Академический Документы
Профессиональный Документы
Культура Документы
The idea for this review of the technology for developing marginal offshore oilfields
arose out of a report which we were commissioned to undertake for the Irish Department
of Energy in October 1984. The Department were looking for information on the
different options for developing small oil accumulations in the exposed Irish offshore
area, what systems were currently available, what new developments were likely in the
next decade and the approximate cost of developing various sizes of reservoir using these
systems.
While compiling the report we discovered that, while all the literature and industry
spokesmen agreed on the importance of marginal field technology, there was no
publication which addressed the topic in any comprehensive fashion, with the possible
exception of studies costing several thousands of dollars or confidential oil company in-
house reports. This review aims to cover this very broad topic in a way which is
intelligible to a general technical reader. It is not possible to cover detailed design aspects
of the various systems described here in a book of this size. References and a
bibliography covering the topics discussed in each chapter are provided for those
interested in pursuing the various subjects in more detail.
We have sought the views of oil companies, design engineers, offshore consultants,
contractors and researchers. We have obtained invaluable assistance from innumerable
individuals and firms, far too many to list here. However, we would like to express our
appreciation for all the time and assistance given, queries answered, literature searches
undertaken, articles provided, etc.
We would especially like to express our appreciation to a number of individuals who
reviewed and edited the draft versions of this book:
—A.R.(Bert) Schultz, Vice-President of Intec Engineering Inc. who provided advice on
technology and cost parameters.
—Dr Pat Shannon, Department of Petroleum Geology, University College Dublin.
—F.B.(Fergus) Cahill, Exploration & Production Manager, Irish National Petroleum
Corporation.
We also thank our respective organisations, the Petroleum Affairs Division, Department
of Energy and the Institute for Industrial Research and Standards, Dublin for their interest
in this area and their permission to incorporate certain material from their report.
However, we wish to emphasise that the opinions expressed herein are the authors’ own
and do not necessarily reflect the views of the Petroleum Affairs Division of the
Department of Energy nor the Institute for Industrial Research and Standards. Last, but
certainly not least, we wish to thank Anna Kennedy, who patiently typed, and retyped,
the document and Heather Gibson, who executed the line drawings.
DEREK FEE
JOHN O’DEA
Contents
Preface vii
Bibliography 223
Appendix Conversion Factors 229
1:
Appendix Glossary of Terms 230
2:
Index 235
Chapter 1
The Challenge of Marginal Fields
Nearly half of the world’s proven reserves of oil lie offshore and it is estimated that over
two-thirds of all future oil discoveries will also be located offshore. But in any oil
exploration area it is the larger fields which tend to be found first and even when small
discoveries are made the oil tends to be left in the ground as the oil companies rush to
develop the larger and more commercial fields.
Classification of a discovery as ‘commercial’, ‘uncommerciar’ or ‘marginal’ depends
on a combination of many factors, economic, technical and political, and is not
necessarily indicative of the size of the field. A useful definition of the three terms would
be:
Commercial — The prospect yields an economically attractive rate of return to the oil
company when conventional technology is applied to its exploitation.
Uncommercial — The prospect is unlikely to yield an economic return to the oil company under
any foreseeable technical or fiscal scenarios.
Marginal — The prospect may be capable of yielding an economic return to the oil
company but only by using some innovative, technical and/or financial
options.
While there is no general rule constituting what is an acceptable return, it appears that
most companies regard a 7% to 15% real rate of return as being ‘marginal’. If the
projected return is less than this level the development is usually postponed, while at
higher rates the project could be expected to proceed.
Oil companies share a characteristic which is common to most economic entities—
they are not charities. It is quite natural that they should develop their more commercial
discoveries first. However, offshore exploration and oil production has now been
underway in the harsh northern latitudes for more than a decade. During that period a
considerable number of marginal fields have been discovered. Indeed many fields which
were quite uncommercial when they were found are now considered marginal as a result
of the dramatic oil price increases since 1973 and recent technological advances.
The purpose of this book is to provide a fairly comprehensive look at the technology
for developing these offshore oilfields which are now considered marginal but which
must be developed in order to ensure the western world’s continued production of
petroleum.
The layout of this book and the order in which the topics are discussed are as follows:
—They are extremely capital intensive because of their massive size. Unfortunately,
decreasing the topside loads, for smaller fields, will not decrease the size, and hence
cost, of the structure to any appreciable extent. This is because up to 80% of the mass
of the structure is acting to resist the environmental forces of waves, current and wind.
—They are site specific—when a field is depleted a fixed structure becomes a major
liability. Again, this is not a problem if the field is in production for the 15 or 20 years
typical of large offshore developments.
However, when one considers a marginal field which may only produce for three
to seven years, the non-revisability of a fixed platform which cannot be
redeployed has to be amortised over the brief life of the field.
The alternative approach to the use of fixed platforms is to consider the use of what we
call ‘Marginal field technology’, i.e. technology which aims to have the following
characteristics:
—Low capital cost—this generally involves a trade-off with higher operating costs and
decreased reliability.
—Rapid development period—thus reducing the time from start of expenditure to first
oil.
—Suitability for short-term use—thus promoting mobility and reuse of the system on
other fields.
—Amenable to innovative financing.
The different marginal field technology options are discussed in the following chapters,
but first let us consider how many of the offshore developments of the next two decades
will be of the marginal field type.
So far most of the development in the North Sea has been concentrated on the larger,
easier to find deposits. The discovery of many further fields of the size of Brent or Forties
is considered unlikely. The cushion of steeply rising oil prices is most unlikely to offset
TABLE 1.1
Likely Number of Future Offshore Developments
in UK Continental Shelf
Size of field (millions of bbls) Number of future developments
Under 50 50
50–100 20
100–150 10
200–500 5
500–1000 1
Over 1000 —
Source: Offshore Business, Vol. I, 1983, Hoare Govett.
Technology for developing marginal offshore oilfields 4
TABLE 1.2
Some W.European Offshore Discoveries and
Development Prospect
UK: Fields with development possibilities
Name/block Operator Notes
number(s)
West Heather Union Oil discovery separate from main Heather structure. May contain
2/5 around 15 mn barrels recoverable
Emerald 2/10a, Chevron/ Oil discovered ’74, declared commercial under new tax regime.
2/15 & 3/11b Sovereign Plans for an extended production test and for possible floating
production facility. Recoverable reserves 40–50 mn barrels
Lyell 3/2 Conoco Oil discovered ’75. Requires further appraisal
Columba 3/7 & Chevron/ BP Marginal oil discovery south of Ninian. Talk of single steel
3/8 platform tied back to Ninian, but no decision expected until
results of extended production test planned for 1985 are known.
