services for the Design Review and Construction
Supervision of Masaka to Bukakata Road (41km); The client was UNRA.
03/2015
to
09/2015 The Scope of Work comprises of, detailed design review, and works construction
supervision.
Responsible for detailed design review including pavement design and geometrical
design review of road; and Review of bidding documents including clarification on the
Bills of Quantities.
Task undertaken during employment, Challenges met and lessons learnt
9
Project Coordinator, Periodic Maintenance Works Of 12 Selected National Roads -
09/2014 Lot 5: Ihunga – Kijnjubwa – Bulyamusenyu Road (42.0 Km) in Masindi District. The
to client was UNRA.
06/2015 The Scope of Work comprises of, but not limited to heavy grading, gravelling, and
drainage improvement works. I was responsible for for directing, organizing and
controlling project activities, under the direction of a Resident Engineer.
Approximate value of the service contract was Ugx 145,500,000 And approximate
value of the works contract was Ugx.3,571,335,000.
Task undertaken during employment, Challenges met and lessons learnt
10
Task undertaken during employment, Challenges met and lessons learnt
11
Assistant Highway Engineer, Technical Audit of Selected National Roads
development Project; Lot 1 - Hoima - Kaiso - Tonya Paved Road Project (192Km).
06/2014 UNRA was the client.
to The Scope of Work comprised of, Rreview of the existing works contract and
12/2014 procurement documentation and contract management documentation like; Drawings,
and Bills of Quantities (BoQ), Material Reports and Conditions of Contract to clearly
and conduction of site visits to the project roads to verify the findings from the document
review for the scheduled roads in the respective districts.Responsible for collecting and
assessing of data for compliance with contractual requirements.
Task undertaken during employment, Challenges met and lessons learnt
Progress photographs captured during the auditing activities are indicated in photographs 4
Verifications of measurements for the newly View of the newly constructed road section.
constructed road section.
Photographs 4: Photographic evidence of the field verification auditing activity
12
Civil Engineer, Professional Services for Un Bundling of Assets, Capitalization,
Reconcile General ledger to Asset Register, Update Register in line with Grap
05/2014
17,barcode,Physical Verification of all Municipality's Assets and Amend Assets
to
08/2014 Management Policy at Lephalale and Thaba chweu local Municipalities in the Republic
of South Africa. The client was Lephalale and Thaba chweu local Municipalities.
The scope of work included: Review of existing data on the municipal infrastructure
assets - Detailed condition survey of unbundled assets – Valuation of the assets;
Drafted Asset Register for the municipalities Infrastructure Assets.
I was responsible for review of existing data including Integrated Development
Plans, Locality Maps, As built drawings, Construction drawings, Completion reports,
and Bills of Quantities; condition assessment for the infrastructure assets; and rate
analysis.
Approximate value of the service contract South African Rand (ZAR) 1800, 000.
Task undertaken during employment, Challenges met and lessons learnt
13
Task undertaken during employment, Challenges met and lessons learnt
Photographs captured of some of the unbundled and valued infrastructure are indicated in photographs
5
Agapanthus road in Lephalale Municipality which was A park in lephalale that was unbundled
unbundled and its condition assessed as captured by
the ROMBDAS machine
Water tank that was unbundled in Lephalale Thaba Chweu Municipality building that was
Municipality. unbundled.
Photographs 5: Some of the Unbundled Assets in Lephalale Municipality and Thaba Chew Municipality.
14
Highway Engineer, Technical and Financial Audit of the following districts under
Uganda Road Fund (URF); Moyo District Local Government (DLG),Oyam
04/2014 DLG,Adjuman DLG,Kitgum DLG,Yumbe DLG, and Rakai DLG. URF was the client.
to
08/2014 The Scope of Work comprised of, Rreview of the existing works contract and
procurement documentation and contract management documentation like; Drawings,
and Bills of Quantities (BoQ), Material Reports and Conditions of Contract to clearly and
conduction of site visits to the project roads to verify the findings from the document
review for the scheduled roads in the respective districts. Responsible for collecting
and assessing of data for compliance with contractual requirements.
Task undertaken during employment, Challenges met and lessons learnt
15
Photographs taken during works Ndeeba- Lwanga-Katatenga Road (39km) road in Rakai are indicated
in photographs 6.
Measuring the width of fill at ch. 5+ 600 Taking gravel samples from borrow pit at ch.1
Verifying the thickness of the gravel wearing course by The whole road is poorly maintained with overgrown
audit team. grass in the shoulders and side drains.
