1.1. OBJECTIVE:-
1.2. PROCEDURE:-
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
1. Working Platform
2. Staging for supporting
3. shutter fixing
4. Reinforcement work
5. Completion of side shutter and supporting work
6. Concrete
Working Platform
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
After completion of Pile cap, a platform will be formed over the Pile cap so
that it would act as working platform for carrying out construction activities
of Pier.
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
Shutter fixing
After completion of staging, formwork for Pier will be shifted to site and
Fixed as per drawing.
Reinforcement work
The reinforcement cage already prepared in the Reinforcement yard as
per the Methodology for preparation of Reinforcement cage will be shifted
to site and positioned to the Pier location .
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
1.3. EQUIPMENTS:-
1. Batching Plant
2. Concrete Pump (Boom Placer)
3. Transit Mixer
4. Survey Instrument with all accessories
5. Slump Cone
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
6. Thermometer
1.4. MATERIALS:-
1. Concrete material
2. Vibrator and needle
3. Cover Blocks
Ref. No. METHODOLOGY OF PIER
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
4. Reinforcement
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
CONCRETING
After approval of concrete Pour, floating Batching plant along with concrete pump will
be mobilized at site and then pouring of concrete can be Started.
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
1.6. SAFETY: -
All necessary safety must be followed as per Norms given in IRC: 55.
CONSTRUCTION METHODOLOGY
Eastern Freeway
Doc. No. Rev .No
From Museum to Anik Junction
2
Eastern Freeway Phase 1
Pier Reinforcement
CONSTRUCTION METHODOLOGY
Doc. No. Eastern Freeway Rev .No
From Museum to Anik Junction