Recoverable reserves 100 mn barrels
Bressay 3/28a & Chevron/ Heavy oil discovery. Feasibility study underway
3/27 Lasmo
Bruce 9/8a & Hamilton/ Gas/condensate field plus small oil reservoir. Development,
9/9b BP hindered by lack of pipeline in area, unlikely before late ’80 s.
Estimated 100–150 mn barrels of condensate plus 2.4 Tcf of gas
Southwest Beryl Mobil Feasibility study by John Brown Offshore is said to be
9/12a & 9/13 concentrating on a floating production facility. Recoverable
reserves 60–100 mn barrels
Crawford 9/28a Hamilton Oil discovery. Further appraisal expected
& 9/29a
Scapa 14/19 Occidental Engineering studies undertaken by John Brown Offshore and
McDermott. Hope to get annex B approval for a subsea
development tied back to Claymore in late 1985. Recoverable
reserves 35 mn barrels
—14/20 Texaco Small oil field close to Tartan. Subsea development planned
Central, East & West Marathon Several structures undergoing appraisal. Steel platform similar
Brae 16/3 & 16/7a to North Brae likely for 16/3 if reserves are proved
Miller 16/8b Conoco Oil and gas discovery. Approximately 110 mn barrels
recoverable. Might extend into BP block 16/7b
‘T’block 16/17 Phillips Comprises Tiffany, Toni, Thelma and Southeast Thelma.
Tiffany likely to be developed first from single steel platform.
80–100 mn barrels of oil recoverable. May extend into 16/12a
Glamis & Sterling Sun Oil Two small discoveries close to Balmoral currently under
16/21 development. 10–30 mn barrels recoverable, likely to be
developed through Balmoral facilities
Andrew 16/27 & BP Marginal 80–90 mn barrel oil and gas prospect. Annex B
16/28 application for single steel platform could be forthcoming ’85
Ettrick 20/2 Britoil Regarded as high priority by operator, but requires further
appraisal. Talk of single steel platform or floater depending on
final reserves estimate (currently 50–75 mn barrels) into 20/3
Glenn 21/2 Zapex Estimated recoverable reserves 60 mn barrels
Sole Pit 48/13 & Shell Several tight gas accumulations. Could contain 28 bn m3 of
48/14 recoverable gas
—48/21a Lasmo Gas and condensates discovery in 15 m of water. Development
studies underway
31/6 Hydro for this deepwater field are still being considered, but firm plans
are unlikely before ’86. Gas sales talks begun
Munin & Mobil Statfjord satellites likely to be developed using a subsea system
Hugin 33/9 tied back to the main platforms or Murchison. Recoverable
reserves 250 mn barrels oil and 5 bn m3 gas
Snorre 34/4 & Saga Large oil discovery still undergoing appraisal—recoverable
34/7 reserves estimated at 725 mn barrels. Onstream 1993?
Agat 35/3 Saga Oil discovery close to coast, but in deepwater
Tyrihans Statoil Oil discovery on Halten Bank
6407/1
Midgard Saga Halten Bank discovery with recoverable reserves put at 104 bn
6407/2 & m3 of gas, 21 bn m3 of condensates and 876 mn barrels of oil
6507/11
Table 1.2 shows some Western European Fields which are future prospects. Most of
these fields are in the marginal category.
Thus the outlook is extremely promising for the development of increasing numbers of
marginal offshore fields. However, according to the controller at Esso Exploration and
Production a 25% reduction in the current cost of developing North Sea fields of 50
million barrels recoverable reserves is necessary in order to make them economic.
It must also be borne in mind that every offshore development involves the State as a
partner, either indirectly through the various combinations of taxes and royalties, or
directly by reason of state participation agreements. Any change in the fiscal environment
can affect the economics of an offshore prospect much more rapidly and effectively than
developments in technology. This is clearly evidenced by the boost given to marginal
field developments by recent favourable changes in the tax code. Similarly, a drop in
interest rates or increase in oil prices can dramatically improve marginal field economics.
Finally, it is worth remembering that changes in technology, capital costs, the oil
price, tax rates, interest rates etc. will not eliminate marginal offshore oilfields. These
changes will merely shift the margin to put even less attractive accumulations into the
‘marginal’ category.
—Exploration drilling: discovering where the oilfield is and what the characteristics of
the oil reservoir are;
—Oil and gas production: recovering the petroleum from the reservoir and getting it to
market.
Let us consider the technology involved in each:
Exploration Drilling
Since that first offshore well in 1946, exploration drilling has advanced rapidly. Today
drilling is conducted all around the world in all types of environment and in very deep
waters. Wells have been drilled in areas which experience 35 m waves, 6 knot currents,
120 knot winds, in water depths of 1000 m, 400 km offshore and in areas of icebergs and
icefloes. Figure 1.1 shows current and future active exploration areas.
The first offshore exploration well was drilled from a fixed wooden structure.
Operators soon realised that drilling wells from a structure which could be moved from
one location to the next would be much more efficient than installing a permanent
structure for a well which could easily be a dry hole.
The mobile offshore drilling unit was the result. This consisted initially of a barge
which could be deballasted to rest on the sea floor and piled in position. The dry upper
deck supported a drill rig arrangement almost identical to that used on land. These
submersible units were obviously very limited as to the depths of water in which they
could operate.
Later the jack-up drilling unit was developed. This consisted, essentially, of a barge-
shaped structure with legs which could be lowered to the sea bed; it was equipped with a
jacking mechanism which enabled the barge, with drill rig and wellhead on top, to be
raised above the sea surface and so provide a stable drilling table. Early jack-ups were
confined to shallow water depths and the sheltered environments of the Gulf of Mexico
and Venezuela. Continued development of these units has produced a current generation
which can drill in harsh North Sea environments in water depths up to 100 m.
Nevertheless, since jack-ups are founded on the sea bottom they are inherently limited in
the water depths in which they can operate. By moving the wellhead to the sea floor and
by drilling from a floating vessel operators realised that the depth limitations of the jack-
up could be overcome. However, when drilling from a vessel floating on the surface it is
apparent that the heave, pitch and roll motions (i.e. vertical and lateral) must be
compensated for to enable the drill bit to stay on the bottom of the hole with the proper
weight and rotation. This was accomplished by developing vessels which had reduced
motions in waves and by mechanisms to compensate for the vessel’s heave and so allow
drilling to take place in open waters. The two basic floating drilling vessels which have
evolved are the ship shaped drilling unit and the semi-submersible.
The ship shaped drilling unit: these are self-propelled and have the
appearance of conventional sea-going ships with a drill rig on top. The
advantage of these units relates to their deep water capability, their
capacity to transport huge supplies of drilling equipment and their
comparatively low cost. However, the current generation of drill ships
have difficulty in operating in rough seas.
