Вы находитесь на странице: 1из 5

SPE 93636

Success Story To Produce 200 MMscfd of Gas From Mutiara


Y.A. Prihartono, A.P. Riksa, and S.R. Affan, VICO Indonesia

Copyright 2005, Society of Petroleum Engineers Inc.

This paper was prepared for presentation at the 2005 Asia Pacific Oil & Gas Conference and
Exhibition held in Jakarta, Indonesia, 5 – 7 April 2005.
Introduction
This paper was selected for presentation by an SPE Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as VICO Indonesia is the operator of Sanga-Sanga PSC in
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to
correction by the author(s). The material, as presented, does not necessarily reflect any East Kalimantan – Indonesia (Fig. 1). VICO has four major
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at fields that averagely produce about 800 MMscfd gas and
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper 30,000 BOPD. The gas is delivered via pipeline to Bontang
for commercial purposes without the written consent of the Society of Petroleum Engineers is LNG Plant and processed to LNG products for distribution
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous and sale in East Asia market. The production facility which
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O. is this paper focused on is in Mutiara Field.
Box 833836, Richardson, TX 75083-3836 U.S.A., fax 01-972-952-9435.

Discovered in 1990, Mutiara Field manages three areas,


Abstract which are located in the southern part of VICO PSC (Fig.
2). These areas are Mutiara, Beras located in southern area
Mutiara Field is one of four fields in VICO Indonesia, East and Pamaguan located in northern area of the field.
Kalimantan that located in southern of the contract area. Hydrocarbon accumulations exist in the Middle to Upper
The central processing plant of Mutiara Field is originally Miocene aged sandstones, at depths from 1,000 feet to
designed for processing 165 MMscfd gas. In 2002-2003, around 11,000 feet. The thickness of the reservoirs range
some planned work programs were done successfully that up to 110 feet while the reservoir permeability is generally
include 5 well workover, installation of additional one MP good and can be as high as 2 D. The original gas in place is
compression unit and 2 well drilling program. The success 1.3 TCF with 1.0 TCF of recoverable gas reserves. To date,
of these work programs became apparent that Mutiara total 100 wells have been drilled with total cumulative
could produce more than 165 MMscfd. However, the plant production around 500 MMscfd.
throughput was limited by flare system capacity and gas
dehydration capacity. So, the challenge was to overcome In the beginning Mutiara Field was focusing on
the capacity limit at minimum cost to allow Mutiara to development of oil reservoir. Until 1990 when a significant
increase sales gas export. gas reserves in this area found. Based on the result, it was
decided to produce the gas to develop the reserve and also
Some inter-multidisciplinary studies were conducted to support gas demand from Bontang LNG Plant. In 1990,
solve the problem, to find the most suitable and most Mutiara started to build the central gas processing plant in
economic solution. The study concluded that there are two Mutiara Central Plant (MCP). This plant receives gas and
options to process gas more than plant capacity limit that liquid from wells in Mutiara area. To support the production,
are: installing additional flare system or to modify plant’s three gas gathering stations were built. Two gas stations
overpressure protection system. The last option was are located in Beras area to receive gas and liquid from
selected based on time and cost justification. This wells in this area; and one gas station in Pamaguan area.
modification is to cease incoming gas to the plant in order Gas in Beras and Pamaguan areas are gathered into
to maintain gas inside the plant below the flare capacity in medium pressure (MP) system or very low pressure (VLP)
case of overpressure occurred in the event of process system then compressed into MP system before it is
upset. delivered to MCP for further processing.

Other problem that exists is limitation of dehydration unit to Gas processing plant in MCP production capacity was 120
absorb water in the gas until the allowable limit. Overhaul MMscfd. Gas delivered to Bontang LNG plant through 20”
dehydration unit had been done to improve its performance. pipeline. The plant is also equipped with gas dehydration
This was also to include clean up and pressure testing of all unit, oil/condensate stabilization system, produced water
equipment associated. Also, some pipeline debottlenecking treatment plant, and utilities facilities.
projects at outlet plant were done to reduce plant outlet
pressure that also supports operation of the plant. Since 1991 until the end of 1999, the production rate was
120 MMscfd. In the beginning of 2000, some gas wells
The above changes were made at almost no capital cost, drilling developments were performed, and gave a good
allowed Mutiara to produced gas at 200 MMscfd started on result that allow Mutiara to delivered gas up to 165 MMscfd.
mid of 2003. Since the plant capacity was designed at 120 MMscfd it is
2 SPE 93636

