ANALISA TEKNIS PEKERJAAN

AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Urugan dan Pemadatan Tanah untuk Sub Grade (M3) (Asumsi Jarak Angkut 5 Km)
6001 201 Pekerja OH 0.0087
6001 206 Mandor OH 0.0022
6001 651 Water Tank Jam 0.0070
6001 709 Excavator (/Hari) Hari 0.0087
6001 621 Dump Truck 5 Ton Jam 0.1839
6001 637 Motor Grader Jam 0.0020
6001 649 Vibrator Roller Jam 0.0543
6001 1264 Tanah Urug M3 1.2000

Pekerjaan Sirtu untuk Sub Base (M3) CBR >25% (Asumsi Jarak Angkut 5 Km)
6002 201 Pekerja OH 0.0225
6002 206 Mandor OH 0.1160
6002 651 Water Tank Jam 0.0104
6002 637 Motor Grader Jam 0.0090
6002 643 Tandem Roller Jam 0.0428
6002 709 Excavator (/Hari) Hari 0.0080
6002 621 Dump Truck 5 Ton Jam 0.3014
6002 1260 Sirtu M3 1.1000

Pekerjaan Batu Pecah untuk Sub Base (M3) CBR >80% (Asumsi Jarak Angkut 5 Km)
6003 206 Mandor OH 0.0117
6003 201 Pekerja OH 0.0225
6003 621 Dump Truck 5 Ton Jam 0.3091
6003 709 Excavator (/Hari) Hari 0.0080
6003 637 Motor Grader Jam 0.0090
6003 651 Water Tank Jam 0.0141
6003 643 Tandem Roller Jam 0.1071
6003 1205 Agregat Pecah Mesin 20-30 mm M3 1.1000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Lean Concrete (M3)


6004 206 Mandor OH 0.0201
6004 201 Pekerja OH 0.1205
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6004 202 Tukang Jam 0.0201


6004 652 Wheel Loader Jam 0.0400
6004 636 Mixer Truck Jam 0.2400
6004 609 Concrete Pan Mixer (Batching Plant) Jam 0.0400
6004 626 Generator Set Jam 0.0400
6004 1102 Semen PC Kg 400.0000
6004 1205 Agregat Pecah Mesin 20-30 mm M3 0.8900
6004 1249 Pasir Beton M3 0.5400
6004 7005 Additive Ltr 1.0500
6004 7007 Air (Kapal) M3 0.2000

Beton Semen Bertulang Mutu K-350, Fr= 45 kg/cm3 untuk Lapisan Atas APron , Run
6005 243 Tukang Batu OH 0.0200
6005 201 Pekerja OH 0.0140
6005 206 Mandor OH 0.0207
6005 671 Slip Form Paver Jam 0.0007
6005 652 Wheel Loader Jam 0.1200
6005 651 Water Tank Jam 0.1200
6005 636 Mixer Truck Jam 0.2400
6005 609 Concrete Pan Mixer (Batching Plant) Jam 0.1400
6005 626 Generator Set Jam 0.0400
6005 1102 Semen PC Kg 750.0000
6005 1205 Agregat Pecah Mesin 20-30 mm M3 0.8200
6005 1249 Pasir Beton M3 0.4700
6005 2617 Wire Mesh M3 25.0000
6005 7005 Additive Ltr 1.0500
6005 7007 Air ( Kapal) M3 0.2000
6005 7142 Joint Sealant M1 3.5000

Sirtu Padat CBR > 25% (Sub Base) tebal = 30 cm (M2)


6006 201 Pekerja OH 0.0680
6006 206 Mandor OH 0.0035
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6006 606 Buldozer Jam 0.0309


6006 637 Motor Grader Jam 0.0309
6006 643 Tandem Roller Jam 0.0009
6006 651 Water Tank Jam 0.0309
6006 1266 Sirtu M3 0.3000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Lapisan Agregat Base Padat CBR > 80% tebal = 25 cm (M2)


6007 201 Pekerja OH 0.0056
6007 206 Mandor OH 0.0291
6007 621 Dump Truck 5 Ton Jam 0.0258
6007 637 Motor Grader Jam 0.0258
6007 649 Vibrator Roller Jam 0.0234
6007 651 Water Tank Jam 0.0258
6007 1205 Agregat Pecah Mesin 20-30 mm M3 0.3000

Lapisan Agregat Base Padat CBR > 80% tebal = 35 cm (M2)


6008 201 Pekerja OH 0.0079
6008 206 Mandor OH 0.0408
6008 621 Dump Truck 5 Ton Jam 0.0361
6008 637 Motor Grader Jam 0.0361
6008 649 Vibrator Roller Jam 0.0328
6008 651 Water Tank Jam 0.0361
6008 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.3500

Lapisan/ Overlay Aspal Penetrasi Tebal 7,5 cm Padat (M2)


6009 206 Mandor OH 0.0233
6009 201 Pekerja OH 0.3513
6009 643 Tandem Roller Jam 0.0060
6009 802 Alat Bantu Ls 0.0030
6009 1024 Aspal AC 60-70 (ex. Shell Drum) Kg 8.0000
6009 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.1000
6009 1249 Pasir Beton M3 0.0020
6009 621 Dump Truck 5 Ton Jam 0.1390
6009 6019 Kayu Bakar M3 0.0020
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Lapisan/ Overlay Aspal kolakan Tebal 7,5 cm Padat (M2)


6010 201 Pekerja OH 0.1513
6010 206 Mandor OH 0.0233
6010 645 Tire Roller Jam 0.0070
6010 802 Alat Bantu Ls 0.0030
6010 643 Tandem Roller Jam 0.0070
6010 1024 Aspal AC 60-70 (ex. Shell Drum) Kg 10.0000
6010 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.1000
6010 1248 Pasir Aspal/ Abu Batu/ Screening M3 0.0100
6010 1249 Pasir Beton M3 0.0100
6010 621 Dump Truck 5 Ton Jam 0.1390
6010 7026 Minyak Tanah Ltr 0.2000
6010 6019 Kayu Bakar M3 0.0400

Lapisan/ Overlay Aspal Beton (AC)Tebal 7,5 cm Padat (M2)


6011 201 Pekerja OH 0.1875
6011 206 Mandor OH 0.0259
6011 643 Tandem Roller Jam 0.0033
6011 652 Wheel Loader Jam 0.0050
6011 645 Tire Roller Jam 0.0048
6011 621 Dump Truck 5 Ton Jam 0.1550
6011 603 Asphalt Finisher Jam 0.0050
6011 601 AMP Jam 0.0082
6011 626 Generator Set Jam 0.0042
6011 1024 Aspal AC 60-70 (ex. Shell Drum) Kg 11.9000
6011 1205 Agregat Pecah Mesin 10-20 mm M3 0.0509
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6011 1206 Agregat Pecah Mesin 5-10 mm M3 0.0518


6011 1248 Pasir Aspal/ Abu Batu/ Screening M3 0.0518
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Lapisan/ Overlay Aspal Penetrasi Tebal 5 cm Padat (M2)


6012 201 Pekerja OH 0.1009
6012 206 Mandor OH 0.0155
6012 643 Tandem Roller Jam 0.0020
6012 802 Alat Bantu Ls 0.0020
6012 1024 Aspal AC 60-70 (ex. Shell Drum) Kg 5.0000
6012 621 Dump Truck 5 Ton Jam 0.0950
6012 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.0667
6012 1249 Pasir Beton M3 0.0013
6012 6019 Kayu Bakar M3 0.0013

Lapisan / Overlay Aspal Kolakan 5 cm Padat (M2)


6013 201 Pekerja OH 0.1009
6013 206 Mandor OH 0.0155
6013 643 Tandem Roller Jam 0.0020
6013 645 Tire Roller Jam 0.0020
6013 802 Alat Bantu Ls 0.0020
6013 1024 Aspal AC 60-70 (ex. Shell Drum) Kg 6.6667
6013 1249 Pasir Beton M3 0.0667
6013 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.0667
6013 621 Dump Truck 5 Ton Jam 0.0927
6013 1248 Pasir Aspal / Abu Batu / Screening M3 0.0067
6013 6019 Kayu Bakar M3 0.0267

Lapisan / Overlay Aspal Beton (AC) 5 cm Padat (M2)


6014 201 Pekerja OH 0.1250
6014 206 Mandor OH 0.0173
6014 643 Tandem Roller Jam 0.0022
6014 652 Wheel Loader Jam 0.0033
6014 645 Tire Roller Jam 0.0032
6014 621 Dump Truck 5 Ton Jam 0.1033
6014 603 Asphalt Finisher Jam 0.0033
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6014 601 AMP Jam 0.0033


6014 626 Generator Set Jam 0.0028
6014 1024 Aspal AC 60-70 (ex. Shell Drum) Kg 7.9333
6014 1205 Agregat Pecah Mesin 10-20 mm M3 0.0339
6014 1206 Agregat Pecah Mesin 5-10 mm M3 0.0345
6014 1248 Pasir Aspal / Abu Batu / Screening M3 0.0345
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Lapisan Cement Treated Base Course (CTBC) (M3)


6015 201 Pekerja OH 0.3797
6015 206 Mandor OH 0.0543
6015 649 Vibrator Roller Jam 0.0330
6015 621 Dump Truck 5 Ton Jam 0.1073
6015 645 Tire Roller Jam 0.2300
6015 609 Concrete Pan Mixer (Batching Plant) Jam 0.0590
6015 651 Water Tank Jam 0.0160
6015 652 Wheel Loader Jam 0.0313
6015 603 Asphalt Finisher Jam 0.0400
6015 1102 Semen PC Kg 256.0000
6015 1205 Agregat Pecah Mesin 20 - 30 mm M3 1.2000

Lapisan Cement Treated Base Course Tebal 25 cm (M2)


6016 201 Pekerja OH 1.5625
6016 206 Mandor OH 0.1953
6016 637 Motor Grader Jam 0.3045
6016 645 Tire Roller Jam 0.0243
6016 649 Vibrator Roller Jam 0.0004
6016 651 Water Tank Jam 0.0243
6016 652 Wheel Loader Jam 0.0021
6016 1102 Semen PC Kg 25.2000
6016 1205 Agregat Pecah Mesin 10-20 mm M3 0.0127
6016 1206 Agregat Pecah Mesin 5-10 mm M3 0.0130

Lapisan Asphalt Treated Base (ATB) Tebal 7,5 cm (M2)


6017 201 Pekerja OH 0.1875
6017 206 Mandor OH 0.0259
6017 643 Tandem Roller Jam 0.0033
6017 652 Wheel Loader Jam 0.0050
6017 645 Tire Roller Jam 0.0048
6017 621 Dump Truck 5 Ton Jam 0.1550
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6017 603 Asphalt Finisher Jam 0.0050


6017 601 AMP Jam 0.0082
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6017 626 Generator Set Jam 0.0042


6017 1024 Aspal AC 60-70 (ex. Shell Drum) Kg 9.1402
6017 1248 Pasir Aspal/ Abu Batu/ Screening M3 0.0023
6017 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.0676
6017 1206 Agregat Pecah Mesin 5-10 mm M3 0.0475
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Lapisan Asphalt Treated Base (ATB) Tebal 5 cm (M2)