Technology for developing marginal offshore oilfields 14
The different kinds of offshore drilling unit are illustrated in Fig. 1.2. A comparison of
the typical motion characteristics of semi-submersibles and ship shaped units is shown in
Fig. 1.3. Water depth records for offshore drilling operations since 1960 are illustrated in
Fig. 1.4.
depths increased these structures became ever larger and it became increasingly
expensive to fabricate a platform for each individual well. The logical solution was to put
all the wells on a single platform and to drill deviated wells. (Sea extensions of the
Huntingdon Beach field in Southern California were tapped by directional wells drilled
from beach locations as early as the 1920 s.)
With modern techniques it is possible to reach deviations up to 60° so that the
reservoir is drilled in the optimum way (see Fig. 1.5). Plotting the water depths in which
platforms have been installed on a log scale against the year that the offshore installation
started the result obtained is that of a linear trend (see Fig. 1.6). A similar line can be
drawn for exploration wells drilled with mobile drilling units. The lines are found to
deviate. The explanation is that with floating drilling techniques the capacity to drill in
deeper waters advanced faster than the capacity to install fixed offshore structures. Two
factors cause the gap to widen, namely cost and lead time. The cost of drilling in 100 or
300 m of water is not strongly dependent on water depth whereas for fixed platforms it is.
Technology for developing marginal offshore oilfields 18
The progress of fixed structures is shown graphically in Fig. 1.8. It appears that the limits
may soon be reached for these fixed structures. They are costly and difficult to fabricate
and install and lead times become excessively long.
In view of the increasingly massive size of fixed structures as water depths increased it
is not surprising that companies have looked for alternatives. One possible solution
consisted of utilising the experience with drilling units—semi-submersibles and ship
shapes—to arrive at a floating production solution. The first floating production unit was
installed in 1975 on the Argyll field in the North Sea. Since then many more such
systems have been developed and refined. The various floating production systems will
be examined closely in later chapters.
Another school of thought believes that the solution lies somewhere between the
completely fixed structure and the floating production unit. Accordingly various hybrid
type structures have been proposed. Three such hybrid types have already been
developed and installed. These are the Guyed Tower (installed on the LENA field, 1983),
Technology for developing marginal offshore oilfields 20
The third alternative is to eliminate the need for any topside facility and to transfer all
operations to the sea bed. Subsea wellheads were installed in the early 1960 s and since
then there have been considerable developments in subsea technology, underwater
control systems etc. and rapid development of the depth capabilities of underwater
completions. See Fig. 1.9 for an illustration of water depth records for subsea production
since 1960.
The challenge of marginal fields 21
design and technology had a major part to play in the history of offshore production; the
major milestones in their development are discussed in Chapter 2.
Once oil is produced there is still the problem of bringing it ashore. Two methods are
commonly used—pipelines to shore and offshore loading into tankers. The technology of
offshore pipelines has kept pace with other offshore developments. Pipelines have now
been successful in over 500 m of water in the Mediterranean.
While pipelines have low operating costs they can involve a large capital investment,
especially for remote offshore fields. Offshore loading systems have also developed over
the years. Originally confined to sheltered coastal waters and estuaries, they are now
operating in some of the harshest offshore environments. The major milestones in the
developments of offshore loading systems are discussed in Chapter 2.
Chapter 2
Elements of a Marginal Field Development
Scheme
In this chapter we shall examine the various components which, connected together, go to
make up a marginal field development system. The development system may be broadly
divided into the following items:
—production support,
—riser,
—subsea equipment,
—crude oil storage,
—export system.
It must be emphasised at this point that the division made above is only to facilitate
analysis of the various components and that production systems for individual fields are
integrated performing an overall function rather than a series of separate operations.
2.1.1 Jack-ups
Jack-ups are normally used in drilling operations but may be used as a production support
where topside weight and water depth are not limitations. The jack-up consists of a deck
section, somewhat like a barge, and several truss or tubular telescopic legs. It is normally
towed to the location with the legs raised. On site, the legs are lowered to the sea bed and
the platform is then jacked up to safe level above the sea. One prerequisite for the use of
Technology for developing marginal offshore oilfields 24
this type of support is the suitability of the sea bed soil conditions and the likely
penetrations of the legs (Fig. 2.1).
The normal water depth operational range of the jack-up is from the seashore to 75 m;
however, the latest generation of jack-ups, the Gorilla class, are able to operate in water
depths of up to 110 m and sea states of up to 30 m wave heights.
A jack-up has been used in only one North Sea development scheme, Ekofisk, where
the Gulf Tide was used as a production support in an early production system for three
years in a water depth of 70 m.
The advantages of using a jack-up as a production support are as follows:
—Jack-ups are leaseable and with a worldwide utilisation rate of 76% day rates are very
competitive.
—Fatigue problems could limit the utilisation to several years unless costly alterations
are made to the structure.
—No storage capability.
A typical example of a field development using a jack-up as a production support is the
Espoir field offshore Ivory Coast. The development was carried out by Phillips Petroleum
and utilised a converted jack-up drilling rig, the Dan Duke, which was leased in Japan
after a 600 ton production module was installed in 1982. The development system
incorporates the following features:
—the use of the Dan Duke as production support,
—a special driven caisson riser housing,
—deepwater, widely spaced subsea wellheads for production in 120–150 m of water,
—deepwater pipelines laid by the reel method from a dynamically positioned reel ship,
—saturation diving for subsea wellhead hook-up from a dynamically positioned diving
support vessel,
—CALRAM field storage tanker,
—shuttle tanker off-loading.
The Dan Duke stands in 130 m of water and is designed to receive through a 1.8 m
diameter riser caisson, twelve 8 in. diameter flowlines and one 12 in. export line to a
Catenary Anchor Leg Rigid Arm Mooring (CALRAM), essentially a tethered buoy to
which is pin connected the Phillips Enterprise, a 230000 dwt. VLCC. An estimated
300000 bbls of processed crude can be stored aboard the Phillips Enterprise. A detailed
field development sketch can be found in Chapter 3.
The project was begun in 1980 with the conversion of the Dan Duke; the addition of
the production module was commenced in 1981 and was completed in early 1982.
2.1.2 Semi-submersibles
Until now this has been the most popular form of floating production support, with 19
fields (see Chapter 3) having been developed using semi-submersibles.
The semi-submersible type of production support is a buoyant structure which is
catenary (conventionally) moored to the sea bed. These moorings allow large heave
motions in extreme environments and impose severe problems on the riser configuration
often resulting in poor production efficiency. In high sea states the riser is disconnected
from the subsea system and recovered on the platform or ‘hung-off’, i.e. suspended from
the platform.
