Country: Romania

Location (exact GPS coordinates,


latitude/longitude, if possible google earth link) – See location maps in attachment
kmz files)

Aerial photos/ maps Google maps attached

Layout of the project (pdf and dwg file formats


(the dwg format is the one that comes from Attached
Autocad)

Size in AC/DC (extensions possible or


10.00 AC
planned?)

Land area 40 ha

Advanced stage: The project is 75%


completed. We still need to obtain the
Project status
final grid connection study and the Grid
Permit.

Substation (distance to location, capacity, 5 km, upgrade necessary (see


voltage level, upgrade necessary or not) attachments)

Estimated energy production in kWh/kWp 1,392

Estimated solar radiation kWh/m2 See Presentation

Estimated IRR 14% p.a. un-levered, 27% levered

FIT or PPA value (PPA agreement already PPA will be signed when the project is
signed? Duration? If not, when?) RTB. Attached a LOI stating this.

Page 1|3
Electricity off-taker Authorized Trader

Yes, land lease contracts in place, for


Land (lease or purchase), agreements signed?
another 19 years, mentioned in the Land
All necessary documentation to prove the
Registry of the respective County.
ownership/purchase/lease is in place?
2,000 Euro/year/ha, once the project is
Payment terms?
operational.

All permits have been obtained, in line


List of necessary permits and their status (to
with obtaining the Building Permits and
be submitted/in process/received)
Preliminary electrical approvals, etc.

Estimated time period from completion of 2 months (technical trials, final


construction till connection to the grid inspection)

The Solar Park will be connected to a


Grid compatibility
20/110 kV substation.

Terrain/soil description:
Terrain structure, soil texture, vegetation,
There are no aspects to hinder the
distance to populated area,
project.
bridges/underpasses/roads, etc. in proximity and
possible obstruction to access the site?

Is any water source in the vicinity, such as


Not in the immediate vicinity.
lakes/rivers/etc?

Evacuation line is underground or overhead Underground, alongside public communal


(going through public or private property)? roads.

Environmental study Was already completed and approved

Shadow report There is a report of annual insulation

Energy yield report from PV Syst See Presentation

Planned module type (poly/mono) and watt


Planned 250 Wp, poly
class
Planned inverters Yes, attached

Page 2|3
Planned mounting structure It can be addressed later
Estimated of project development till RTB
4 months since receiving the funds
stage
Equipment costs Total Park EPC
(modules/inverters/mounting structure)
Land costs 80,000 Euro/year

Connection costs Attached, Tariff + Beneficiary

Construction financing is in place? No

Expected construction begin 5 months

Expected commissioning of the project 2018

We have already obtained the Building


Country-specific regulations for the erection
Permits, which include the environmental
of PV plants?
permits, etc. so no issue here.
Please indicate any further open issues or
add any remarks

Page 3|3