6018 201 Pekerja OH 0.1250
6018 206 Mandor OH 0.0173
6018 643 Tandem Roller Jam 0.0022
6018 652 Wheel Loader Jam 0.0033
6018 645 Tire Roller Jam 0.0032
6018 621 Dump Truck 5 Ton Jam 0.1033
6018 603 Asphalt Finisher Jam 0.0033
6018 601 AMP Jam 0.0055
6018 626 Generator Set Jam 0.0028
6018 1024 Aspal AC 60-70 (ex. Shell Drum) Kg 6.0935
6018 1248 Pasir Aspal/ Abu Batu/ Screening M3 0.0015
6018 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.0451
6018 1206 Agregat Pecah Mesin 5-10 mm M3 0.0317

Bekisting (M2)
6019 206 Mandor OH 0.1000
6019 214 Kepala Tukang Kayu OH 0.5000
6019 252 Tukang Kayu OH 5.0000
6019 201 Pekerja OH 2.0000
6019 2201 Paku Kg 4.0000
6019 6033 Kayu Papan Kelas III M3 0.4000
6019 6084 Triplek t= 6 mm Lbr 1.7000

Lean Concrete > K100 tebal 20 cm


6020 201 Pekerja OH 0.0241
6020 202 Tukang OH 0.0040
6020 206 Mandor OH 0.0040
6020 609 Concrete Pan Mixer (Batching Plant) Jam 0.0080
6020 652 Wheel Loader Jam 0.0080
6020 636 Mixer Truck Jam 0.0480
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6020 626 Generator Set Jam 0.0080


6020 1102 Semen PC Kg 80.0000
6020 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.1780
6020 1249 Pasir Beton M3 0.1080
6020 7005 Additive Ltr 0.2100
6020 7007 Air ( Kapal) M3 0.0400
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Dowel Bar D= 25 mm


6021 2021 Dowel Bar D = 25 mm Bh 1.0000

Slab Beton mutu K 350, tebal = 35 cm (M2)


6022 201 Pekerja OH 0.0800
6022 202 Tukang OH 0.0070
6022 206 Mandor OH 0.0072
6022 609 Concrete Pan Mixer (Batching Plant) Jam 0.0240
6022 671 Slip Form Paver Jam 0.0070
6022 652 Wheel Loader Jam 0.0420
6022 651 Water Tanker Jam 0.0420
6022 626 Generator Set Jam 0.0140
6022 636 Mixer Truck Jam 0.0840
6022 1102 Semen PC Kg 262.5000
6022 1205 Agregat Pecah Mesin 20 - 30 mm M3 0.2870
6022 1249 Pasir Beton M3 0.1645
6022 2617 Wire Mesh Kg 8.7500
6022 7005 Additive Ltr 0.3675
6022 7007 Air ( Kapal) M3 0.0700
6022 7142 Joint Sealant M' 1.2250

Prime Coating 2,5 Kg/m2


6023 201 Pekerja OH 0.0018
6023 206 Mandor OH 0.0013
6023 604 Asphalt Sprayer Jam 0.2640
6023 607 Compressor Jam 0.0320
6023 7026 Minyak Tanah Ltr 0.3166
6023 1024 Aspal AC 60-70 (Ex. Shell Drum) Kg 2.4000

Take Coating 1,5 Kg/m2


AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6024 201 Pekerja OH 0.0113


6024 206 Mandor OH 0.0009
6024 604 Asphalt Sprayer Jam 0.2400
6024 607 Compressor Jam 0.0320
6024 1024 Aspal AC 60-70 (Ex. Shell Drum) Kg 1.2000
6024 7026 Minyak Tanah Ltr 0.1166
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengecatan / Marking (m2)


6025 201 Pekerja OH 0.1000
6025 206 Mandor OH 0.0220
6025 640 Sprayer Cat Jam 0.0480
6025 813 Alat Bantu Pengecatan Ls 1.0000
6025 7045 Thinner Ltr 0.2100
6025 7118 Cat Marka Kg 1.0500

Pengukuran (m2)
6026 201 Pekerja OH 0.0050
6026 209 Juru Gambar OH 0.0020
6026 272 Mandor (Pengukuran) OH 0.0140
6026 666 Theodolite Jam 0.0240
6026 667 Waterpass Jam 0.0240
6026 674 Mistar Ukur Jam 0.0480

Begisting Slab Beton (Plat Besi) (m2)


6027 206 Mandor OH 0.0667
6027 202 Tukang OH 0.2000
6027 201 Pekerja OH 0.8000
6027 624 Flatbed Truck 3,5 Ton Jam 0.0386
6027 802 Alat Bantu Ls 1.0000
6027 827 Pabrikasi Ls 1.0000
6027 2012 Besi Plat Kg 0.3240
6027 2214 Besi Siku Kg 2.6790
6027 2999 Material Bantu Bekisting Plat Besi Ls 1.0000

Baja Tulangan Dowel/Tie Bar Support (U-40 Ulir) (Kg)


6028 201 Pekerja OH 0.1050
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6028 202 Tukang OH 0.0350


6028 205 Kepala Tukang OH 0.0350
6028 2020 Dowel and Tie Bar Kg 1.0500
6028 2303 Kawat Beton Kg 0.0200
6028 802 Alat Bantu Ls 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Peralatan Utama CCTV (Alt-1)


6101 9308 Coaxial Cable M' 1.0000
6101 9309 Control Cable 2 Pair M' 1.0000
6101 9349 Supply Cable M' 1.0000
6101 9827 Pan / Tilt Head BH 1.0000
6101 9861 CCD Camera Buah 1.0000
6101 9862 Infra Red Camera Buah 1.0000
6101 9863 Monitor 14" Buah 1.0000
6101 9864 Monitor 9" Buah 1.0000
6101 9866 Remote Control PAN/TILS Buah 1.0000
6101 9867 Sequantial Switcher 10:1 Buah 1.0000
6101 9868 Sequantial Switcher 3:1 Buah 1.0000
6101 9869 Video Distributor Amplifier Buah 1.0000
6101 9870 Zoom Lensa 6:1 Buah 1.0000

Pengadaan Peralatan Utama CCTV (Alt-2)


6102 9308 Coaxial Cable M' 1.0000
6102 9309 Control Cable 2 Pair M' 1.0000
6102 9349 Supply Cable M' 1.0000
6102 9827 Pan / Tilt Head BH 1.0000
6102 9861 CCD Camera Buah 1.0000
6102 9862 Infra Red Camera Buah 1.0000
6102 9863 Monitor 14" Buah 1.0000
6102 9864 Monitor 9" Buah 1.0000
6102 9866 Remote Control PAN/TILS Buah 1.0000
6102 9867 Sequantial Switcher 10:1 Buah 1.0000
6102 9868 Sequantial Switcher 3:1 Buah 1.0000
6102 9870 Zoom Lensa 6:1 Buah 1.0000

Pengadaan Peralatan Walktrough Metal Detector


6103 35124 UPS 1 KVA Tipe On Line Unit 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6103 35127 Walk Trough Metal Detector Unit 1.0000


AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Peralatan Multiview X-Ray Cabin


6104 35117 Peralatan X-Ray (Cabin) Unit 1.0000
6104 35126 UPS 3 KVA Tipe Online Unit 1.0000

Pengadaan Peralatan Multiview X-Ray Bagasi


6105 35116 Peralatan X-Ray Bagasi Unit 1.0000
6105 35128 UPS 5 KVA Tipe Online Unit 1.0000

Pengadaan Peralatan Multiview X-Ray Cargo


6106 35116 Peralatan X-Ray Cargo Unit 1.0000
6106 35129 UPS 10 KVA Tipe Online Unit 1.0000

Pengadaan Peralatan Multiview X-Ray Cabin dengan TIP


6107 35120 Peralatan X-Ray (Cabin) dengan Threat Unit 1.0000
Image Protection (TIP)
6107 35126 UPS 3 KVA Tipe Online Unit 1.0000

Pengadaan Peralatan Multiview X-Ray Bagasi dengan TIP


6108 35119 Peralatan X-Ray (Bagasi) dengan Threat Unit 1.0000
Image Protection (TIP)
6108 35126 UPS 3 KVA Tipe Online Unit 1.0000

Pengadaan Peralatan Multiview X-Ray Cargo dengan TIP


6109 35121 Peralatan X-Ray (Cargo) dengan Threat Unit 1.0000
Image Protection (TIP)
6109 35128 UPS 5 KVA Tipe Online Unit 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pemasangan Remote Control


6112 201 Pekerja OH 1.5000
6112 206 Mandor OH 0.4000
6112 267 Ahli Line Up / Set Up System OH 0.5000
6112 268 Ahli Muda Line / Set Up System OH 1.0000

Pemasangan Unit Camera


6113 201 Pekerja OH 3.2000
6113 206 Mandor OH 0.9000
6113 267 Ahli Line Up / Set Up System OH 2.0000
6113 268 Ahli Muda Line / Set Up System OH 4.0000

Line Up / Set Up System (OH)


6114 267 Ahli Line Up / Set Up System OH 1.0000
6114 268 Ahli Muda Line / Set Up System OH 1.0000
6114 237 Teknisi Line Up / Set Up System OH 1.0000

Uji Coba System (OH)


6115 267 Ahli Line Up / Set Up System OH 1.0000
6115 268 Ahli Muda Line / Set Up System OH 1.0000
6115 237 Teknisi Line Up / Set Up System OH 1.0000

Akomodasi Pemasangan CCTV (OH)


6116 237 Teknisi Line Up / Set Up System OH 1.0000

Pemasangan Peralatan Utama Ke Dalam Console (OH)


AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6117 201 Pekerja OH 3.2000


6117 267 Ahli Line Up / Set Up System OH 1.0500
6117 268 Ahli Muda Line / Set Up System OH 1.0500
6117 237 Teknisi Line Up / Set Up System OH 0.0900

Pemasangan / Instalasi Software


6118 267 Ahli Line Up / Set Up System OH 0.5000
6118 237 Teknisi Line Up / Set Up System OH 1.0800

Pemasangan Bracket
6119 201 Pekerja OH 2.0000
6119 237 Teknisi Line Up / Set Up System OH 1.0000
6119 2303 Kawat Beton Kg 1.0000

Pemasangan Bracket
6120 540 Pemasangan Cable Audio / Video / Antenna Unit 1.0000
6120 541 Pemasangan Cable Power / Penyambungan M 1.0000
dari Panel
6120 9871 Audio Cable BH 1.0000
6120 9872 Power Cable BH 1.0000
6120 9873 Video Cable BH 1.0000
6120 11045 Pengadaan Bahan Instalasi Cable Tray / Btg 1.0000
Protective Cable
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan dan Pemasangan Karpet (M2)