There are many configurations of semi-submersible but they all consist of a vessel
with a majority of its displacement some distance under water and with small cross-
sectional area members piercing the water surface.
The advantages of the semi-submersible are as follows:
—The motions of the semi-submersible are small, and therefore it can be used in severe
environments.
—There are many semi-submersibles available for conversion.
—Low abandonment cost, and can be returned to drilling.
—Mooring is normally of the conventional catenary type.
Technology for developing marginal offshore oilfields 26
production from Buchan began in May 1981 with design production being achieved in
July, 1981.
2.1.3 Tankers
This type of production support consists of a tanker converted for production operations
with a permanent yoke attachment to a single point mooring (SPM). There are various
types of SPM that have evolved from the basic catenary anchor leg mooring (CALM) and
single anchor leg mooring (SALM); the two types used to date are the single buoy
storage (SBS) and the single anchor leg storage (SALS). These systems will be examined
in detail in the section on export systems.
The tanker is allowed to weathervane around the SPM by means of a fluid swivel
arrangement at the yoke/SPM interface. The production riser extends from the sea floor
to the fluid swivel. A converted tanker is used because it provides the cheapest form of
floating platform and already has existing oil storage capacity. This storage capacity is a
major factor in the operation of this type of system as it increases production efficiency
by providing buffer storage when the weather prohibits offloading by shuttle tanker.
The advantages of a tanker based system can be summarised as follows:
—Large capacity in terms of weight carrying.
—Large area for process equipment installation.
—Large capacity for storage of products.
—Oversupply on the market, therefore cheap to buy.
—Easily converted to a production support.
—Includes adequate accommodation.
—Easy loading of shuttle tanker from production tanker.
—Ability to withstand 100yr storm conditions while continuing production.
The disadvantages of a tanker based production system are:
—No possibility of work-over operations (exception: Castellon).
—Moored tankers are subject to large motions, therefore the mooring system must
incorporate the concept of weathervaning.
—The mooring must be combined with the riser system.
—Maximum number of wells is currently 8.
—Operational water depth is 50–150 m.
The Tazerka field development incorporates the latest in technology relating to tanker
based production systems. The field was discovered in July 1979 by Shell Tunirex
operating for a joint venture with Agip (40%) and Entreprise Tunisienne d’Activites
Petrolieres (ETAP 20%). It is situated some 56 km offshore Tunisia in water depths of
140–300 m in the Hammemet Grand Fonds permit.
The production system includes the following elements:
—A converted 210000 dwt. tanker Murex as a production support.
—A production riser system consisting of eight 4 in. production risers and eight 4 in.
service lines.
Technology for developing marginal offshore oilfields 28
—A single anchor leg storage (SALS) system including a 25 m across, 7 m high gravity
base through which the flowlines from the wells pass into rigid steel piping.
—A series of subsea wells (4) connected to the base by flexible flowlines.
—A 250 ton manifold chamber installed above the yoke used for tanker mooring.
—A 6×4 in. multi-path high pressure swivel specifically designed to accommodate
facilities for production, testing, gas-lift and water injection while permitting the
production tanker to weathervane.
The Tazerka field was the first to utilise a multi-well concept necessitating a high
pressure multiple path swivel. The SALS consists of a structural member 140 m long, 5
m in outer diameter with an inner well of 2.2 m diameter which contains all the conduits
and control lines for the wells. The fluid-path coupling across the unijoint at the base is
by a jumper hose arrangement from steel pipe on a frame on the base to steel pipe
extending from the bottom of the riser.
Tazerka, having recoverable reserves of 10 m barrels, began producing in 1982 and
reached its designed production capacity of 10000 bbls/day in 1983.
—Low payload capability, it is unlikely that an articulated column could be used alone as
a production support.
—No work-over capability.
—No gas lift or water injection capability.
The only development utilising an articulated column as a production support is the
North East Frigg field developed by Elf. North East Frigg is a marginal field 18 km from
the Frigg field, the reserves of which were not sufficient to justify a traditional
development.
The development incorporates the following elements:
(1) A subsea station which includes the wellheads for six clustered gas producing wells, a
manifold, the control umbilicals and the 16 in. export line to the Frigg field. The
equipment is protected by a heavy subsea template (20 m×30 m×8 m, 350 tonnes)
piled to the sea bed.
(2) The field control station (FCS) consists of an 8 m diameter articulated steel tubular
column installed in 100 m of water and located 150 m from the subsea station. The
function of the FCS is to house the equipment required to
—convert electrical signals from the Frigg field into hydraulic pressures for operating
the subsea gas production valves;
—control closely the wells through individual 2 in. kill lines;
—periodically leak test the production tubing safety valves in each well;
—inject continuously hydrate inhibitor into wells during gas flow.
(3) Six specially designed umbilicals, each consisting of one 2 in. tube and twenty
tubes, link each christmas tree to the deck of the FCS.
(4) The North East Frigg facilities are linked to TCP2 Frigg field platform via a 16 in. gas
line.
The field development was begun in 1981 with the construction and installation of the
subsea template and manifold. The wells were drilled in 1982 and completed in 1985;
assembly and installation of the FCS took place in 1983. The total system was
commissioned in 1984 and production began in that year.
The North East Frigg production support is designed for unattended operation.
Routine maintenance is carried out by personnel from the Frigg platform as required.
wires will allow the structure to tilt without seriously affecting the tension of the wires
(Fig. 2.3).
The guyed tower has the following advantages:
—In similar water depths it is much cheaper than conventional platforms.
—It is easy to build because of repetition of design joints.
The disadvantages are:
—Unproven technology.
—Limited payload.
—No storage.
—Installation and maintenance costs of guy wires unknown.
—Guy wires may snarl fishing trawls.
There has been only one development incorporating a guyed tower as a production
support; that is Mississippi Canyon Block 280in the Gulf of Mexico which has been
developed by Exxon. The site is in 300 m of water and lies approximately 183 km south-
east of New Orleans.
Twenty guy lines secure the tower to the sea bed and allow it to comply with wind and
wave forces. Each of the guys is 520 m long and is terminated on the sea bed by 200 ton
weights. The weights are joined together on the sea bed somewhat like bicycle chain
links. Anchor lines 400 m long extend from each clump to an anchor pile. The production
equipment provides separation, oil treatment, gas dehydration and compression for
50MMcfd of natural gas, 30000 b/d of oil and condensate and 10000 b/d of water. Eight
Technology for developing marginal offshore oilfields 34
main piles have been driven through the centre of the tower into the sea bed to support
the weight of the structure and an additional six 1828 mm diameter piles were driven
around the outside of the tower to keep it from twisting.
