Вы находитесь на странице: 1из 14

4

Eastern Freeway Phase 1

1.1. OBJECTIVE:-

Objective of this methodology is to construct pile .

1.2. PROCEDURE:-

1. Survey and Fixing of pile location

METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

2. Installation of liner
3. Rebar cage Installation
4. Concreting

Survey and Fixing of pile location


The location of the pile will be fixed on the ground by using GPS and it will be
counter checked by using total station and temporary bench mark.
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

Installation of liner and driving of pile


The hydraulic piling rig is adjusted to the piling axis with the help of GPS total
station. Pegs are placed at a fixed distance from the centre around the axis
and the distance is noted. The liner is aligned with the centre of the axis with
the help of the fixed peg distance. The pre fabricated liner is sunken into the
land.
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

Installation of Re-bar cage


The rebar cage will be fabricated and made in the reinforcement yard as per
the drawing and design. The prefabricated re-bar cage is shifted to the pile
site. The re-bars cage segments are joined with the help of bar couplers. The
bar coupled cages are lowered into the bored pile with the help of cranes up

METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

to the bottom level. After completion of rebar work it will be inspected and
approval of pour card will be obtained.

Concreting of Pile
After obtaining pour card, the tremie pipe is installed for pile concreting.
Flushing of the pile is done. The concrete is transported to the pile site on
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

Transit mixers from the Batching plants. Pouring of concrete is done till the
pile is complete.

1.3. EQUIPMENTS:-

1. Cranes
2. Grab bucket
3. Piling Rig
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

4. Gensets
5. Pneumatic Compressor
6. Cutting and Bending Machine
7. Lathe Machines
8. Batching Plant
9. Transit Mixers
10. Tremie pipe
METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

11. Vibro-hammer
12. GPS and Total Station
13. Auto Levels
14. Concrete Pump

1.4. MATERIALS:-

Concrete material, Tremie pipe, Re-Bars cage, Liner, Bridge Instrumentation


METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

1.5. QUALITY / INSPECTION:-

Quality of the concrete mix will be checked as per the IS Codes ……

1.6. SAFETY: -
After the drilling is done the pile should be covered till the concreting starts.

METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

1.7. SKETCH / DRAWINGS :-

Figure - Showing the Boring and Installation of Liner

Ref. No. METHODOLOGY OF CONSTRUCTION OF


PILE IN LAND

CONSTRUCTION METHODOLOGY
Doc. No. Eastern Freeway Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

Figure - Showing the Boring and Installation of Liner

Ref. No. METHODOLOGY OF CONSTRUCTION OF


PILE IN LAND

CONSTRUCTION METHODOLOGY
Doc. No. Eastern Freeway Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

Figure - Showing Installation of Re-Bar Cage

METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

Ref. No. METHODOLOGY OF CONSTRUCTION OF


PILE IN LAND

CONSTRUCTION METHODOLOGY
Doc. No. Eastern Freeway Rev .No
From Museum to Anik Junction
4
Eastern Freeway Phase 1

METHODOLOGY OF CONSTRUCTION OF
Ref. No.
PILE IN LAND

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction

Вам также может понравиться