6121 542 Pengadaan / Pemasangan Karpet M2 1.0000

Pengadaan Peralatan FIDS


6122 34002 Perangkat Sofware FIDS Unit 1.0000
6122 34003 Komputer FIDS Set 1.0000
6122 34003 LCD Monitor 17" Unit 3.0000
6122 34005 LCD Monitor 29" Unit 7.0000
6122 9943 Bracket TV BH 7.0000
6122 34006 Printer Dot Matrix Unit 1.0000
6122 34007 Perangkat Jaringan FIDS LOT 1.0000
6122 9308 Coaxial Cable M' 700.0000
6122 32861 Power Cable NYY 3x16 Sqmm/1kV M 150.0000
6122 32401 AC 1 PK Unit 1.0000
6122 35124 UPS 1 KVA Tipe Online Unit 1.0000

Pengadaan Pemasangan Coaxial Cable (m')


6123 201 Pekerja OH 0.3200
6123 206 Mander OH 0.1600
6123 2323 Tyreb (Pengikat Cable) BH 1.0000
6123 9308 Coaxial Cable M' 1.0000

Site Acceptant Tes (Ls/Hr)


6124 267 Ahli Line Up / Set Up System OH 1.0000
6124 268 Ahli Muda Line/ Set Up System OH 1.0000

Site Training Untuk 1 Teknisi dan 1 Operator (Ls/Hr)


AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6125 229 Pengajar OH 1.0000


6125 543 Uang Saku untuk Pelatihan Teknisi/Operator OH 2.0000

Site Training Untuk 2 Teknisi + 2 Operator (Ls/Hr) + 1 Personil Dit. Teknis


6126 229 Pengajar OH 1.0000
6126 543 Uang Saku untuk Pelatihan Teknisi/Operator OH 5.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Peralatan Penunjang FIDS (Set)


6127 9319 Junction Cable Switch BH 1.0000
6127 9923 Meja Operator BH 1.0000
6127 9942 Antena TV BH 1.0000
6127 9943 Bracket TV BH 1.0000
6127 9944 Kursi Operator BH 1.0000
6127 9945 Meja Printer BH 1.0000
Pengadaan Bahan Instalasi Cable Tray / 1.0000
6127 11045 Btg
Protective Cable

Galian Tanah Untuk Gelar Kabel /M3


6128 205 Kepala Tukang OH 0.3714
6128 201 Pekerja OH 0.4000

Urugan Tanah Untuk Gear Kabel /M3


6129 205 Kepala Tukang OH 0.3000
6129 201 Pekerja OH 0.1643

Bata Pengaman Kabel


6130 1214 Bata Merah Press Mesin BH 1.0000
1.0000

Pengelaran Series Kabel, Control, BC dan Power (M)


6131 216 Kepala Tukang Listrik OH 0.0020
6131 206 Mandor OH 0.0010
6131 255 Tukang Listrik OH 0.0050
6131 201 Pekerja OH 0.0230
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pembutan Bak Trafo Size 1 : Runway Light, Apron Dan PAPI

Galian Tanah Biasa Sedalam 1 M(M3) (SNI


6132 90023 M3 1.0000
2835-2008-01)
Menggurug Pasir Urug (M3) (SNI 2835-2008-
6132 90033 M3 0.5000
11)
6132 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 0.0550

Pasang Bekisting Untuk Pondasi (M2) (SNI


6132 90141 M2 0.9000
7394-2008-20)

Pembutan Bak Trafo Size 2: Threshold

Galian Tanah Biasa Sedalam 1 M(M3) (SNI


6133 90023 M3 2.0000
2835-2008-01)
6133 90033 Menggurug Pasir Urug (M3) (SNI 2835-2008-11) M3 1.0000
6133 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 0.2850
Pasang Bekisting Untuk Pondasi (M2) (SNI
6133 90141 M2 2.7900
7394-2008-20)
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pondasi Base Plate Runway, Threshold dan Apron Light/Unit


Galian Tanah Biasa Sedalam 1 M(M3) (SNI
6134 90023 M3 0.7000
2835-2008-01)
Menggurug Pasir Urug (M3) (SNI 2835-2008-
6134 90033 M3 0.1000
11)
Pasang Bekisting Untuk Pondasi (M2) (SNI
6134 90141 M2 1.7000
7394-2008-20)
6134 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 0.1500

Pondasi Taxi Guidance Sign Information/ Unit


Galian Tanah Biasa Sedalam 1 M(M3) (SNI
6135 90023 M3 0.9500
2835-2008-01)

Menggurug Pasir Urug (M3) (SNI 2835-2008-


6135 90033 M3 0.3550
11)
Pasang Bekisting Untuk Pondasi (M2) (SNI
6135 90141 M2 2.4000
7394-2008-20)
6135 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 0.2500
Galian Tanah Biasa Sedalam 1 M(M3) (SNI
6136 90023 M3 1.8550
2835-2008-01)
Menggurug Pasir Urug (M3) (SNI 2835-2008-
6136 90033 M3 0.7650
11)
Pasang Bekisting Untuk Pondasi (M2) (SNI
6136 90141 M2 4.4800
7394-2008-20)
6136 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 0.6200

Pondasi Runway Threshold Identification Light (RTIL)/ Unit

Galian Tanah Biasa Sedalam 1 M(M3) (SNI


6137 90023 M3 0.6250
2835-2008-01)

Menggurug Pasir Urug (M3) (SNI 2835-2008-


6137 90033 M3 0.2550
11)

Pasang Bekisting Untuk Pondasi (M2) (SNI


6137 90141 M2 2.4000
7394-2008-20)
6137 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 0.2500
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pondasi Wind Direction Indicator (WDI) /unit

Galian Tanah Biasa Sedalam 1 M(M3) (SNI


6138 90023 M3 2.7000
2835-2008-01)
Menggurug Pasir Urug (M3) (SNI 2835-2008-
6138 90033 M3 1.2000
11)
Pasang Bekisting Untuk Pondasi (M2) (SNI
6138 90141 M2 15.0000
7394-2008-20)
6138 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 3.2500
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pondasi PAPI / unit

Galian Tanah Biasa Sedalam 1 M(M3) (SNI M3 1.2000


6139 90023
2835-2008-01)
Menggurug Pasir Urug (M3) (SNI 2835-2008-
6139 90033 M3 0.5000
11)
Pasang Bekisting Untuk Pondasi (M2) (SNI
6139 90141 M2 3.5000
7394-2008-20)
6139 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 0.4000

Pondasi PAPI 3x30 Meter/ Unit

Galian Tanah Biasa Sedalam 1 M(M3) (SNI


6140 90023 M3 3.5600
2835-2008-01)

Menggurug Pasir Urug (M3) (SNI 2835-2008-


6140 90033 M3 1.2250
11)
Pasang Bekisting Untuk Pondasi (M2) (SNI
6140 90141 M2 19.2000
7394-2008-20)
6140 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 3.2500

Pondasi Ground Check PAPI

Galian Tanah Biasa Sedalam 1 M(M3) (SNI


6141 90023 M3 0.2500
2835-2008-01)

Menggurug Pasir Urug (M3) (SNI 2835-2008-


6141 90033 M3 0.0080
11)

Pasang Bekisting Untuk Pondasi (M2) (SNI


6141 90141 M2 0.9000
7394-2008-20)
6141 90193 Beton Campuran 1Pc : 2 Ps : 3 Kr(M3) M3 0.0550

Pengukuran Tempat-Tempat Kedudukan Runaway Light, PAPI dengan Theodolite


6142 210 Juru Ukur OH 8.0000
6142 209 Juru Gambar OH 4.0000
6142 239 Tenaga Ahli OH 6.0000
6142 666 Theodolite Jam 8.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengukuran Tempat-Tempat Kedudukan RTIL


6143 209 Juru Gambar OH 2.0000
6143 210 Juru Ukur OH 5.0000
6143 239 Tenaga Ahli OH 0.2000
6143 817 Alat Bantu Pengukuran Ls 1.0000

Pembuatan gambar design lokasi PAPI


6144 209 Juru Gambar OH 1.0000
6144 210 Juru Ukur OH 1.0000
6144 239 Tenaga Ahli OH 0.5000

Pemasangan Base Plate Anchor Stake PAPI, RTIL Pada Pondasi/ Pcs
6145 201 pekerja OH 1.5000
6145 206 Mandor OH 0.2000
6145 238 Teknisi OH 0.8500

Pemasangan dan penyetelan Runway Light, TXA & TEX, Turning Area dan RTIL/unit
6146 666 Theodolite Jam 5.0000
6146 9946 Patok Lot 0.2000
6146 210 Juru Ukur OH 2.0000

Pemasangan Penyambung dan Instalasi Konektor Kit dan Two Pole Plug
6147 201 pekerja OH 1.5000
6147 206 Mandor OH 0.2000
6147 238 Teknisi OH 0.8500
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pemasangan Dan Penyetelan Montage Box PAPI/ Unit


6148 201 pekerja OH 1.5000
6148 206 Mandor OH 0.2000
6148 238 Teknisi OH 0.8500

Pemasangan dan Instalasi Isolating Transformer/unit


6149 201 pekerja OH 1.5000
6149 206 Mandor OH 0.2000
6149 238 Teknisi OH 0.8500
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

pekerjaan Pemasangan, Penyambungan Dan Instalasi Series Kabel, Power Kabel dan
6150 201 pekerja OH 0.0230
6150 239 Tenaga Ahli OH 0.0010
6150 255 Tukang Listrik OH 0.0050
6150 216 Kepala Tukang Listrik OH 0.0040

Instalasi CCR termasuk instalasi kabel power dari MVSB ke CCR dan kabel control da
6151 263 Tenaga Ahli Khusus OH 10.0000
6151 239 Tenaga Ahli OH 20.0000
6151 255 Tukang Listrik OH 20.0000
6151 262 Pembantu Tukang Listrik OH 20.0000
6151 201 pekerja OH 10.0000
6151 826 Alat Bantu Instalasi Kabel Power Lot 1.0000

Instalasi WDI / Rotating Beacon


6152 206 Mandor OH 0.5500
6152 238 Teknisi OH 2.0000
6152 826 Alat Bantu Instalasi Kabel Power Lot 1.0000
6152 201 pekerja OH 3.5100

Instalasi Rotating Beacon


6153 201 Pekerja OH 3.5100
6153 206 Mandor OH 0.5500
6153 238 Teknisi OH 2.0000
6153 826 Alat Bantu Instalasi Kabel Power Lot 1.0000

Instalasi WDI
6154 201 Pekerja OH 3.5100
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6154 206 Mandor OH 0.5500


6154 238 Teknisi OH 2.0000
6154 826 Alat Bantu Instalasi Kabel Power Lot 1.0000

Instalasi Remot Control Desk


6155 209 Juru Gambar OH 4.0000
6155 238 Teknisi OH 10.0000
6155 239 Tenaga Ahli OH 10.0000
6155 206 Mandor OH 10.0000
6155 206 Alat Bantu Pemasangan Remote Control Ls 1.0000
Desk

Pemasangan Taxiway Guidance Sign


6156 206 Mandor OH 1.0000
6156 255 Tukang Listrik OH 3.0000
6156 262 Pembantu Tukang Listrik OH 2.5000
6156 201 pekerja OH 5.0000
6156 216 Kepala Tukang Listrik OH 2.5000