The tower was loaded out and installed in July 1983 and production began in early
1984.
TABLE 2.2
Comparison of Four Tanker Based Marginal
Production Systems
Installation Vessel Mooring Water Wave Production Number Excess gas
site size type depth ht. capacity of wells disposal
(dwt.) (m) (max., (b/d) (max)
m)
Castellon 60000 SALS 117 15 20000 1 Incinerators
field (Spain)
Nilde field 80000 SALS 90 18 20000 1 Vent Stack
(Italy)
Cadlao field 127 000 SBS 90 17 30 000 2 Ground
(Philippines) Flare
Tazerka field 210000 SALS 140 18 20000 8 Vent System
(Tunisia)
Source: Carter, H.T. and Foolen, J., Evolutionary developments advancing the floating production,
storage and offloading concept. OTC 4273, Offshore Technology Conference, Houston, Texas,
1982.
TABLE 2.3
Factors Affecting Choice of a Marginal Field
Production Support
Drilling/ No. of Environmental Water depth Type of support
workover wells conditions (m)
Mild/moderate 300 DP tanker with workover
rig
One Severe 700 Conventionally anchored
semi-sub
Yes
There are a large range of design tools available for the selection and testing of the
various elements of a marginal production system. Computer programs have been
developed which can accurately predict the motion characteristics of various production
supports under the influence of forces generated by specific environmental conditions.
These programs can examine several mooring configurations and check riser
configurations.
Table 2.1 and 2.3 summarise the characteristics of the various production supports and
give an indication of the conditions under which each support can be used.
Table 2.2 compares four tanker based production systems.
2.2 RISERS
The riser is one of the most important and complex items in any offshore development,
floating or fixed. Before proceeding to an examination of the various riser systems
currently being used it is perhaps useful to examine some of the terms used in connection
with risers.
Definition—‘riser’ is a generic term describing a single tubular or a series of tubulars
connecting a sea bed termination to a facility at, or above, the sea surface. The term
applies whether fluids are moving upwards or downwards.
In general there are five possible riser systems:
(a) production riser system,
(b) drilling riser,
(c) workover riser,
(d) wireline riser,
(e) product sales/export riser.
(b) at the upper end, the fluid off-takes and the tensioners including compressors and
controls.
Also included in the production riser system are such items as the RCP test stump, riser
test equipment and all riser handling, running and pulling equipment which supplements
the derrick, draw-works and outfitted cranage.
Riser Bundle
This includes all the tubulars, any structural members, buoyancy collars, guide funnels,
individual line tensioners, articulated joints, telescopic joints etc. which make up the
completed production riser system in its operational form, but excluding the main
tensioning system and the fluid off-take flexibles.
(f) Service riser—one or more lines which have several duties, the more important of
which are the hydraulic testing of the connected riser lines and flushing out of riser
lines prior to pulling.
(g) Hydraulic control lines to control well functions, riser hydraulic connectors, air can
monitoring and control.
Riser Joint
This is one finite length of fluid conductor between connections; these connections may
be screwed, bolted or may have ‘dogs’ or latches.
Stand
This consists of two or three joints made up to 100 ft in length, the stand being stowed in
the derrick rack. The handling of stands obviously reduces riser running/pulling times.
This operation is similar to drill pipe handling during drilling.
Since the Argyll production system utilises a tanker offloading system and because
there is no storage capacity in the production support, the limiting factor for riser
disconnection is the sea state at which the tanker would have to disconnect from the
mooring buoy. However, operational experience has shown that tanker disconnection is
not the limiting factor but the heave of the semi-submersible is in fact the over-riding
design parameter. A maximum semi-sub heave of 2.0 m leads to riser disconnection; this
heave occurs at wave heights well below the design case for tanker disconnection.
line is supported by a tension collar to which eight riser tensioners are connected. A
gooseneck mounted on top of the riser carries the 12 in. hose which connects to the semi-
sub. At the bottom, the export line is flanged to a universal joint which is fixed to the
subsea manifold by a connector. The peripheral lines are also built in 50 ft lengths. Four
tensioners provide the tension for the peripheral risers by distribution through a system of
bridles.
The Buchan riser is designed to permit production in sea states of up to 5 m significant
wave height and to remain connected in sea states of up to 6.5 m significant wave. The
design wave height for riser disconnection is 7 m whereas the design wave for
disconnection of the loading tanker is 5 m (see Chapter 5).
Elements of a marginal field development scheme 43
—An interlocking spiralled steel carcass (layer 1) provides resistance to crushing and
prevents deformation of the pipe.
—An inner thermoplastic sheath (layer 2) and an outside thermoplastic sheath (layer 5)
composed of polyamide II render the riser leakproof.
—An interlocking zeta spiral (layer 3), called the pressure armour, ensures the inner
Rilsan sheath’s binding and the integrity of the structure’s internal pressure.
—Two cross-armoured steel wire layers (layer 4) provides resistance to pulling and
longitudinal stresses induced by internal pressure.
The quick connect/disconnect coupling is used to disconnect the riser quite rapidly (less
than 10 seconds) in the event of an emergency, such as fire, anchoring chain rupture etc.
without risks of pollution.
The plastic bending restrictor is fitted behind the end fitting in order to limit the cyclical
bending movements of the riser caused by the relative motions of the semi-sub.
The riser is anchored so that its position will not be disturbed by the movements of the
semi-submersible platform during its operational life.
The advantages of flexible risers over rigid risers for some applications may be
summarised as follows:
—less investment cost;
—no requirement for riser retrieval in difficult weather conditions, which means less
down time and higher production;
—no sea bottom connection or re-entry which means less maintenance cost;
—more easily and rapidly installed;
—easy extension to system capacity;
—marginal impact on floating vessel design;
—excellent corrosion resistance.
In each bundle all lines are independent and free to move relative to each other.
Ribbon Riser
This type of riser system has been developed by Shell for deep water applications and
consists of a flat array of risers in the form of a subsea
Systems have been designed which have emphasised the compatability of the fluid
transferring equipment with the column and head rotations. This system is particularly
useful in extreme environments and in water depths up to 400 m.
Introduction
The oil industry has always believed in the use of tried and true technology when
designing field developments. One of the cornerstones of oilfield production system
design philosophy has been the requirement to put as much production equipment as
possible ‘in the dry’. This philosophy is well founded in good design practice with such
factors as access, safety, environmental protection and easy operational maintenance
being cited as reasons for this dry equipment requirement. The giant North Sea platforms,
whose function is to house all the equipment associated with production operations, are a
testament to the enduring nature of the ‘all in the dry’ design philosophy.