Photographs 6: Progress photographs during site condition audit on Ndeeba- Lwanga-Katatenga Road (39km) road
in Rakai
16
Assistant Resident Engineer (ARE), Consultancy Services for the Supervision of
Periodic Maintenance Works of Selected National Roads, Lot 6- Katunguru to Ishasha
11/2012
road (87Km). UNRA was the client.
to
10/2014 The Scope of Work comprised of, but not limited to medium grading, gravelling,
drainage improvement works, and bituminous Surfacing.
Responsible for carrying out day-to-day Construction Supervision for the maintenance
works. Approximate value of the service contract is Uganda Shillings (Ugx)
208,208,000. And approximate value of the works contract was 6,239,172,950/=.
Task undertaken during employment, Challenges met and lessons learnt
17
Task undertaken during employment, Challenges met and lessons learnt
Bituminous surfacing works progress between 27+000 to 29+000 under my close supervision.
Photographs 7: Progress photographs taken during periodic maintenance works for katunguru to Ishasha road.
18
Civil Engineer /Assistant Team leader, Provision of consultancy
services for Technical and Financial reviews in the following DA:- Mbale, Manafwa,
07/2012
Tororo, Kotido, Kabongo, and Amurial. URF was the client. Responsible for
to
collecting, analyzing, interpreting, and documenting Technical information to meet
11/2012
the goals of Uganda Road Fund (URF). Approximate value of the Service contract
was Ugx 200,000,000/=.
19
Section of Walang road in Mbale District that was Broken and Washed out culvert line on Bubuto to Magale
inadequately compacted. Road in Manafwa District
Photographs 8: Progress photographs taken of some of the roads’ condition at the auditing time.
20
Civil Works Supervisor, Provision of consultancy services for civil work supervision of
drilling exploration activities at Tangi and Bugungu sites, Exploration Area 1, Albertine
Graben, republic of Uganda, Total Exploration & Production. The client was Total
05/2012 Exploration and Production
to I was Responsible for direct supervision of Contractors on Work site preparation,
6/2012 earthworks (Excavating/Backfilling as well as gravelling), Concrete works, and Sewage-
Drainage-Waste disposal of three well pads each measuring 100m X 100m and at cost of
USD $ 406, 730.86 each.
Task undertaken during employment, Challenges met and lessons learnt
21
Task undertaken during employment, Challenges met and lessons learnt
one well pad formed the basis for the construction of others;
In the construction of pads, OHSE should be ensured at all times during construction due to
toxicity of oil and sensitivity of working within the NP.
Concrete Works
around Cellar pipe
Oil/Water Interceptor
Oil/Water interceptor, and Evaporation pit Installation of cellar pipe and casting of concrete to hold
constructed on well pad. it firmly in position.(Ngiri D well pad construction)
Photographs 9: Progress photographs taken during oil pad construction.
22
Assistant Resident Engineer, Consultancy Services for the Supervision of Corner
Cwagere- Wii-Gudu Landing site (Apyenyang) road, Aburawak to Apenyoweo P/s road,
BarEbong/Arukene-Aburawak roads all in Dokolo District, funded under the Multi Year
01/2011 Assistance Programme (MYAP) in Northern and Eastern Uganda, ACDI/VOCA was the
to
12/2012 client.
23
Task undertaken during employment, Challenges met and lessons learnt
During wet season, it’s rewarding to maximize on design review of the project especially the
drainage.
Re-alignment of roads should be considered whenever the road passes through compounds of
social centers such as schools and Hospitals.
Photographs of some of road works constructional activities supervised are indicated in photographs 10
24
Highway Engineer, Consultancy Services for the Provision of Technical Assistance
11/2011 to to AFRICARE funded under the Multi Year Assistance Programme (MYAP) in
12/2011 Eastern Uganda. ACDI/VOCA was the client. Responsible for work planning,
technical management and execution of rehabilitation/construction of 30km of road
sections in Kumi, and Bukedia.
25
Dumped gravel on Konguga to Nalugai Road Curing of gravelled sections
Photographs 11: Progress photographs taken during the road works progress.
26
Highway Engineer/Assistant Team leader, Management services for the
Condition Assessment, Detailed Design, Cost Estimation and Tender document
08/2011 – preparation for the rehabilitation of community infrastructure, roads, funded under the
11/2011 Multi Year Assistance Programme (MYAP) in North and Eastern Uganda,
ACDI/VOCA. I was Responsible for condition assessment, detailed engineering
design and preparation of cost estimates as well as development of rehabilitation
plans for 81.7km of district feeder roads in the following Districts: Dokolo. Kaberamaido,
Soroti, Serere and Amuria.
Water running through the erosional gullies formed Water in flowing on to the road surface in the area of
in the road way due to inadequate drainage on weak soils on Okolongo-Akumoi Road in Serere District.
Orungo-Moruinera-Akerai in Amuria.