Bimbingan Teknis Peralatan


6157 238 Teknisi OH 10.0000
6157 268 Ahli Muda Line/Set Up System OH 6.0000
6157 267 Ahli Line Up/ Set Up System OH 3.0000
6157 270 Tenaga Ahli Pusat (Termasuk OH 1.0000
Tiket+hotel+Akomodasi) (Disesuaikan
6157 271 Tenaga Agen (Termasuk Tiket) (Disesuaikan OH 1.0000
Dengan Lokasi Kegiatan)
Dengan Lokasi Kegiatan)

Evaluasi Teknis Peralatan


6158 238 Teknisi OH 10.0000
6158 268 Ahli Muda Line/Set Up System OH 6.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6158 267 Ahli Line Up/ Set Up System OH 3.0000


6158 270 Tenaga Ahli Pusat (Termasuk OH 1.0000
Tiket+hotel+Akomodasi) (Disesuaikan
6158 271 Tenaga Agen (Termasuk Tiket) (Disesuaikan OH 1.0000
Dengan Lokasi Kegiatan)
Dengan Lokasi Kegiatan)

Drilling Taxiway dan Jalan Untuk Jalur Kabel Pada Pipa


6182 547 Drilling Taxiway dan Jalan Untuk Jalur Kabel d M' 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Runway Edge Light Type 1 (R/W.2500x45 PA)


6201 32802 High Intensity Elevated Light Complete Unit 42.0000
clear150 W;6.6a
6201 32803 High Intensity Elevated Light Complete Unit 20.0000
clear/yelow 150 W;6.6a
6201 32804 High Intensity Elevated Light Complete Unit 2.0000
yelow 150 W;6.6a
6201 32831 Isolating Transformer 150 W; 6.6/6.6 A. Pcs 82.0000
6201 32849 Connector Kit Terdiri Dari FAA- Plug dan Set 82.0000
socket single pole.
6201 32850 two pole plug Connector kit. pcs 82.0000
6201 32856 Series cable FL2XCY 1x6 Sqmm. 3/6 kV M 14000.0000
6201 32852 Base Plate Pcs 82.0000
6201 32861 Power cable NYY 3x16 Sqmm/1kv M 20.0000
6201 32860 Control Cable 2x10x0.8 sqmm. 1kv M 20.0000
6201 32840 CCR 20 KVA/KW Pcs 2.0000

Pengadaan Runway Edge Light Type 1 (R/W 1.850 x 30) taxi LED
6205 32802 High intensity Elevated Light Complete clear Unit 20.0000
150 W;6.6A.
6205 32803 High intensity Elevated Light Complete Unit 20.0000
clear/yelow 150 W;6.6A.
6205 32804 High intensity Elevated Light Complete Unit 20.0000
yelow/clear 150 W;6.6A.
6205 32831 Isolating transformer 150 W;6.6/6.6 A. Pcs 60.0000
6205 32849 Connector kit terdiri dari FAA-plug dan Set 60.0000
socket single pole.
6205 32850 Two pole plug connector kit. Pcs 60.0000
6205 32856 Series Cable FL2XCY 1x6 Sqmm. 3/6 kV. M 12000.0000
6205 32852 Base plate. Pcs 60.0000
6205 32861 Power cable NYY 3x16 Sqmm/1kV M 20.0000
6205 32860 Control cable 2 x 10 x 0.8 sqmm. 1 kv M 20.0000
6205 32839 CCR 15 KVA/KW Pcs 2.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Runway Edge Light Type 1 (R/W 1.850 x 30)


6206 32802 High intensity Elevated Light Complete clear Unit 20.0000
150 W;6.6A.
6206 32803 High intensity Elevated Light Complete Unit 20.0000
clear/yelow 150 W;6.6A.
6206 32804 High intensity Elevated Light Complete Unit 20.0000
yelow/clear 150 W;6.6A.
6206 32831 Isolating transformer 150 W;6.6/6.6 A. Pcs 60.0000
6206 32849 Connector kit terdiri dari FAA-plug dan Set 60.0000
socket single pole.
6206 32850 Two pole plug connector kit. Pcs 60.0000
6206 32856 Series Cable FL2XCY 1x6 Sqmm. 3/6 kV. M 12000.0000
6206 32852 Base plate. Pcs 60.0000
6206 32861 Power cable NYY 3x16 Sqmm/1kV M 20.0000
6206 32860 Control cable 2 x 10 x 0.8 sqmm. 1 kv M 20.0000
6206 32839 CCR 15 KVA/KW Pcs 2.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Runway Edge Light Type 1 (R/W 1.400 x 30)


6207 32802 High intensity Elevated Light Complete clear Unit 26.0000
150 W;6.6A.
6207 32803 High intensity Elevated Light Complete Unit 10.0000
clear/yelow 150 W;6.6A.
6207 32804 High intensity Elevated Light Complete Unit 10.0000
yelow/clear 150 W;6.6A.
6207 32831 Isolating transformer 150 W;6.6/6.6 A. Pcs 46.0000
6207 32849 Connector kit terdiri dari FAA-plug dan Set 46.0000
socket single pole.
6207 32850 Two pole plug connector kit. Pcs 46.0000
6207 32856 Series Cable FL2XCY 1x6 Sqmm. 3/6 kV. M 10000.0000
6207 32852 Base plate. Pcs 46.0000
6207 32861 Power cable NYY 3x16 Sqmm/1kV M 20.0000
6207 32860 Control cable 2 x 10 x 0.8 sqmm. 1 kv M 20.0000
6207 32839 CCR 15 KVA/KW Pcs 2.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Runway Edge Light Type 1 (R/W 1.400 x 30) taxi LED
6208 32802 High intensity Elevated Light Complete clear Unit 26.0000
150 W;6.6A.
6208 32803 High intensity Elevated Light Complete Unit 10.0000
clear/yelow 150 W;6.6A.
6208 32804 High intensity Elevated Light Complete Unit 10.0000
yelow/clear 150 W;6.6A.
6208 32831 Isolating transformer 150 W;6.6/6.6 A. Pcs 46.0000
6208 32849 Connector kit terdiri dari FAA-plug dan Set 46.0000
socket single pole.
6208 32850 Two pole plug connector kit. Pcs 46.0000
6208 32856 Series Cable FL2XCY 1x6 Sqmm. 3/6 kV. M 10000.0000
6208 32852 Base plate. Pcs 46.0000
6208 32861 Power cable NYY 3x16 Sqmm/1kV M 20.0000
6208 32860 Control cable 2 x 10 x 0.8 sqmm. 1 kv M 20.0000
6208 32839 CCR 15 KVA/KW Pcs 2.0000

Pengadaan Taxiway Edge Light dan Apron Light (LED)


6209 32815 Omnidirectional Elevated Light Complete Unit 18.0000
Blue LED 8-11W;6.6A.
6209 32816 Omnidirectional Elevated Light Complete Unit 6.0000
Red LED 8-11W;6.6A.
6209 32828 Isolating transformer 30/45 W;6.6/6.6 A. Pcs 24.0000
6209 32849 Connector kit terdiri dari FAA-plug dan Set 24.0000
socket single pole.
6209 32850 Two pole plug connector kit. Pcs 24.0000
6209 32856 Series Cable FL2XCY 1x6 Sqmm. 3/6 kV. M 3000.0000
6209 32852 Base plate. Pcs 24.0000
6209 32861 Power cable NYY 3x16 Sqmm/1kV M 20.0000
6209 32860 Control cable 2 x 10 x 0.8 sqmm. 1 kv M 20.0000
6209 32837 CCR 7.5 KVA/KW Pcs 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Taxiway Edge Light dan Apron Light (Blub)


6210 32813 Omnidirectional Elevated Light Complete Unit 18.0000
Blue 30/45W;6.6A.
6210 32814 Omnidirectional Elevated Light Complete Unit 6.0000
Red 30/45W;6.6A.
6210 32829 Isolating transformer 30/45 W;6.6/6.6 A. Pcs 24.0000
6210 32849 Connector kit terdiri dari FAA-plug dan Set 24.0000
socket single pole.
6210 32850 Two pole plug connector kit. Pcs 24.0000
6210 32856 Series Cable FL2XCY 1x6 Sqmm. 3/6 kV. M 3000.0000
6210 32852 Base plate. Pcs 24.0000
6210 32861 Power cable NYY 3x16 Sqmm/1kV M 20.0000
6210 32860 Control cable 2 x 10 x 0.8 sqmm. 1 kv M 20.0000
6210 32837 CCR 7.5 KVA/KW Pcs 1.0000

Pengadaan Threshold Light (R/W 2500x45 PA dan R/W 1850x45 PA)


6211 32809 High Intensity Inset Threshold light Unit 3.0000
complete. Green/red 3x105 W;6.6 A
6211 32810 High Intensity Inset Threshold light Unit 4.0000
complete. Green/blank 2x105 W;6.6 A
6211 32831 Isolating transformer 150 W;6.6/6.6 A. Pcs 54.0000
6211 32833 Isolating transformer 300 W;6.6/6.6 A. Pcs 7.0000
6211 32849 Connector kit terdiri dari FAA-plug dan Set 8.0000
socket single pole.
6211 32850 Two pole plug connector kit. Pcs 61.0000
6211 32852 Base plate. Pcs 54.0000
6211 32808 High Intesity Undirectional threshold light Unit 10.0000
complete red 150 W;6.6A
6211 32807 High Intesity Undirectional threshold light Unit 28.0000
complete green 150 W;6.6A
6211 32874 High Intesity Undirectional wing bar Unit 16.0000
threshold light complete green 150 W;6.6A
6211 32851 Colfor 200 + hardener + groot/primer Pcs 7.0000
6211 32858 Pipa PVC 5/8" pelindung kabel NYHY 2 x 4 Pcs 54.0000
Sqmm
6211 32383 Secondary Cable NYHY 2 x 4 Sqmm M 600.0000

Pengadaan Threshold Light (R/W 1850x30)


6212 32831 Isolating transformer 150 W;6.6/6.6 A. Pcs 44.0000
6212 32849 Connector kit terdiri dari FAA-plug dan Set 8.0000
socket single pole.
6212 32850 Two pole plug connector kit. Pcs 44.0000
6212 32852 Base plate. Pcs 44.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6212 32808 High Intesity Undirectional threshold light Unit 16.0000


complete red 150 W;6.6A
6212 32807 High Intesity Undirectional threshold light Unit 28.0000
complete green 150 W;6.6A
6212 32858 Pipa PVC 5/8" pelindung kabel NYHY 2 x 4 Pcs 44.0000
Sqmm
6212 32383 Secondary Cable NYHY 2 x 4 Sqmm M 600.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Threshold Light (R/W 1850x45 NPA)