The industry took its first step into subsea production equipment in the 1950 s when
an ordinary land production tree was installed a few feet underwater. Since then major
Elements of a marginal field development scheme 51
advances have taken place in subsea equipment development and several subsea
production systems are in existence or under test which will greatly extend the range of
application of this technology.
As with offshore loading systems, which are examined in detail in Section 2.5, subsea
production equipment has become a feature of marginal field development schemes.
There are four basic elements in a subsea production system, i.e. template, wells,
manifold and control system. The specific configurations of these elements are defined
by the reservoir characteristics and the other components of the development scheme,
particularly the riser.
required has been fixed and/or several slots can be left empty for future use. Templates
are usually fabricated at a dockside facility and are normally of ‘passive’ or non-buoyant
construction (Fig. 2.11).
Technology for developing marginal offshore oilfields 52
The choice between cluster or satellite wells or indeed a combination of the two is
usually dictated by the reservoir characteristics. The first requirement of any development
plan is that it ensures the most efficient depletion of the reservoir. Cluster wells are
normally deviated wells drilled through a subsea template which may, or may not, be
located directly below the production support. If the field cannot be drained by a cluster
system then a wholly satellite or cluster/satellite combination must be used. A limitation
with satellite wells is the requirement that the reservoir should be sufficiently pressured
in order to ensure flow between the tree and the production support. This requirement
limits the distance a satellite well may be situated from the production support. It is
unlikely that a cluster system would be capable of efficiently draining a shallow
reservoir.
Elements of a marginal field development scheme 53
Because they are integrally linked there is a trade-off between riser and manifold
design. If the riser is required to be simple the manifold must be designed to comingle the
flows of the various production wells or disperse the flow of the various production wells
and/or disperse the flow to a series of injection wells. The more complex the manifold
design the more controls will be required. Conversely if the riser system is designed to
incorporate individual well risers this substantially reduces the complexity of the
manifold. The design of the riser system and the manifold are thus inextricably linked.
Other factors which influence manifold design are the nature of the product
(oil/gas/condensate), the number and location of the wells, the maximum allowable
pressure drop, the maximum flowrate required, the maintenance system employed (TFL
or non-TFL) and the need for pipeline pigging/scraping from the floating unit.
Manifolds, like christmas trees, can be either wet or dry. In the wet configuration the
manifold is open to the marine environment while in the dry configuration the manifold is
located in a chamber, the interior of which is maintained at atmospheric pressure.
The manifold incorporates a further function which is of great importance. The riser
base is usually located on the manifold and is surmounted by an assembly which permits
the remote disconnection or connection of a number of lines. This element of the
manifold is extremely important for marginal field systems employing floating
production supports and has been the subject of considerable study in the past five years.
Garoupa, which is located 260 km east north-east of Rio de Janeiro, is the world’s largest
subsea production system using equipment installed in dry, atmospheric chambers
located on the sea bed at water depths ranging from 118 to 165 m. The system is
currently producing some 23200 b/d of oil (Fig. 2.13).
The system consists of two major components, the wellhead cellar (WHC), a dry 1-
atmosphere pressure chamber which houses the production tree and control equipment,
and a dry 1-atmosphere manifold centre.
The Garoupa wells were drilled and completed by a conventional semi-submersible.
The wells were completed in such a way as to leave them live. After setting the down-
hole safety valve and locking the tubing plugs the BOP stack was removed and the
wellhead cellar was keelhauled to place it in position beneath the drilling slot of the semi-
sub. The WHC was then picked up by the drillpipe and lowered to the ocean floor where
it was mated with the conductor pipe, using the same profile as the BOP stack. The WHC
was made fast by actuating the hydraulic connector.
Elements of a marginal field development scheme 55
project, i.e. removing production equipment from a dry surface environment to a dry
subsea environment, was logical and correct. The operation of the system has been
carefully monitored by Petrobras and figures presented show that the manifold centre has
been available for production 98% of the time. Down time for the WHCs has varied from
unit to unit with an average time on production of 96%. These figures would seem to
indicate that the subsea production system was not a limiting factor in field down time.
This development constitutes the current state of the art in subsea production systems
since it includes all the elements, e.g. production, delivery, control, maintenance and
reservoir pressure maintenance, associated with offshore operations. The structure was
installed in May 1982, drilling began in October 1982, and production started in mid-
1983. The operational experience with the UMC should establish the viability of subsea
manifold systems.
hydraulic system is utilised where it is needed most, i.e. subsea. Control pods are
normally designed and installed for easy removal if repairs are required. Disadvantages
include high cost, complexity, increased maintenance and limited experience.
The use of subsea components in offshore field developments can now be considered as
established technology. Many fields worldwide incorporate satellite wells (whether wet
or dry) and a greater level of confidence is available for systems employing subsea
templates and manifolds. TFL techniques, although not widely used to date, have been
accepted as a viable method for down-hole intervention.
One of the major problems associated with the viability of subsea production systems
is the lack of understanding of the two-phase flow mechanism. This lack of
understanding has thus far limited the distance of satellite wells to approximately 18 km
from the point at which the crude is processed.
Technology for developing marginal offshore oilfields 62
TABLE 2.5
List of Fields Employing Subsea Production
Technology
Satellite Completions Satellite to subsea Completions Template and long life
or riser manifold systems
Beryl (4) Argyll (8) Cormorant (9+)
Central
Casablanca (2) Buchan (7) Grondin (2)
Claymore (3) Castellon (1) Frigg N.E. (6)
Cormorant Dorado (2)
Emilio (1) Espoir (5) Total 17
trees
Lavinia (1) Nilde (1)
Magnus (7) Tazerka (6/8)
Murchison (3)
N.Hewitt (2) Total 30 trees
Ninian (1)
Tartan (6)
Total 30 trees
Source: The Oilman, March 1983.
Two major research programmes, one in France and one in Norway, are underway
with a view to gaining a better picture of the two-phase flow mechanism. The empirical
information obtained by these programmes has led to the development of computer
programs which can predict two-phase flow patterns. This type of information is
necessary for two-phase flow pipeline design.
The French research programme has led to the development of a pump capable of
handling two-phase flows. The use of a two-phase flow pump would permit the
possibility of production from satellite wells or fields far distant from the point of crude
oil processing.
A major problem area for subsea production systems is undoubtedly associated with
the control and repair and maintenance functions.
Research programmes are currently underway to improve wellhead control systems,
particularly by employing more accurate transducers. Skuld and other subsea test stations
can be used to establish repair and maintenance procedures, and will inevitably lead to
improvements in equipment design.
Marginal field developments, especially those small fields associated with larger finds,
will make substantial use of subsea production technology. The development plans
accepted for the Texaco Highlander field and Hamilton’s Duncan field shows industry
and government acceptance of subsea technological advances. The research and field
Elements of a marginal field development scheme 63
testing stage of this technology is coming to a close and the experience with the existing
producing systems should form the cornerstone of the future designs.
