Вы находитесь на странице: 1из 8

IRRIGATION

Project Name: Construction for Kahramaa New Tower

Client Name: KAHRAMAA

Tender No: GTC-519-2012

Item Time Req./Hr.


Fittings F/Charge Tech. HP Cost M/P Cost Total Rate
Item Description Size Qty Unit Cost (QR) Cost/Set
Include (QR) Cost (QR) (QR) (QR) (QR)
(QR) Tech. Helper

IRRIGATION

Pipe Work

UPVC pipes Class E; including fittings, supports, sleeves, fire


stop, anchors, clean out and all accessories

1 25 mm diameter pipe \ 280 m 5.50 75% 4.1 9.6 15 13 0 9.6

2 40 mm diameter pipe \ 350 m 6.00 75% 4.5 10.5 15 13 0 10.5

3 50 mm diameter pipe \ 130 m 7.00 75% 5.3 12.3 15 13 0 12.3

4 80 mm diameter pipe \ 60 m 8.75 100% 8.8 17.5 15 13 0 17.5

Valves

Valves; jointed to UPVC pipes ; including adaptors, flanges,


reducers, etc.

Isolating valves

5 50 mm diameter pipe \ 3 no 175.00 25% 43.8 218.8 15 13 0 218.8

6 80 mm diameter pipe \ 2 no 550.00 75% 412.5 962.5 15 13 0 962.5

Water Pumps

Construction for Kahramaa New Tower


Bill of Quantities BQ/7/3/1
June 2013
IRRIGATION

Item Time Req./Hr.


Fittings F/Charge Tech. HP Cost M/P Cost Total Rate
Item Description Size Qty Unit Cost (QR) Cost/Set
Include (QR) Cost (QR) (QR) (QR) (QR)
(QR) Tech. Helper

IRRIGATION

Irrigation booster pump sets, vertical multi-stage or end


suction centrifugal type as specified, mounted on steel base
frame; complete with suction and delivery manifold,
expansion vessel, isolating valves, non-return valves,
strainer, pressure gauges, flow controllers, flexible
connections to cold water suction and delivery pipework;
install on prepared base

Booster centrifugal pump set; variable speed; one duty and


one standby; flow rate

7 80/gpm; ref. BSI \ 1 no 35000.00 25% 8750.0 43750.0 15 13 0 43750.0

Irrigation Water System to Planter Area

Irrigation water system; including bubblers, emitters, flow


meters, valve box, drip line, controllers and all associated
items

8 to planter area; complete \ 1320 m2 100.00 35% 35.0 135.0 15 13 0 135.0

GENERAL REQUIREMENTS IRRIGATION WATER


SYSTEMS

Submissions and Approvals

Submittal documentation; product data. certificates and


9 miscellaneous submittals as specified and required for \ 1 Item 10000 10% 1000 11000 15 13 0 11000
approval

10 Submission of material samples \ 1 Item 7500 10% 750 8250 15 13 0 8250

11 Shop Drawings \ 1 Item 5000 10% 500 5500 15 13 0 5500

12 As-built drawings \ 1 Item 5000 10% 500 5500 15 13 0 5500

Cleaning and Preparation

Preparatory operations to pipework system prior to Testing


13 \ 1 Item 5000 10% 500 5500 15 13 0 5500
and Commissioning procedures as specified

Construction for Kahramaa New Tower


Bill of Quantities BQ/7/3/2
June 2013
IRRIGATION

Item Time Req./Hr.


Fittings F/Charge Tech. HP Cost M/P Cost Total Rate
Item Description Size Qty Unit Cost (QR) Cost/Set
Include (QR) Cost (QR) (QR) (QR) (QR)
(QR) Tech. Helper

IRRIGATION

Testing and Commissioning

Testing and Commissioning of pipework system and


14 equipments rectifying and making good all defects to leave a \ 1 Item 5000 10% 500 5500 15 13 0 5500
fully compliant and operational system as specified

Construction for Kahramaa New Tower


Bill of Quantities BQ/7/3/3
June 2013
IRRIGATION

Item Time Req./Hr.