6213 32383 Secondary Cable NYHY 2 x 4 Sqmm M 500.0000
6213 32807 High Intesity Undirectional threshold light Unit 20.0000
complete green 150 W;6.6A
6213 32808 High Intesity Undirectional threshold light Unit 12.0000
complete red 150 W;6.6A
6213 32831 Isolating transformer 150 W;6.6/6.6 A. Pcs 32.0000
6213 32849 Connector kit terdiri dari FAA-plug dan Set 8.0000
socket single pole.
6213 32850 Two pole plug connector kit. Pcs 32.0000
6213 32852 Base plate. Pcs 32.0000
6213 32858 Pipa PVC 5/8" pelindung kabel NYHY 2 x 4 Pcs 32.0000
Sqmm

Pengadaan Turning Area Light (R/W 1850x30)


6214 32875 Omnidirectional Elevated Light Complete Unit 10.0000
Blue 100W;6.6A.
6214 32830 Isolating transformer 100 W;6.6/6.6 A. Pcs 10.0000
6214 32849 Connector kit terdiri dari FAA-plug dan Set 10.0000
socket single pole.
6214 32850 Two pole plug connector kit. Pcs 10.0000
6214 32852 Base plate. Pcs 10.0000

Pengadaan WDI (RW 2500m')


6215 32846 Wind Directional Indicator (WDI) Pcs 1.0000
6215 32384 Power Cable NYFGBY 3 x 16 Sqmm/1 kV M' 2500.0000

Pengadaan WDI (RW 1850m')


6216 32846 Wind Directional Indicator (WDI) Pcs 1.0000
6216 32384 Power Cable NYFGBY 3 x 16 Sqmm/1 kV M' 1300.0000

Pengadaan WDI (RW 1400m')


6217 32846 Wind Directional Indicator (WDI) Pcs 1.0000
6217 32384 Power Cable NYFGBY 3 x 16 Sqmm/1 kV M' 1000.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Rotating Beacon


6218 32847 Rotating Beacon Pcs 1.0000
6218 32861 Power Cable NYY 3x16 Sqmm/1 kV M' 100.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Runway Thershold Identification Light (RTIL)


6219 32821 Runway Thershold Identification Light (RTIL) Unit 2.0000
6219 32384 Power Cable NYFGBY 3 x 16 Sqmm/1 kV M' 1500.0000
6219 32860 Control Cable 2 x 10 x 0,8 Sqmm. 1 kV M 100.0000
6219 32872 Flexsibel Conduit Set 30.0000

Pengadaan PAPI 1 (satu) Ujung 1 (satu) Sisi


6220 32822 Precission Approach Path Indicator (PAPI) Unit 4.0000
6220 32832 Isolating Transformer 200 W; 6.6/6.6 A. Pcs 8.0000
6220 32856 Series Cable FL2XCY 1x6 Sqmm. 3/6 kV M 3000.0000
6220 32861 Power Cable NYY 3x16 Sqmm/1 kV M 20.0000
6220 32860 Control Cable 2 x 10 x 0,8 Sqmm. 1 kV M 20.0000
6220 32849 Connector kit terdiri dari FAA-plug dan Set 4.0000
Socket Single Pole
6220 32850 Two Pole Plug Connector Kit Pcs 8.0000
6220 32859 Joint Sleeve FL2XCY 1x6 Sqmm 3/6 kV Set 3.0000
6220 32824 Clinometer Unit 1.0000
6220 32836 CCR 4 KVA/KW berikut selector switch Pcs 1.0000

Pengadaan PAPI 2 (dua) Ujung 1 (satu) Sisi


6220 32822 Precission Approach Path Indicator (PAPI) Unit 8.0000
6220 32832 Isolating Transformer 200 W; 6.6/6.6 A. Pcs 16.0000
6220 32856 Series Cable FL2XCY 1x6 Sqmm. 3/6 kV M 7000.0000
6220 32861 Power Cable NYY 3x16 Sqmm/1 kV M 20.0000
6220 32860 Control Cable 2 x 10 x 0,8 Sqmm. 1 kV M 20.0000
6220 32849 Connector kit terdiri dari FAA-plug dan Set 8.0000
Socket Single Pole
6220 32850 Two Pole Plug Connector Kit Pcs 16.0000
6220 32859 Joint Sleeve FL2XCY 1x6 Sqmm 3/6 kV Set 7.0000
6220 32824 Clinometer Unit 1.0000
6220 32836 CCR 4 KVA/KW berikut selector switch Pcs 2.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Medium Approach Light System (MALS) 420 M


6222 32801 Unidirectional Approach Light Complete Unit 45.0000
Clear 150 W;6.6 A.
6222 32831 Isolating Transformer 150 W; 6.6/6.6 A. Pcs 45.0000
6222 32849 Connector kit terdiri dari FAA-plug dan Set 18.0000
Socket Single Pole
6222 82850 Two Pole Plug Connector Kit Pcs 45.0000
6222 32856 Series Cable FL2XCY 1x6 Sqmm 3/6 kV M 9000.0000
6222 32859 Joint Sleeve FL2XCY 1x6 Sqmm 3/6 kV Set 9.0000
6222 32861 Power Cable NYY 3x16 Sqmm/1 kV M 20.0000
6222 32857 Secondary Cable NYYHY 2 x 4 Sqmm M 500.0000
6222 32860 Control Cable 2 x 10 x 0,8 sqmm. 1 kV M 20.0000
6222 32953 Tiang Konstruksi MALS (Infrangible) Set 8.0000
6222 32852 Base Plate Pcs 5.0000
6222 32838 CCR 10 KVA/KW Pcs 2.0000

Pengadaan Medium Approach Light System (PALS) 900 M


6223 32801 Unidirectional Approach Light Complete Unit 166.0000
Clear 150 W;6.6 A.
6223 32831 Isolating Transformer 150 W; 6.6/6.6 A. Pcs 166.0000
6223 32849 Connector kit terdiri dari FAA-plug dan Set 34.0000
Socket Single Pole
6223 82850 Two Pole Plug Connector Kit Pcs 166.0000
6223 32856 Series Cable FL2XCY 1x6 Sqmm 3/6 kV M 12000.0000
6223 32859 Joint Sleeve FL2XCY 1x6 Sqmm 3/6 kV Set 10.0000
6223 32861 Power Cable NYY 3x16 Sqmm/1 kV M 20.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6223 32857 Secondary Cable NYYHY 2 x 4 Sqmm M 800.0000


6223 32860 Control Cable 2 x 10 x 0,8 sqmm. 1 kV M 20.0000
6223 32953 Tiang Konstruksi PALS wing bar Set 2.0000
6223 32955 Tiang Konstruksi PALS Set 18.0000
6223 32956 Tiang Konstruksi PALS (Infrangible) Set 10.0000
6223 32852 Base Plate Pcs 10.0000
6223 32841 CCR 25 KVA/KW Pcs 2.0000

Pengadaan Precission Approach Light System (Inset Light)


6224 32809 High Intensity Inset Threshold Light Unit 10.0000
Complete. Green/Red 3x105 W;6.6 A
6224 32801 Unidirectional Approach Light Complete Unit 156.0000
Clear 150 W;6.6A.
6224 32833 Isolating Transformer 300 W; 6.6/6.6A. Pcs 10.0000
6224 32831 Isolating Transformer 150 W; 6.6/6.6A. Pcs 156.0000
6224 32849 Connector kit terdiri dari FAA-plug dan Set 34.0000
Socket Single Pole
6224 32850 Two Pole Plug Connector Kit Pcs 166.0000
6224 32856 Series Cable FL2XCY 1x6 Sqmm 3/6 kV M 12000.0000
6224 32859 Joint Sleeve FL2XCY 1x6 Sqmm 3/6 kV Set 10.0000
6224 32861 Power Cable NYY 3x16 Sqmm/1 kV M 20.0000
6224 32851 Colfor 200 + Hardener + Groot/Primer Pcs 10.0000
6224 32857 Secondary Cable NYYHY 2 x 4 Sqmm M 800.0000
6224 32860 Control Cable 2 x 10 x 0,8 sqmm. 1 kV M 20.0000
6224 32954 Tiang Konstruksi PALS wing bar Set 2.0000
6224 32955 Tiang Konstruksi PALS Set 23.0000
6224 32956 Tiang Konstruksi PALS (Infrangible) Set 5.0000
6224 32852 Base Plate Pcs 5.0000
6224 32841 CCR 25 KVA/KW Pcs 2.0000

Pengadaan Power dan Control System AFL


6225 32825 Remote Control Desk Unit 1.0000
6225 32374 NYFGBY 4 x 35 mm2 M 50.0000
6225 32385 Cable Control 60 x 2 x 0,8 Sqmm M' 300.0000
6225 32870 Marshalling Cabinet Unit 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6225 32302 Panel Medium Voltage Switch Board (MVSB) Unit 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Power dan Control System PAPI


6226 32032 Panel Medium Voltage Switch Board (MVSB) Unit 1.0000
6226 32374 NYFGBY 4 x 35 mm2 M 50.0000

Pengadaan Grounding untuk AFL (RW 2500m')


6227 32862 BC 50 M 6500.0000
6227 32863 BC 16 M 900.0000
6227 32864 Kabel Grounding 6 Sqmm M 400.0000
6227 32386 Copper Rod Pcs 22.0000

Pengadaan Grounding untuk AFL (RW 1850m')


6228 32862 BC 50 M 5500.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6228 32863 BC 16 M 900.0000


6228 32864 Kabel Grounding 6 Sqmm M 300.0000
6228 32386 Copper Rod Pcs 16.0000

Pengadaan Grounding untuk AFL (RW 1400m')


6229 32862 BC 50 M 5000.0000
6229 32863 BC 16 M 600.0000
6229 32864 Kabel Grounding 6 Sqmm M 200.0000
6229 32386 Copper Rod Pcs 14.0000
6229 32862 BC 50 M 3000.0000
6229 32863 BC 16 M 20.0000
6229 32864 Kabel Grounding 6 Sqmm M 20.0000
6229 32386 Copper Rod Pcs 8.0000

Pengadaan Grounding untuk REH dan TXE


6230 32862 BC 50 M 1500.0000
6230 32863 BC 16 M 20.0000
6230 32864 Kabel Grounding 6 Sqmm M 20.0000
6230 32386 Copper Rod Pcs 6.0000

Pengadaan Grounding untuk PAPI


6231 32862 BC 50 M 3000.0000
6231 32863 BC 16 M 20.0000
6231 32864 Kabel Grounding 6 Sqmm M 20.0000
6231 32386 Copper Rod Pcs 8.0000

Pengadaan Grounding untuk MALS


6232 32862 BC 50 M 2000.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6232 32863 BC 16 M 500.0000


6232 32864 Kabel Grounding 6 Sqmm M 50.0000
6232 32386 Copper Rod Pcs 4.0000
6232 32862 BC 50 M 2500.0000
6232 32863 BC 16 M 800.0000
6232 32864 Kabel Grounding 6 Sqmm M 100.0000
6232 32386 Copper Rod Pcs 8.0000

Pengadaan Grounding Untuk PALS (Insert Light)


6234 32862 BC 50 M 2500.0000
6234 32863 BC 15 M 600.0000
6234 32864 Kabel Grounding 6 sqrmm M 100.0000
6234 32386 Copper Rod Psc 8.0000