The Poseidon concept opens up new and exciting horizons for subsea production and
will lead to a further refinement of technology.
2.4 STORAGE
Introduction
Crude oil storage in relation to marginal field developments invariably means offshore
storage. In other sections, particularly those on production supports and loading systems,
most of the components used for offshore storage are examined.
Offshore storage is normally required because there is inevitably a question of down
time (time during which a system is not operational) associated with offshore loading
concepts. The normal method of crude evacuation is by shuttle tankers which may be
loaded directly from a loading system or via a storage vessel. If no storage is provided
and adverse weather prevents shuttle tanker loading, the platform supervisory personnel
have no option but to shut down field production. The field reservoir characteristics are
not always consistent with this stop-start type of production so some element of buffer
storage must be considered. The exception to this rule has been Argyll field which has
been subject to this stop-start production rhythm but has suffered no damage as a result.
Several aspects of crude oil evacuation must be examined before a suitable buffer
storage system is selected. Among the factors to be considered are:
—storm occurrence interval and persistancy,
—throughput of oil,
—distance of the field from port of discharge,
—speed of the shuttle tanker,
—number and capacity of the shuttle tanker(s),
—efficiency of discharge port equipment,
—loading system maintenance down time (hoses, hawser, etc.).
The environmental factors will, of course, have a bearing on the type of storage structure
selected but the factors listed above govern the quantity of storage required.
Four basic structures suitable for offshore storage include:
—tanker,
—barge,
—articulated column,
—spar.
Articulated columns have already been considered as production supports and will later
be extensively examined as loading systems.
The storage capacity of the articulated column is a byproduct of the column’s
geometry. The articulated column can have a very substantial (depending on the design)
underwater tubular structure which has both buoyancy and stability functions. This
structure, which can be considered as hollow, can be arranged into a series of storage
compartments which can be used for buffer storage if tanker loading is interrupted.
The Maureen Articulated Loading Column, which is examined in detail later, is a steel
concrete hybrid structure 148 m high with a column outside diameter of 10 m. The
column has been designed to incorporate a buffer store of 650000bbis.
2.4.5 Conclusions
Offshore storage capacity is generally sought in those circumstances where loading
system down time can lead to production shut-in. The various concepts on offer are based
on well proven technology and can easily be adapted to whatever loading system has
been selected. Several loading system designs, particularly SPAR type structures, have
the inherent capability to act as buffer storage.
When used simply as buffer storage, all the systems examined above have proven
operationally successful and have in no way been a limiting factor in the overall
production system’s performance.
Introduction
A notable feature of all marginal field and early production systems is the use of an
offshore loading facility for crude oil export. Unless the marginal field is close to shore or
in the vicinity of an existing pipeline system with spare capacity, offshore loading
constitutes the optimum solution, both in terms of technology and cost.
Offshore loading technology has been developed from the use in the 1960 s of buoys
for crude oil transfer from tankers to refinery tank storage. The development of this
technology was necessitated by the inability of very large crude carriers (VLCCs) to dock
at existing port facilities due to draft limitations.
The extension of the technology to encompass the offshore loading of crude oil was
developed in order to eliminate the requirement for sea-bed pipelines and booster stations
and thereby reduce investment costs.
Technology for developing marginal offshore oilfields 66
One of the major drawbacks of a mooring buoy loading system is its sensitivity to
environmental conditions. During storms or high sea state conditions, tankers are unable
to moor safely and therefore production must be suspended, sometimes for extended
periods, until the weather improves sufficiently to resume operations.
A solution to this problem is to provide crude oil storage capacity, generally in the
form of a permanently moored tanker, so that production stoppages are eliminated. The
technology has, therefore, evolved on two fronts. First, the development of ‘mooring’
buoy technology and, second, the adaptation of the buoy technology to the provision of
some level of buffer storage.
There are four basic configurations of offshore loading systems with variations
applicable to specific development criteria. The following is a list of the systems
including, where possible, a specific field application.
(a) Catenary anchor leg mooring (CALM)—Buchan field, derivatives include:
—exposed location single buoy mooring (ELSBM)—Auk field,
—SPA—Brent field,
—single buoy storage (SBS)—Ashtart, Tunisia,
—turret moored tanker.
(b) Single anchor leg mooring (SALM)—Thistle field, derivatives include:
—single anchor leg storage (SALS)—Castellon and Tazerka.
(c) Articulated loading column (ALC)—Maureen and Beryl.
(d) Fixed tower—Cayo Arcas.
marginal field or early production, product lines are normally in the range of 8 in. to 12
in. The swivel associated with the loading system must be designed to accommodate the
fluids and withstand their pressures. The transferred fluids may consist of processed
crude, live crude oil and gas directly from the well, natural gas for fuel, hydraulic fluids
for valve control, treated associated water and liquid petroleum gas (LPG). The swivel
must also be designed to handle the various pressures associated with the fluids being
transported. These pressures may vary from 225–275 psi for processed crudes to much
higher pressures for live crude and hydraulic lines (1200–2000 psi).
Most of the offshore loading systems are designed for 100% occupancy, that is they
must be available continuously for fluid transfer. The overall design of the system must
reflect this criterion. In addition, routine and preventative maintenance procedures,
excluding hoses and hawsers, must be designed for execution with the tanker on the
mooring.
Once the export or storage tanker has been selected the forces it will exert on the
loading system can be calculated and the system designed to accommodate those loads.
TABLE 2.6
Main Characteristics of some CALM Terminals
Terminal Location Water Tanker Flow rate Oil piping Buoy
depth size (dwt.) (m3/hour) size (in.) diameter
(m) (m)
Rospo Mare Adriatic Sea 22 35000 50 1×12 9
(Italy)
Abu al Persian Gulf 28 230000 530 2×10 12
Bukhoosh (Abu Dhabi)
Panama (2 Chiriqui 23 Up to 9500 2×20 11
buoys) Lagoon 150000
(Panama)
Victoria Gulf of Guinea 57 50 to 5000 2×20 12
280000
Pampo Campos Basin 125 50000 250 1×8 13
(Brazil)
Source: EMH.
which posed the threat of wax build up should the flow be curtailed and the crude
allowed to cool.
—Two tankers are dedicated to the field minimising the risk of production shut-down.
—The hook-up and departure procedure is designed so that no assistance from small craft
is required.
—A self aligning quick hose connector is being used to attach and detach the floating
hose from the buoy’s pipearm. This system greatly simplifies installation and
maintenance by limiting the need for divers and calm sea conditions.