decided to install additional MP compression unit (55 Gas Flaring System Capacity
MMscfd capacity). Theoretically, after installation of the new Mutiara Central Plant has equipped with overpressure
compressor Mutiara gas production more than 165 MMscfd. protection system that consist of several pressure safety
Another constraint was the flare stack capacity with valves (PSV), blowdown valves (BDV), pressure control
maximum capacity at 165 MMscfd, it was decided to limit valves (PCV) and other relief system that usually connected
the plant capacity to produce gas at this level for safety to gas flaring system. The function of the overpressure
reasons (Fig. 3). protection system is to protect related equipment from
undesirable condition (such as fire, high or low pressure) to
In 2002-2003, some planned work programs were done ensure the equipment are operating in safe condition.
successfully which gave the results higher than prediction.
These work programs consist of 5 wells workover, 2 The overpressure protection system was designed to
development drillings, and installation of another MP release all gas in the system to flare system if undesirable
compression unit (increased MP compression capacity up condition occurred. Total rate from released gas into the
to 180 MMscfd). Well workover and drilling programs gave flare system has to be lower than flare capacity. In the
very high rate with high reservoir pressure, and produced existing plant, flare system has the maximum capacity at
into HP system (no more depend on the MP compression 165 MMscfd and the released gas can be maintained at this
capacity). The success of these work programs became rate since the maximum incoming rate into the plant is also
apparent that Mutiara could have produce gas more than maintained at this level.
200 MMscfd.
However, increasing plant delivery more than 165 MMscfd
To accommodate this purpose, some inter-multidisciplinary will increase the risk for the plant. If the plant processes gas
reviews were conducted. A multidiscipline team consists of more than 165 MMscfd, the possible released gas into the
production and maintenance team, production engineer, flare system will also increase. This condition creates
process and compressor engineer was formed to do the unsafe situation for the plant. In order to overcome the
review. The main objective of this team was to identify the limitation of gas flaring capacity, two options are
bottlenecking of the existing production facilities and find recommended:
the solution to maximizing gas delivery from Mutiara Field. • Increase flare capacity up to 200 MMscfd by install
additional flare stack in MCP, parallel with the
After reviewing the engineering data of the existing existing flare stack.
production facilities, operational history data, and current • Modify the overpressure protection system to
practice of daily operation and maintenance, the team ensure the load the flare system when undesirable
comes up with the following findings: event happens does not exceed the existing flare
• The plant throughput was limited by gas flaring stack capacity, although the gas rate in plant is
system capacity. Increasing the production rate will higher than 165 MMscfd.
increase load into the flare system when the
undesirable condition occurred, such as fire or Then, it is decided to select the second option base on cost
overpressure. and timing consideration. To install a new flare stack will
• Gas dehydration unit is designed for 120 MMscfd require high capital cost and also time consumed, while the
capacities. Increasing the rate will make the demand for the gas is high in the period.
performance of the unit became lower and
increasing the water content and risk in the The proposed of new overpressure protection system in
pipeline. The daily operational record also shows MCP is to reduce load of the released gas into the flare
that the unit was running in non-optimum condition system when undesirable event happens. This new system
and gave worse results compared to the original changes the philosophy of overpressure protection system
design. by closing all incoming gas into the plant when fire or high
• The other constraint is pipeline network problem. In pressure condition in the system occurs. The modifications
the existing configuration, Mutiara Field used 20” are as follows:
pipeline to Bontang, sharing with other gas • For high pressure system: lowering pressure setting
producer in East Kalimantan. This condition point for all SDV’s at the inlet manifold by 100 psig. This
resulted high back pressure to Mutiara and modification will increase the sensitivity of the SDV’s at
lowering the compressor performance. inlet manifold and allow all HP gas wells are closed at
the inlet manifold and reduce released gas into flaring
Improvement and Implementation Planning system.
• For medium pressure system:
- Reduces pressure setting point for all SDV’s at the
Further study was conducted to solve the above constraints
inlet manifold by 15 psig. The modifications have
in order to increase Mutiara plant capacity; and several
similar impact as high pressure system.
options were identified for the improvement. Some
- Increase the setting point of the BDV’s at suction of
considerations for this improvement are the options have to
MP compressor units by 5 psig to reduce the
be safe to be implemented, with reasonable cost and
sensitivity of valves in order to reduce load to flare
schedule.
system.
SPE 93636 3