Pengadan Squence Flashing Light


6235 32817 Flash Light Unidirectional (SFL) Unit 30.0000
6235 32819 Individual Control Unit Lengkap (UCC) (SFL) Unit 30.0000
6235 32820 Master Control Unit (UCC) (SFL) Unit 1.0000
6235 32372 NYFGBY 4 x 16 mm² M 2500.0000
6235 32871 Control Kabel 12 x 1,5 Sqmm/ 1 kV Pcs 2500.0000
6235 32873 Juction Box Berikut Flexibel Condiut Set 30.0000
6235 32957 Tiang Tunggal SQFL Set 30.0000

Pengadaan Sequence Flashing Light (Insert Light)


6236 32818 Flash Light Insert (SFL) Unit 1.0000
6236 32817 Flash Light Unidirectional (SFL) Unit 29.0000
6236 32819 Individual Control Unit Lengkap (UCC) (SFL) Unit 29.0000
6236 32820 Master Control Unit (UCC) (SFL) Unit 1.0000
6236 32372 NYFGBY 4 x 16 mm² m 2500.0000
6236 32871 Control Kabel 12 x 1,5 Sqmm/ 1 kV Pcs 2500.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6236 32873 Juction Box Berikut Flexibel Condiut Set 30.0000


6236 32957 Tiang Tunggal SQFL Set 29.0000

Pemasangan Garbarata Unit


6301 264 Tenaga Ahli Garbarata OH 20.0000
6301 265 Teknisi Garbarata OH 24.0000
6301 266 Pembantu Teknisi Garbarata OH 24.0000
6301 740 Trailer Hari 3.0000
6301 744 Truk Hari 1.0000
6301 738 Crane Telescopic 45 Ton Jam 48.0000
6301 739 Forklift Hari 2.0000
6301 741 Genset Mesin, Las, Dll Set 1.0000
6301 742 Toolkit Untuk Pemasangan Garbarata Set 1.0000
6301 743 Scafolding, Tangga, Lampu Penerangan, Dll Set 1.0000

Pemasangan Fix Walkway (20 m)


6302 264 Pemasangan Fix Walkway (20 Meter) OH 2.0000
6302 265 Teknisi Garbarata OH 4.0000
6302 266 Pembantu Teknisi Garbarata OH 6.0000
6302 740 Trailer Hari 1.0000
6302 744 Truk Hari 1.0000
6302 738 Crane Telescopic 45 Ton Jam 1.0000
6302 739 Forklift Hari 1.0000
6302 741 Genset, Mesin Las, Dll Set 1.0000
6302 742 Toolkit Untuk Pemasangan Garbarata Set 1.0000

6302 743 Scafolding, Tangga, Lampu Penerangan, Dll Set 1.0000

Pemasangan Garbarata 2 Tunnel


6303 32601 Avio Bridge (Garbarata) 2 Tunnel Set 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6303 32603 Material Fix Walkway, Type Single Glass Set 1.0000
Wall, Panjang 20 m dan Lebar 2,1 m

Pemasangan Garbarata 3 Tunnel


6304 32602 Avio Bridge (Garbarata) 3 Tunnel Set 1.0000
6304 32603 Material Fix Walkway, Type Single Glass Set 1.0000
Wall, Panjang 20 m dan Lebar 2,1 m

Pengadaan Peralatan Utama PIDS


6159 34018 Dual View PTZ Thermal Camera Unit 1.0000
6159 34019 Infrared (IR) Unit 1.0000
6159 34021 LCD Monitor 42" Unit 1.0000
6159 34022 Storage 2U, 19" Rackmount Chasis 3 TB Unit 1.0000
6159 34023 Rack Mount Unit 1.0000
6159 34024 Gigabit Switch 24 Port Unit 1.0000
6159 34025 Komputer All In One Unit 1.0000
6159 34026 Meja + Kursi Unit 1.0000
6159 34017 Handy Talky (HT) Unit 1.0000
6159 35126 UPS 3 KVA Tipe One Line Unit 1.0000

Pengadaan Peralatan Penunjang PIDS


6160 34030 Fiber Optic Cable M 1.0000
6160 34031 Enclosure DataHub High Backbone Pcs 1.0000
6160 34032 Folding Pole for Camera Pcs 1.0000
6160 34033 Standalone Surge Protector Pcs 1.0000
6160 34034 Plastic Counduit Pcs 1.0000
6160 34035 Plastic Cable Pull Boxes Pcs 1.0000

Pengadaan Peralatan Utama CCTV Closed Circuit Television (CCT)


6161 34036 IP Speed Dome + Bracket Unit 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6161 34037 HD IP Speed Dome + Bracket Unit 1.0000


6161 34038 Day/Night Infrared IP Camera Unit 1.0000
6161 34039 Day/Night IP Camera Full HD Unit 1.0000
6161 34040 Varifocal Lense Unit 1.0000
6161 34041 Power Supply Camera POE Unit 1.0000
6161 34042 Multiplexer Digital Recording 8 Channel Unit 1.0000
(DVD 8 Channel)
Multiplexer Digital Recording 16 Channel 1.0000
6161 34043 Unit
(DVD 16 Channel)
6161 34044 Outdoor Housing Camera Unit 1.0000
6161 34045 Mount Ceiling Feed Bracket Unit 1.0000
6161 34046 Decoder Video Streaming 8 Channel Unit 1.0000
6161 34047 Pan/Tilt Drive Unit Unit 1.0000
6161 34048 Pan/Tilt & Zoom Lens Controller Unit 1.0000

8 Ch Standalone Hybrid Recorder (8 Analog 1.0000


6161 34049 Unit
+ 8 IP)
8 Ch Five Independent Multi Streaming 3G 1.0000
6161 34050 Unit
Server
6161 34051 Video Client Software 8 Channel Unit 1.0000
6161 34052 Video Client Software 16 Channel Unit 1.0000
6161 34027 Decoder Video Streaming 16 Channel Unit 1.0000

16 Ch standalone Hybrid Recorder (16 1.0000


6161 34053 Unit
Analog + 16 IP)

16 Ch Five Independent Multi Streaming 3G 1.0000


6161 34054 Unit
Server

Pengadaan Peralatan Pendukung CCTV Closed Circuit Television (CCT)


6162 34025 Komputer All In One Unit 1.0000
6162 34021 LCD Monitor 42" Unit 1.0000
6162 34055 Mounting Rack Double Door 19"/12U Unit 1.0000
6162 34026 Meja + Kursi Unit 1.0000
6162 35125 UPS 2 KVA Tipe One Line Unit 1.0000
6162 34056 Gigabit Switch 8 Port Unit 1.0000
6162 34024 Gigabit Switch 24 Port Unit 1.0000
6162 9362 Cable Coaxial Belden M 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

6162 9363 Cable Data M 1.0000


6162 9874 Cable Power 2 x 1,5 M 1.0000
6162 9875 Box Panel CCTV Buah 1.0000
6162 9876 Pipa Plastik 1/2" Buah 1.0000
6162 9877 Cable Duct Buah 1.0000
6162 9878 Klem Pipa Buah 1.0000

Pengadaan Peralatan Utama Access Door


6163 9947 Door Temper Glass Unit 1.0000
6163 9948 Access Door Reader Control Unit 1.0000
6163 9949 Access Modular Controller Unit 1.0000
6163 9950 Electro Magnetic Lock Unit 1.0000
6163 35125 UPS 2 KVA Tipe On Line Unit 1.0000
6163 9951 Access Card Unit 1.0000
6163 9952 PC Access Door Recorder Unit 1.0000
6163 9953 Management Sotware Access Unit 1.0000

Pengadaan PeralatanPendukung Access Door


6164 9954 Door Closer Handle Unit 1.0000
6164 9955 Push Button Exit Unit 1.0000
6164 9956 Braket Temper Glass Unit 1.0000
6164 9957 Floor Hinge Unit 1.0000
6164 9958 Door Sensor Unit 1.0000

Pengadaan Walk Through Metal Detector (WTMD)


6165 35127 Walk Trough Metal Detector (WTMD) Unit 1.0000
6165 35124 UPS 1 KVA Tipe On Line Unit 1.0000
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.

Pengadaan Hand Held Metal Detector (HHMD)


6165 34001 Hand Held Metal Detector Unit 1.0000

Pengadaan Explosive Detector


6167 34016 Explosive Detector Unit 1.0000

Pengadaan Consumables Part


6168 34028 Consumables Part Set 1.0000

Pengadaan Liquid Detector


6169 34029 Liquid Detector Set 1.0000

Clearing dan Grubbing (M2)


6029 201 Pekerja OH 0.0589
6029 206 Mandor OH 0.0132
6029 606 Bulldozer Jam 0.0098
6029 621 Dump Truck 5 Ton Jam 0.0080
6029 623 Excavator Jam 0.0138

Stripping Top Soil t = 20 cm (M2)


6030 201 Pekerja OH 0.0045
6030 206 Mandor OH 0.0330
6030 606 Bulldozer Jam 0.0416
6030 621 Dump Truck 5 Ton Jam 0.0090
6030 623 Excavator Jam 0.0107
AnisID ResID Nama Bahan/Alat/Upah Satuan Koef.
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

PEKERJAAN BOWPLANK
1. Pengukuran dan Pemasangan Bowplank (m1) (SNI 03-235-2002-01)
4 201 Pekerja OH 0.1000
4 206 Mandor OH 0.0050
4 214 Kepala Tukang Kayu OH 0.0100
4 252 Tukang Kayu OH 0.1000
4 2201 Paku Kg 0.0200
4 6090 Papan (3x20) cm (Borneo) M3 0.0070
4 6087 Usuk : 5/7 (Borneo) M3 0.0120
5 201 Pekerja OH 1.0000
5 206 Mandor OH 0.0500
5 214 Kepala Tukang Kayu OH 0.3000
5 252 Tukang Kayu OH 2.0000
5 1102 Semen PC Kg 10.5000
5 1205 Agregat Pecah Mesin 20-30 mm M3 0.0500
5 1249 Pasir Beton M3 0.0300
5 2201 Paku Kg 0.3000
5 6030 Kayu Kelas III M3 0.2100
5 8015 Atap Seng Gelombang Lbr 1.5000
5 6011 Dolken Kayu Dia 8 cm Btg 1.7000

2. Papan Nama Proyek 80x120 cm (bh)


20 6030 Kayu Kelas III M3 0.0350
20 2131 Plat Seng Tebal 0,050 cm Lebar 0,90 m M' 1.4000
20 2201 Paku Kg 0.6000
20 7115 Cat Kayu Kg 1.5000
20 1102 Semen PC Kg 16.8000
20 1249 Pasir Beton M3 0.0270
20 1246 Koral/Krikil M3 0.0405
20 243 Tukang Batu OH 0.0175
20 252 Tukang Kayu OH 1.0000
20 248 Tukang Cat OH 1.0000
20 201 Pekerja OH 2.1000
20 206 Mandor OH 1.0050
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

