FOR : COA
THRU : SSS
FROM : ACCOUNTING DEPARTMENT
RE : SPOT AUDIT ON GOVERNOR HILLS & THE GENTRI HEIGHTS
HOUSING UNITS
DATE : MARCH 17, 2016
AUDIT REPORT
AUDIT OBJECTIVE:
1.) To check adherence of the contractors to the units’ contract completion date.
2.) To verify the accomplishment billed by the contractors by comparing it to actual status of
the unit.
3.) To assess the working condition and orderliness of the ongoing house constructions.
AUDIT PROCEDURE:
1.) Actual Inspection
2.) Discussion
AUDIT SUBJECT: STATE LAND- 33 units( Annex I)
The Gentri Heights - 29 units (Annex II)
AUDIT FINDINGS: During our course of Audit we found out the following.
The Detailed accomplishment of Governor’s hills Ysabella model unit with phase 5
block 27 lot 12 was improperly evaluated (see Annex I). The said unit is awarded to Almonte
Construction and Trading Corporation. The table below shown some scope of works evaluated
were different based on actual accomplishment of the said unit. Attached in the report is the
approved evaluated detailed accomplishment report of the contractor for 1/9/16 – 2/8/16 and
look for Annex I actual images of the unit.
The tables below showed the summary of units with delay of construction and their corresponding
reasons of delay in construction as per discussion with Project Officers and Project Manager with
supporting documents (see Report dated March 7, 2015)
Homeowner
GT P2 B21 L16 1/10/16 50 92% Request of
Modification/Alteration
According to P.O, there
has been delay of
construction due to the
first contract submitted
GT P3 B33 L47 2/29/16 0 63% SPI to Yashar have a
typographical error,
instead of Yashar it is
Arcopaul Construction
which is the reason
they can’t sign the said
contract and took three
weeks before they
signed the contract.
TABLE2.1 Units noted with contract for expiration but lower percentage of completion.
REMAINI ACTUAL
LOCATION DATE OF NG % OF CAUSE OF REASON OF DELAY
EXPIRATION DAYS COMP DELAY
2/29/16 LETION
According to Project Officer Homeowners are aware of being delayed and contractors are advice
to submit time extension. As per SPM Engr. Wilmo F. Fallar, Jr. to avoid none submission of time
extension within the contract duration of the contract Construction below 80% accomplishment of the unit
with 1 month remaining days to complete the contract will be subject for time extension with reasonable
cause of delay.
And Engr Fallar will review the evaluation done by project Officers before contractor’s billings
forwarded for payment.
IV. RECOMMEDATION
Project Officer should conduct detailed checking on evaluated detailed accomplishment report on
progress billings compared to actual condition of the unit to avoid any discrepancies on preparing
the billings. Project Manager should ensure compliance on this part during or after the checking
of evaluated detailed accomplishment report.
A review of standard contract duration considering the model unit and modification or additional
works requested by Homeowner if any.