Eastern Freeway Phase 1

1.1. OBJECTIVE:-

The purpose of this Methodology is to formulate guideline for construction of a


Pier

1.2. PROCEDURE:-

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

1. Working Platform
2. Staging for supporting
3. shutter fixing
4. Reinforcement work
5. Completion of side shutter and supporting work
6. Concrete

Working Platform

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

After completion of Pile cap, a platform will be formed over the Pile cap so
that it would act as working platform for carrying out construction activities
of Pier.

Staging for supporting


The staging will be provided so as to support the Formwork for Pier and to
carry the Reinforcement work.

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

Shutter fixing
After completion of staging, formwork for Pier will be shifted to site and
Fixed as per drawing.

Reinforcement work
The reinforcement cage already prepared in the Reinforcement yard as
per the Methodology for preparation of Reinforcement cage will be shifted
to site and positioned to the Pier location .

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

Completion of side shutter and supporting work


After completion of Reinforcement work, the remaining side shuttering and
supporting work is completed. Final inspection work will be done with the
help of survey and then the approval of concrete pour will be taken.

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

1.3. EQUIPMENTS:-

1. Batching Plant
2. Concrete Pump (Boom Placer)
3. Transit Mixer
4. Survey Instrument with all accessories
5. Slump Cone

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

6. Thermometer

1.4. MATERIALS:-

1. Concrete material
2. Vibrator and needle
3. Cover Blocks
Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

4. Reinforcement

1.5. QUALITY / INSPECTION:-

During Concreting of Pier following inspections should be done.


1. Checking of supports
2. Slump as per mix design

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

3. Casting of concrete cubes as per requirement


4. Proper vibration of the mix

CONCRETING

After approval of concrete Pour, floating Batching plant along with concrete pump will
be mobilized at site and then pouring of concrete can be Started.

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

1.6. SAFETY: -

All necessary safety must be followed as per Norms given in IRC: 55.

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1

1.7. SKETCH / DRAWINGS :-

Pier Reinforcement

Ref. No. METHODOLOGY OF PIER

CONSTRUCTION METHODOLOGY
Doc. No. Eastern Freeway Rev .No