PEKERJAAN GALIAN TANAH


1. Galian Tanah Biasa Sedalam 1 m (m3) (SNI 2835-2008-01)
23 201 Pekerja OH 0.7500
23 206 Mandor OH 0.0250

2. Urugan Sirtu (m3) (SNI 2835-2008-15)


37 201 Pekerja OH 0.2500
37 206 Mandor OH 0.0250
37 1260 Sirtu M3 1.2000

3. Galian Tanah Biasa Diangkut > 1 m Dibuang (m3)


38 201 Pekerja OH 0.9500
38 206 Mandor OH 0.0350

4. Cut and Fill (m3)


40 201 Pekerja OH 0.0255
40 206 Mandor OH 0.0101
40 214 Kepala Tukang Kayu OH 0.0000
40 252 Tukang Kayu OH 0.0000
40 623 Excavator Jam 0.0126
40 637 Motor Grader Jam 0.0059
40 649 Vibrator Roller Jam 0.0064
40 651 Water Tanker Jam 0.0005
40 652 Wheel Loader Jam 0.0075

PEKERJAAN GALIAN BATU


1. Pasang pondasi batu kosong (anstamping) (M3) (SNI 2836-2008-09)
41 201 Pekerja. OH 0.7800
41 206 Mandor. OH 0.0390
41 211 Kepala Tukang Batu. OH 0.0390
41 243 Tukang Batu OH 0.3900
41 1220 Batu belah 15/20 M3 1.2000
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

41 1255 Pasir urug M3 0.4320


No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

ang pondasi
2. batu kali 1 Pc : 1 Ps (M3)
42 201 Pekerja. OH 1.5000
42 206 Mandor. OH 0.0750
42 211 Kepala Tukang Batu. OH 0.0600
42 243 Tukang Batu OH 0.6000
42 1102 Semen PC Kg 392.0000
42 1222 Batu Gunung/kali M3 1.1000
42 1252 Pasir pasang M3 0.3140

3. Pasang pondasi batu kali 1 Pc : 2 Ps (M3)


43 201 Pekerja. OH 1.5000
43 206 Mandor. OH 0.0750
43 211 Kepala Tukang Batu. OH 0.0600
43 243 Tukang Batu OH 0.6000
43 1102 Semen PC Kg 267.0000
43 1222 Batu Gunung/kali M3 1.1000
43 1252 Pasir pasang M3 0.4270

4. Pasang pondasi batu kali 1 Pc : 3 Ps (M3) (SNI 2836-2008-01)


44 201 Pekerja. OH 1.5000
44 206 Mandor. OH 0.0750
44 211 Kepala Tukang Batu. OH 0.0750
44 243 Tukang Batu OH 0.7500
44 1102 Semen PC Kg 202.0000
44 1222 Batu Gunung/kali M3 1.2000
44 1252 Pasir pasang M3 0.4850

5. Pasang pondasi batu kali 1 Pc : 4 Ps (M3) (SNI 2836-2008-02)


45 201 Pekerja. OH 1.5000
45 206 Mandor. OH 0.0750
45 211 Kepala Tukang Batu. OH 0.0750
45 243 Tukang Batu OH 0.7500
45 1102 Semen PC Kg 163.0000
45 1222 Batu Gunung/kali M3 1.2000
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

45 1252 Pasir pasang M3 0.5200


No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

6. Pasang pondasi batu kali 1 Pc : 5 Ps (M3) (SNI 2836-2008-03)


46 201 Pekerja. OH 1.5000
46 206 Mandor. OH 0.0750
46 211 Kepala Tukang Batu. OH 0.0750
46 243 Tukang Batu OH 0.7500
46 1102 Semen PC Kg 136.0000
46 1222 Batu Gunung/kali M3 1.2000
46 1252 Pasir pasang M3 0.5440

7. Pasang pondasi batu kali 1 Pc : 2.5 Ps (M3)


47 201 Pekerja. OH 1.5000
47 206 Mandor. OH 0.0750
47 211 Kepala Tukang Batu. OH 0.0750
47 243 Tukang Batu OH 0.7500
47 1102 Semen PC Kg 217.0000
47 1222 Batu Gunung/kali M3 1.1000
47 1252 Pasir pasang M3 0.3140

6. Pasang pondasi batu kali 1 Pc : 5 Ps (M3) (SNI 2836-2008-04)


48 201 Pekerja. OH 1.5000
48 206 Mandor. OH 0.0750
48 211 Kepala Tukang Batu. OH 0.0750
48 243 Tukang Batu OH 0.7500
48 1102 Semen PC Kg 117.0000
48 1222 Batu Gunung/kali M3 1.2000
48 1252 Pasir pasang M3 0.5610

PEKERJAAN PLESTERAN
1. Plesteran 1 Pc : 1 Ps tebal 15 mm(m2) (SNI 2837:2008-01)
88 201 Mandor OH 0.3000
88 206 Mandor OH 0.01500
88 211 Kepala Tukang Batu OH 0.01500
88 243 Tukang Batu Oh 0.1500
88 1102 Semen PC Kg 15.5040
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

88 1252 Pasir Pasang M3 0.0160

2. Plesteran 1 Pc : 2 Ps tebal 15 mm(m2) (SNI 2837:2008-02)


89 201 Pekerja OH 0.3000
89 206 Mandor OH 0.0150
89 211 Kepala Tukang Batu OH 0.0150
89 243 Tukang Batu Oh 0.1500
89 1102 Semen PC Kg 10.2240
89 1252 Pasir Pasang M3 0.0200
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

3. Plesteran 1 Pc : 3 Ps tebal 15 mm(m2) (SNI 2837:2008-03)


90 201 Pekerja OH 0.3000
90 206 Mandor OH 0.0150
90 211 Kepala Tukang Batu OH 0.0150
90 243 Tukang Batu Oh 0.1500
90 1102 Semen PC Kg 7.7760
90 1252 Pasir Pasang M3 0.0230

4. Plesteran 1 Pc : 4 Ps tebal 15 mm(m2) (SNI 2837:2008-04)


91 201 Pekerja OH 0.3000
91 206 Mandor OH 0.0150
91 211 Kepala Tukang Batu OH 0.0150
91 243 Tukang Batu Oh 0.1500
91 1102 Semen PC Kg 6.2400
91 1252 Pasir Pasang M3 0.0240

5. Plesteran 1 Pc : 5 Ps tebal 15 mm(m2) (SNI 2837:2008-05)


92 201 Pekerja OH 0.3000
92 206 Mandor OH 0.0150
92 211 Kepala Tukang Batu OH 0.0150
92 243 Tukang Batu Oh 0.1500
92 1102 Semen PC Kg 5.1840
92 1252 Pasir Pasang M3 0.0260

6. Plesteran 1 Pc : 6 Ps tebal 15 mm(m2) (SNI 2837:2008-06)


92 201 Pekerja OH 0.3000
92 206 Mandor OH 0.0150
92 211 Kepala Tukang Batu OH 0.0150
92 243 Tukang Batu Oh 0.1500
92 1102 Semen PC Kg 4.4160
92 1252 Pasir Pasang M3 0.0270
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

7. Plesteran 1 Pc : 8 Ps tebal 15 mm(m2) (SNI 2837:2008-08)


94 201 Pekerja OH 0.3000
94 206 Mandor OH 0.0150
94 211 Kepala Tukang Batu OH 0.0150
94 243 Tukang Batu Oh 0.1500
94 1102 Semen PC Kg 3.4560
94 1252 Pasir Pasang M3 0.0290
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

PEKERJAAN BETON BERTULANG


1. Beton bertulang 1:2:3 k.100 (M3) (SNI 7394-2008-01) f'c = 7,4 Mpa Slump (12 ± 2 )
130 201 Pekerja OH 1.6500
130 206 Mandor OH 0.0830
130 211 Kepala Tukang Batu OH 0.0280
130 243 Tukang Batu OH 0.2750
130 1102 Semen PC Kg 247.0000
130 1205 Agregat Pecah Mesin 20-30 mm M3 0.5550
130 1249 Pasir Beton M3 0.6207
130 7007 Air (Kapal) M3 0.2150

2. Beton bertulang 1:2:3 k.125 (M3) (SNI 7394-2008-02) f'c = 9,8 Mpa Slump (12 ± 2 )
131 201 Pekerja OH 1.6500
131 206 Mandor OH 0.0830
131 211 Kepala Tukang Batu OH 0.0280
131 243 Tukang Batu OH 0.2750
131 1102 Semen PC Kg 276.0000
131 1205 Agregat Pecah Mesin 20-30 mm M3 0.5622
131 1249 Pasir Beton M3 0.5914
131 7007 Air (Kapal) M3 0.2150

3. Beton bertulang 1:2:3 k.150 (M3) (SNI 7394-2008-03) f'c = 12,2 Mpa Slump (12 ± 2
132 201 Pekerja OH 1.6500
132 206 Mandor OH 0.0830
132 211 Kepala Tukang Batu OH 0.0280
132 243 Tukang Batu OH 0.2750
132 1102 Semen PC Kg 299.0000
132 1205 Agregat Pecah Mesin 20-30 mm M3 0.5650
132 1249 Pasir Beton M3 0.5707
132 7007 Air (Kapal) M3 0.2150

4. Beton bertulang 1:2:3 k.175 (M3) (SNI 7394-2008-05) f'c = 14,5 Mpa Slump (12 ± 2
133 201 Pekerja OH 1.6500
133 206 Mandor OH 0.0830
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

133 211 Kepala Tukang Batu OH 0.0280


133 243 Tukang Batu OH 0.2750
133 1102 Semen PC Kg 326.0000
133 1205 Agregat Pecah Mesin 20-30 mm M3 0.5717
133 1249 Pasir Beton M3 0.5429
133 7007 Air (Kapal) M3 0.2150

5. Beton bertulang 1:2:3 k.200 (M3) (SNI 7394-2008-06) f'c = 16,9 Mpa Slump (12 ± 2
134 201 Pekerja OH 1.6500
134 206 Mandor OH 0.0830
134 211 Kepala Tukang Batu OH 0.0280
134 243 Tukang Batu OH 0.2750
134 1102 Semen PC Kg 352.0000
134 1205 Agregat Pecah Mesin 20-30 mm M3 0.5728
134 1249 Pasir Beton M3 0.5221
134 7007 Air (Kapal) M3 0.2150
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

6. Beton bertulang 1:2:3 k.225 (M3) (SNI 7394-2008-07) f'c = 19,3 Mpa Slump (12 ± 2
135 201 Pekerja OH 1.6500
135 206 Mandor OH 0.0830
135 211 Kepala Tukang Batu OH 0.0280
135 243 Tukang Batu OH 0.2750
135 1102 Semen PC Kg 371.0000
135 1205 Agregat Pecah Mesin 20-30 mm M3 0.5817
135 1249 Pasir Beton M3 0.4986
135 7007 Air (Kapal) M3 0.2150

) (SNI 7394-2008-08)
7. f'c = 21,7 Mpa Slump (12 ± 2 ) cm w/c=0,56
136 201 Pekerja OH 1.6500
136 206 Mandor OH 0.0830
136 211 Kepala Tukang Batu OH 0.0280
136 243 Tukang Batu OH 0.2750
136 1102 Semen PC Kg 384.0000
136 1205 Agregat Pecah Mesin 20-30 mm M3 0.5772
136 1249 Pasir Beton M3 0.4943
136 7007 Air (Kapal) M3 0.2150