- Resetting all pressure system in every well to by waxy material and prevented the water to vaporize from
accommodate with manifold’s SDV. the glycol and keep the water content in the glycol high.
- Remove BDV at trunkline from stations. Originally Another problem found was the glycol purity was lower than
BDV will release gas from the stations when MCP the manufacturer’s specification. To solve the problem,
unable to process the gas. By this modification, the inspection, testing and general clean up of the reboiler,
trunkline closed when MCP is unavailable and glycol tank, glycol filter and gas contactor were performed.
reduce gas load into the flare system. Then a new glycol with 99% purity was used for
operational.
In general, these modifications change the MCP shutdown
system philosophy by closing the unit first before excess After the system was cleaned up completely, several gas
gas is flared. dehydration performance tests were done. The operational
parameters are monitored and optimized regularly; the
Gas Dehydration Unit glycol purity was checked regularly by sending the glycol
sample to laboratory, and also improved the glycol
Other problem constraints Mutiara to produce higher gas regeneration system was working to remove the water until
rate was limitation of gas dehydration unit. The existing gas less than 1%. As the final result, the water content in the
dehydration unit is designed for 120 MMscfd gas rate with export gas can be maintained within the specification.
moisture content in the export gas at 7 lb/MMscfd gas.
Currently, VICO adopts moisture content standard for gas Pipeline System
in pipeline at lower than 20 lb/MMscfd.
In the existing configuration, Mutiara gas flows thru 20”
The dehydration unit used in Mutiara is a liquid desiccant pipeline to Bontang, sharing with other gas producer in East
type with triethylene glycol (TEG) as water absorber. The Kalimantan. By this configuration, the plant outlet pressure
unit consists of gas contactor and glycol reboiler unit. The at MCP is about 990 psig, and sometimes are higher
gas contactor is used to mix the wet gas (usually from HP depends on back pressure from Bontang and gas rate from
gas well or from discharge MP compressor) with lean glycol other gas producer. This condition also affects the
in counter current flow. Moisture in the gas will be absorbed performance of MP compressor units and whenever the
by the lean glycol from the reboiler. Gas contactor that used pipeline pressure increased, causing compression capacity
in Mutiara is structured packing type inside the unit. Glycol lower and reduces the plant delivery.
reboiler unit to regenerate the rich glycol contains high
water. The rich glycol heated in reboiler to vaporize the Based on engineering simulation, increasing gas delivery
water to produce the lean glycol before it pumped back to up to 200 MMscfd will increase pipeline pressure from 990
gas contactor. to 1065 psig at MCP. Increase the plant outlet pressure up
to this level will decrease the compression capacity by 15
Based on engineering simulation, if the plant capacity MMscfd. The simulation also shows very high pressure
upgraded to 200 MMscfd, the existing gas contactor had to drop will occur in the pipeline section between MCP and PK
be able to process up to 140 MMscfd with moisture content 1.4 point (when the pipeline is connected to other gas
maximum 7 lb/MMscfd; while the rest of the gas flows producer).
though by-pass line of the contactor in order to achieve 20
lb/MMscfd moisture content in the sales gas. To solve this condition, a pipeline debottlenecking project
has to be conducted, either by installing parallel pipeline
To maintain the moisture content at <20 lb/MMscfd, gas from MCP to PK 1.4 point to reduce the pressure drop or by
dehydration unit had to be modified by the following connected to another pipeline that owned by other gas
options: producer. The pipeline size is 42 inches pipeline and
• Replace the existing structured packing with new crossing nearby MCP and has lower operating pressure.
type of packing to improve gas dehydration system
gas produce lower moisture content in gas. Project Implementation and the Results
• Install new dehydration system with capacity 60
MMscfd. In the beginning of 2003, the options for each constraint
• Relocate dehydration unit from other field in VICO, were selected. The schedule was set to produce Mutiara
but has lower maximum allowable working gas at 180 MMscfd by mid of 2003 and 200 MMscfd by Q4-
pressure. 2003.

From the operation side, it was found moisture content in The modification of the overpressure protection was
the gas stream was higher than the original design. Then, it conducted by Maintenance team. The modifications cover
was recommended to improve the gas dehydration resetting of related overpressure protection equipment and
performance to achieve the original design parameter. also actual test of shutdown system. The modifications
were completed in mid of 2003. Overhaul of gas
The option selected was not to install the new equipment, dehydration unit and performance test were performed by
but improving the existing unit as per original design, while Production team.
the excess gas will be by-passing the contractor. An
overhaul of gas dehydration unit was performed. It was The modification of pipeline network was also completed by
found that the still column of the reboiler unit was plugged mid of 2003. A connection from plant outlet into the 42
4 SPE 93636

inches pipeline was proved to lower plant discharge Acknowledgments


pressure by 100 psig that also support operation of the The authors wish to thank the management of VICO
plant. Indonesia and BP-MIGAS for permission to publish and
present this paper at the 2005 SPE Asia Pacific Oil and
When the commissioning was performed in mid of 2003, Gas Conference and Exhibition.
Mutiara Central Plant produces gas at 180 MMscfd. And at
the beginning of October 2003, when new drilled well and
References
MP compressor were put on service, the gas delivery
increased to 200 MMscfd. The above changes made at
almost no capital cost. 1. VICO Indonesia, Mutiara Field Engineering Data Book,
1991
Currently, the field production is 195 MMscfd gas and 4500 2. VICO Indonesia, Mutiara/Beras/Pamaguan Standard
BPD hydrocarbon liquid. (Fig. 4) Operating Procedure, 2000
3. VICO Indonesia, Glycol Dehydration System
Conclusion Troubleshooting, 1997
4. VICO Indonesia year book reserves, 2005
This paper presented an overview of the improvement of a
gas plant to increase plant capacity. The following
concluding remarks are made:
• This project is driven by successful work programs,
such as development drilling, well workover and
facility project.
• The time required to implement this project from
concept to successful operation was about six
months.
• The implementation of this project is possible due
to support and participation from many disciplines
team.
SPE 93636 5

Pamaguan

To
Bontang
Mutiara
Central Plant

M6
Station From
other
company

M8
Station

Sanga-Sanga PSC in East Kalimantan – Indonesia (Fig. 1) Mutiara Field areas (Fig. 2)

Gas Production Profile


1991-2005

Mutiara compression schematic (Fig. 3) Mutiara gas production (Fig. 4)

Вам также может понравиться