Photographs 12: Progress photographs taken during the roads condition surveys progress.
27
Assistant Resident Engineer, Consultancy Services for the Supervision of
Ayami – Ayile – Odoro – Barrpi road (24.8km), Abutadi – Barowo-Ayenga Road
04/2011 to (7.6km), Alanyi – Alebtong Road (17.8km), Aloworo – Wiiodyek Road (8.6km) ,Akol
11/2011 – Ogur Road (10.3km) and Ogur – Barlonyo – Orit road (11.6km), funded under
the Multi Year Assistance Programme (MYAP) in Northern and Eastern Uganda,
ACDI/VOCA. Responsible for carrying out Construction Supervision for the feeder
roads. Works included bush clearance, formation works, gravelling, culvert works,
and swamp filling.
28
Task undertaken during employment, Challenges met and lessons learnt
Heavy frequent rainfalls that always interfered with progress of gravelling of works.
Lessons learnt
Design Review should always be carried out during works execution (especially in wet
weather) to cater for especially cross drainage that might be left out at initial design stage
especially carried out in dry weather.
Sharp corners should be straightened as much as possible to minimize safety risks to the
road users.
It’s desirable that heavy grading is always carried out especially at the beginning of a wet
season to ensure that the road is constructed with the correct profile for effectively shedding
during the rains.
Photographs of taken of the respective roads construction activities are indicated in photograph 13
Thickness Confirmatory checking of Gravel wearing Completed culvert works crossing one of the
Coarse by the Acting Lira District Engineer (3rd from rivers across the road.
left) and the Assistant Resident Engineer (my self).
Curing of gravel wearing course on Alanyi – Alebtong Confirmatory Testing of Abutadi – Barowo-
Road. Ayenga Road gravel wearing coarse
compaction, by Ministry of works laboratory-
gulu.
Photographs 13: Progress photographs taken during the respective roads construction activities.
29
Site Agent/ Engineer, Construction of Girik River Bridge (30m span) including its pile
06/2010 to foundation (24 piles of 15m as average depth) under Karamoja Roads Development
03/2011 Programme (KRDP). Responsible for Day to day site management of the contract,
planning, coordinating and monitoring site activities, acting as the primary contact
person for all site related issues, establish and maintain schedule of activities to ensure
work was carried out in time.
The works were executed to completion at a contract price of Ugx 2,208,693,192/=
30
SPT machine in use Cut piles protruding in
concrete blinding
SPT at one of the drilled pile hole- Pile foundation for the Cast piles Ready to receive pile cap during construction
proposed Girik River Bridge site. Girik river bridge pile foundation for Abutment 1.
Erected Abutment
Walls and Central Pier
of Girik Bridge
Pile cap
reinforcements in
place
Abutment walls and Center pier construction for Girik Reinforcements for the pile cap-Girik River Bridge.
River Bridge.
Photographs 14: Progress photographs taken of bridge construction activities.
31
Site Agent/Site Engineer, Rehabilitation of Girik River – Lokales - Karita
01/2009 to road (under Karamoja Roads Development Programme (KRDP).
03/2011 Responsible for Day to day site management of the contract, planning,
coordinating and monitoring site activities, acting as the primary contact person for all
site related issues, establish and maintain project and schedule of activities to ensure
work is carried out in time. The works were executed to completion at a contract price of
Ugx 1,502,845,430/=.
32
Task undertaken during employment, Challenges met and lessons learnt
available and it may be necessary to use lower the grade of murram than specified to make use
of what is available.
Photographs of taken of the road construction activities are indicated in photograph 15
Casuals loading
gabions for drift
foundation Rock being removed
Drift construction at season river crossing through the Removal of rock outcrops from the road.
road.
Photographs 15: Progress photographs taken of road construction activities.
33
3.0 CONCLUSION
As discussed in above sections of the report, I attained my pupilage engineering experience in roads
and bridge construction for a period of over 2years after completing my degree in BSC. Civil
Engineering. In addition, I have over 4 years post pupillage experience since April 2011 to date.
Therefore, the duration of my pupillage and post pupillage engineering experience is well above the
required minimum duration of 4 years, specified by UIPE in her guidelines for potential candidates who
wish to register with UIPE and become corporate members of ERB.
Throughout my career development, I have performed tasks in planning, design, construction, and
maintenance of infrastructure projects specially roads bridge projects, and parking yards. I have also
performed major roles in financial and technical audits on several road projects; and preparation of
Asset Management Registers for infrastructure assets like buildings, water treatment plants, paved and
unpaved roads.
Therefore, my experience as set out in the report fulfills the expectation of UIPE for potential candidates
to have gained experience in the following areas of projects execution: Project design, Documentation,
Construction/installation, and Operation and maintenance.
34