8. Beton bertulang 1:2:3 k.275 (M3) (SNI 7394-2008-09) f'c = 24,0 Mpa Slump (12 ± 2
137 201 Pekerja OH 1.6500
137 206 Mandor OH 0.0830
137 211 Kepala Tukang Batu OH 0.0280
137 243 Tukang Batu OH 0.2750
137 1102 Semen PC Kg 406.0000
137 1205 Agregat Pecah Mesin 20-30 mm M3 0.5700
137 1249 Pasir Beton M3 0.4886
137 7007 Air (Kapal) M3 0.2150

9. Beton bertulang 1:2:3 k.300 (M3) (SNI 7394-2008-10) f'c = 26,4 Mpa Slump (12 ± 2
138 201 Pekerja OH 1.6500
138 206 Mandor OH 0.0830
138 211 Kepala Tukang Batu OH 0.0280
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

138 243 Tukang Batu OH 0.2750


138 1102 Semen PC Kg 413.0000
138 1205 Agregat Pecah Mesin 20-30 mm M3 0.5672
138 1249 Pasir Beton M3 0.4864
138 7007 Air (Kapal) M3 0.2150
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

10. Beton bertulang 1:2:3 k.325 (M3) (SNI 7394-2008-11) f'c = 28,8 Mpa Slump (12 ± 2
139 201 Pekerja OH 2.1000
139 206 Mandor OH 0.1050
139 211 Kepala Tukang Batu OH 0.0350
139 243 Tukang Batu OH 0.3500
139 1102 Semen PC Kg 439.0000
139 1205 Agregat Pecah Mesin 20-30 mm M3 0.5589
139 1249 Pasir Beton M3 0.4786
139 7007 Air (Kapal) M3 0.2150

11. Beton bertulang 1:2:3 k.350 (M3) (SNI 7394-2008-12) f'c = 31,2 Mpa Slump (12 ± 2
140 201 Pekerja OH 2.1000
140 206 Mandor OH 0.1050
140 211 Kepala Tukang Batu OH 0.0350
140 243 Tukang Batu OH 0.3500
140 1102 Semen PC Kg 448.0000
140 1205 Agregat Pecah Mesin 20-30 mm M3 0.5556
140 1249 Pasir Beton M3 0.4764
140 7007 Air (Kapal) M3 0.2150

PEKERJAAN BEKISTING
1. Pasang Bekesting untuk pondasi (m2) (SNI 7394-2008-20)
141 201 Pekerja OH 0.5200
141 206 Mandor OH 0.0260
141 214 Kepala Tukang Kayu OH 0.0260
141 252 Tukang Kayu OH 0.2600
141 2201 Paku Kg 0.3000
141 6030 Kayu Kelas III M3 0.0400
141 7022 Minyak Bekisting Ltr 0.1000

2. Pasang Bekesting untuk sloof (m2) (SNI 7394-2008-21)


142 201 Pekerja OH 0.5200
142 206 Mandor OH 0.0260
142 214 Kepala Tukang Kayu OH 0.0260
142 252 Tukang Kayu OH 0.2600
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

142 2201 Paku Kg 0.3000


142 6030 Kayu Kelas III M3 0.0450
142 7022 Minyak Bekisting Ltr 0.1000
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

3. Pasang Bekesting untuk kolom (m2) (SNI 7394-2008-22)


143 201 Pekerja OH 0.6600
143 206 Mandor OH 0.0330
143 214 Kepala Tukang Kayu OH 0.0330
143 252 Tukang Kayu OH 0.3300
143 6030 Kayu Kelas III M3 0.0400
143 2201 Paku Kg 0.4000
143 7022 Minyak Bekisting Ltr 0.2000
143 6021 Kayu Balok Kelas II M3 0.0150
143 6059 Plywood (t=9 mm) Lbr 0.3500
143 6011 Dolken Kayu Dia 8 Cm Btg 2.0000

4. Pasang Bekesting untuk balok (m2) (SNI 7394-2008-23)


144 201 Pekerja OH 0.6600
144 206 Mandor OH 0.0330
144 214 Kepala Tukang Kayu OH 0.0330
144 252 Tukang Kayu OH 0.3300
144 6030 Kayu Kelas III M3 0.0400
144 2201 Paku Kg 0.4000
144 7022 Minyak Bekisting Ltr 0.2000
144 6021 Kayu Balok Kelas II M3 0.0180
144 6059 Plywood (t=9 mm) Lbr 0.3500
144 6011 Dolken Kayu Dia 8 Cm Btg 2.0000

5. Pasang Bekesting untuk plat lantai (m2) (SNI 7394-2008-24)


145 201 Pekerja OH 0.6600
145 206 Mandor OH 0.0330
145 214 Kepala Tukang Kayu OH 0.0330
145 252 Tukang Kayu OH 0.3300
145 6030 Kayu Kelas III M3 0.0400
145 2201 Paku Kg 0.4000
145 7022 Minyak Bekisting Ltr 0.2000
145 6021 Kayu Balok Kelas II M3 0.0150
145 6059 Plywood (t=9 mm) Lbr 0.3500
145 6011 Dolken Kayu Dia 8 Cm Btg 6.0000
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

6. Pasang Bekesting untuk Tangga (m2) (SNI 7394-2008-26)


146 201 Pekerja OH 0.6600
146 206 Mandor OH 0.0330
146 214 Kepala Tukang Kayu OH 0.0330
146 252 Tukang Kayu OH 0.3300
146 6030 Kayu Kelas III M3 0.0300
146 2201 Paku Kg 0.4000
146 7022 Minyak Bekisting Ltr 0.1500
146 6021 Kayu Balok Kelas II M3 0.0150
146 6059 Plywood (t=9 mm) Lbr 0.3500
146 6011 Dolken Kayu Dia 8 Cm Btg 2.0000

7. Pasang Bekesting untuk Dinding (m2) (SNI 7394-2008-25)


147 201 Pekerja OH 0.6600
147 206 Mandor OH 0.0330
147 214 Kepala Tukang Kayu OH 0.0330
147 252 Tukang Kayu OH 0.3300
147 6030 Kayu Kelas III M3 0.0300
147 2201 Paku Kg 0.4000
147 7022 Minyak Bekisting Ltr 0.2000
147 6021 Kayu Balok Kelas II M3 0.0200
147 6059 Plywood (t=9 mm) Lbr 0.3500
147 6011 Dolken Kayu Dia 8 Cm Btg 3.0000

PEKERJAAN PEMBESIAN
1 Pembesian dengan besi polos (Kg)
148 201 Pekerja OH 0.0070
148 206 Mandor OH 0.0003
148 211 Kepala Tukang Batu OH 0.0007
148 243 Tukang Batu OH 0.0070
148 2005 Besi Beton Polos Kg 1.0500
148 2304 Kawat Beton/Bendrat RRT Kg 0.0150

2 Pembesian dengan besi ulir (Kg)


No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

149 201 Pekerja OH 0.0050


149 206 Mandor OH 0.0003
149 211 Kepala Tukang Batu OH 0.0005
149 243 Tukang Batu OH 0.0050
149 2006 Besi Beton Ulir Kg 1.0500
149 2304 Kawat Beton/Bendrat RRT Kg 0.0150

3 Pembesian Dengan Besi Polos atau Besi Ulir (10 Kg) (SNI 7394-2008-17)
150 201 Pekerja OH 0.0700
150 206 Mandor OH 0.0040
150 212 Kepala Tukang Besi OH 0.0070
150 244 Tukang Besi OH 0.0700
150 2005 Besi Beton Polos Kg 10.5000
150 2302 Kawat Baja/Bindraad Kg 0.1500
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

4 Pembesian Dengan Besi Ulir (10 Kg) (SNI - DT 91-0008-2007-21)


151 201 Pekerja OH 0.0700
151 206 Mandor OH 0.0040
151 212 Kepala Tukang Besi OH 0.0070
151 244 Tukang Besi OH 0.0700
151 2005 Besi Beton Polos Kg 10.5000
151 2302 Kawat Baja/Bindraad Kg 0.1500

5 Pembesian Dengan Besi Polos (110 Kg) (SNI DT 91-0008-2007-22)


152 201 Pekerja OH 0.7700
152 206 Mandor OH 0.0440
152 212 Kepala Tukang Besi OH 0.0770
152 244 Tukang Besi OH 0.7700
152 2005 Besi Beton Polos Kg 115.5000
152 2302 Kawat Baja/Bindraad Kg 1.6500

6 Pembesian Dengan Besi Polos (120 Kg) (SNI DT 91-0008-2007-23)


153 201 Pekerja OH 0.8400
153 206 Mandor OH 0.0480
153 212 Kepala Tukang Besi OH 0.0840
153 244 Tukang Besi OH 0.8400
153 2005 Besi Beton Polos Kg 126.0000
153 2302 Kawat Baja/Bindraad Kg 1.8000

7 Pembesian Dengan Besi Polos (130 Kg) (SNI DT 91-0008-2007-24)


154 201 Pekerja OH 0.9100
154 206 Mandor OH 0.0520
154 212 Kepala Tukang Besi OH 0.0910
154 244 Tukang Besi OH 0.9100
154 2005 Besi Beton Polos Kg 136.5000
154 2302 Kawat Baja/Bindraad Kg 1.9500
No. AnlsID ResID Nama Bahan / Upah /Alat Sat Koef.

8 Pembesian Dengan Besi Polos (140 Kg) (SNI DT 91-0008-2007-25)


155 201 Pekerja OH 0.9800
155 206 Mandor OH 0.0560
155 212 Kepala Tukang Besi OH 0.0980
155 244 Tukang Besi OH 0.9800
155 2005 Besi Beton Polos Kg 147.0000
155 2302 Kawat Baja/Bindraad Kg 2.1000
) (SNI 7394-2008-01) f'c = 7,4 Mpa Slump (12 ± 2 ) cm w/c=0,87

) (SNI 7394-2008-02) f'c = 9,8 Mpa Slump (12 ± 2 ) cm w/c=0,78

) (SNI 7394-2008-03) f'c = 12,2 Mpa Slump (12 ± 2 ) cm w/c=0,72

) (SNI 7394-2008-05) f'c = 14,5 Mpa Slump (12 ± 2 ) cm w/c=0,66


) (SNI 7394-2008-06) f'c = 16,9 Mpa Slump (12 ± 2 ) cm w/c=0,61
) (SNI 7394-2008-07) f'c = 19,3 Mpa Slump (12 ± 2 ) cm w/c=0,58

) (SNI 7394-2008-09) f'c = 24,0 Mpa Slump (12 ± 2 ) cm w/c=0,53

) (SNI 7394-2008-10) f'c = 26,4 Mpa Slump (12 ± 2 ) cm w/c=0,52


) (SNI 7394-2008-11) f'c = 28,8 Mpa Slump (12 ± 2 ) cm w/c=0,49

) (SNI 7394-2008-12) f'c = 31,2 Mpa Slump (12 ± 2 ) cm w/c=0,48