Fittings F/Charge Tech. HP Cost M/P Cost Total Rate
Item Description Size Qty Unit Cost (QR) Cost/Set
Include (QR) Cost (QR) (QR) (QR) (QR)
(QR) Tech. Helper

IRRIGATION

Operation and maintenance

15 Operation and maintenance manuals and spare part lists \ 1 Item 72068 10% 7206.8 79274.8 15 13 0 79274.8

16 Staff training \ 1 Item 5000 10% 500 5500 15 13 0 5500

17 Spare parts, tools, and the like \ 1 Item 15000 10% 1500 16500 15 13 0 16500

Identification

Nameplates, labelling including identification of valves,


18 motor control identification,schedules and charts and color \ 1 Item 2500 10% 250 2750 15 13 0 2750
bands for coding service pipes as specified

BUILDER'S WORK IN CONNECTION WITH WATER


SERVICES

General Construction Works

Works to structure and fabric; to accommodate pipes,


equipment,, and the like, and to carry out all construction Excluded
works; including marking positions, making good, patching

Cutting and forming openings, forming mortices, sinkings in


19 walls, floors, ceilings, and the like; including sealing, pipe \ 1 Item Excluded 15 13 0 0
sleeves, and the like

Cutting and forming openings, forming mortices, sinkings in


fire rated walls, floors, ceilings, and the like; including fire
20 \ 1 Item Excluded 15 13 0 0
sealing, intumescent putty material, fire stops, pipe sleeves,
and the like

21 Chases, channels, in walls, floors, ceilings, and the like \ 1 Item Excluded 15 13 0 0

Construction for Kahramaa New Tower


Bill of Quantities BQ/7/3/4
June 2013
IRRIGATION

ESTIMATION SHEET

% Profit Profit/Item Total Item Rate


Total Item Cost Total M/P Cost Total Amount Net Profi
(QR) Amt. (QR) (QR)

30% 13 2,695 0 2,695 3,504 809

30% 14 3,675 0 3,675 4,778 1,103

30% 16 1,593 0 1,593 2,070 478

30% 23 1,050 0 1,050 1,365 315

30% 284 656 0 656 853 197

30% 1,251 1,925 0 1,925 2,503 578

Construction for Kahramaa New Tower


Bill of Quantities BQ/7/3/5
June 2013
IRRIGATION

% Profit Profit/Item Total Item Rate


Total Item Cost Total M/P Cost Total Amount Net Profi
(QR) Amt. (QR) (QR)

30% 56,875 43,750 0 43,750 56,875 13,125

30% 176 178,200 0 178,200 231,660 53,460

30% 14,300 11,000.00 - 11,000.00 14,300.00 3,300.00

30% 10,725 8,250.00 - 8,250.00 10,725.00 2,475.00

30% 7,150 5,500.00 - 5,500.00 7,150.00 1,650.00

30% 7,150 5,500.00 - 5,500.00 7,150.00 1,650.00

30% 7,150 5,500.00 - 5,500.00 7,150.00 1,650.00

Construction for Kahramaa New Tower


Bill of Quantities BQ/7/3/6
June 2013
IRRIGATION

% Profit Profit/Item Total Item Rate


Total Item Cost Total M/P Cost Total Amount Net Profi
(QR) Amt. (QR) (QR)

30% 7,150 5,500.00 - 5,500.00 7,150.00 1,650.00

Construction for Kahramaa New Tower


Bill of Quantities BQ/7/3/7
June 2013
IRRIGATION

% Profit Profit/Item Total Item Rate


Total Item Cost Total M/P Cost Total Amount Net Profi
(QR) Amt. (QR) (QR)

30% 103,057 79,274.80 - 79,274.80 103,057.24 23,782.44

30% 7,150 5,500.00 - 5,500.00 7,150.00 1,650.00

30% 21,450 16,500.00 - 16,500.00 21,450.00 4,950.00

30% 3,575 2,750.00 - 2,750.00 3,575.00 825.00

30% 0 - - - - -

30% 0 - - - - -

30% 0 - - - - -

Total Cost 378,818.55 - 378,818.55 492,464.12 113,645.57

Construction for Kahramaa New Tower


Bill of Quantities BQ/7/3/8
June 2013

Вам также может понравиться