—The buoy’s deck equipment includes a chain jack for retensioning any of the buoy’s six
anchor chains. With this equipment, the anchor chains can be retensioned to the
appropriate catenary shape while avoiding the need for crane barges and other costly
installation equipment (see Chapter 5).
2.5.4 SPAR
The SPAR concept has been developed and utilised exclusively by Shell. SPAR is
another adaptation of CALM technology incorporating some of the features of the
ELSBM with the ability to store crude oil. However, the structure as a whole is
considerably larger than any loading buoy. The storage concept requires that the main
storage tanks are kept full of either crude oil or sea water or a combination of both (Fig.
2.16).
and is located 2.9 km from Brent ‘A’. The structure can be divided into two sections, the
substructure and the superstructure.
The substructure is 29.1 m in diameter and 93 m high and is divided into 18 tanks, six
storage tanks and twelve buoyancy tanks. It floats below the water surface at a design
draught of 109 m. The draught of the structure is controlled during all loading operations
so that structural stability is maintained.
The substructure is surmounted by a column which connects the underwater storage
vessel with the superstructure. The column is 17 m in diameter and 32 m high and
protrudes above the surface. A free floating central shaft of 3.4 m diameter extends from
the superstructure to the base of the substructure.
The superstructure is 26 m in diameter and 12 m high. It contains four decks and
supports a turntable with cargo crane, loading swivel, helicopter platform and mooring
arrangements. The superstructure also includes accommodation for 30 people, 12 normal
crew with additional space for personnel required for diving operations or major
overhauls.
Processed crude is received continuously from the nearby platforms and is transferred
to the SPAR unit from a pipeline end manifold located directly below the structure. The
structure is held in. position by six anchor chains and wires terminating at six 1000 tonne
concrete gravity anchor blocks. The SPAR is kept at constant draught by keeping the
storage tanks filled. If crude is not available for filling the tanks sea water is used.
Loading from the Brent SPAR is usually suspended when sea states exceed 8 m and
wind speed 40 knots. The Brent SPAR was installed in June 1976.
contrast, the restoring forces in a conventional CALM are functions of the weight and
spacing of the catenary draped anchor chains supported above the sea bed by the
displaced buoy body. As with all mooring buoy designs the buoy in the SALM
incorporates a 360° swivel in the horizontal plane which allows the loading vessel to
weathervane so as to take up the position of least resistance to the combined forces of
wind, waves and current (Fig. 2.19).
The advantages of the SALM system are:
—It is applicable to a wide range of water depths.
—Because a gravity or piled base is used to locate the riser/mooring system a wide range
of soil conditions are acceptable.
—The major elements of the system can be reused.
—Mooring forces are minimised as the tanker weathervanes about the buoy.
The main disadvantage is that the product swivel is generally located underwater, and
hence divers are required for maintenance and repair.
The primary components of the Fulmar SALM are the buoy, rigid arm, product swivel,
base and the mechanical articulations which connect them.
The anchor leg of the Fulmar SALM is a rigid buoy connected to the base by an
articulated joint and connected at the top directly to the rigid arm through a triaxial
universal joint and mooring swivel. The buoy weighs 1829 tonnes and the outside
diameter ranges from 8 m at the lower end to 15.9 m at the maximum diameter down to
5.5 m at the top. The buoy is sub-divided into 18 compartments to provide damage
stability and a 3 m diameter central column provides access to the various compartments
for inspection and maintenance.
The rigid arm is a box truss triangular structure. The arm weighs 800 tonnes and
measures 61 m in length and is 30.5 m at the hinged connection to the tanker. The arm
carries all the rigid fluid lines necessary to carry out fluid transfer.
The base is of gravity/piled design and consists of a steel hexagonal structure with a
pile located at each corner. The piles were driven to a depth of 29 m and were then
grouted to the pile sleeves in order to resist the environmentally imposed loads.
The universal joint which weighs 360 tonnes connects lugs on the bottom of the buoy
to those on the base structure via two 1560 mm diameter by 7.9 m long tubular pins and a
coupler sleeve assembly.
The Fulmar SALM stands in 82 m of water and is capable of handling approximately
180000 b/d of crude oil and loading tankers at a rate of 40000 b/h. The structure was
installed in May 1981.
The single anchor leg storage system or SALS is a variation of the SALM described
above. The system is based upon a single vertical riser between the sea bed anchor point
and the storage/production vessel mooring yoke. The yoke incorporates a submerged
buoyancy tank or tanks for maintaining a permanent tension force to the riser regardless
of sea state or loading conditions. As in the case of the SALM the articulated single chain
riser (or single tubular riser) is connected by means of universal joints at both the top and
the bottom ends (Fig. 2.20).
Elements of a marginal field development scheme 77
—The principal buoyancy section, which is submerged and stabilises the structure.
—The marine compartment which is a tubular section connecting the buoyancy chamber
with the superstructure. This section is in communication with the surface of the water
and is designed to reduce the wave action forces on the structure and in consequence
the articulation.
—The superstructure, containing the various pieces of equipment necessary to assure the
various functions of the column, particularly a helipad to allow column maintenance.
The columns may be fabricated in steel or concrete or a combination of the two.
The tanker is moored to the articulated column through a rigid yoke or a hawser
depending on the environmental conditions at the site.
The CAT concept is applicable to water depths ranging from 40 to 80 m in severe
environmental conditions.
While the concept is not based directly on articulated column technology, the structure
itself may be architecturally similar to a column but is firmly fixed to the site. The fixed
tower requires some form of fendering to absorb tanker contact (Fig. 2.22).
The system substantially reduces the relative motion between the loading terminal and
the tanker; however, there are limitations in terms of abandonment, initial cost, and site
conditions, i.e. water depth and wave height.
Technology for developing marginal offshore oilfields 82
Yes
−50 Fixed tower
40–80 CAT
Severe 50–200 SPAR/SALS
80–200 ALC
wheel’ fender. This type of fender is necessary because of the possibility of collision
between the fixed tower and the tanker. Since the tower is a permanently located
structure, it is much more vulnerable to collision than moored or articulated structures.
Elements of a marginal field development scheme 83
The processing facilities for an offshore development can vary from a simple separation
and disposal system to a highly complex processing plant utilising miles of inter-
connecting pipework and dozens of processing vessels.
Figure 2.23 shows some possible combinations of process plant which may be required
offshore. The following list of systems is not exhaustive and by no means would every
development use them all. The possibilities include, but are not limited to:
—gathering system,
—separation system,
—oil treatment and disposal system,
—gas treatment and disposal system,
—water treatment and disposal system,
—safety systems,
—utility systems.
connected to a test header. If the field involves wells which flow at different pressures, a
few wells may have insufficient pressure to flow into the first stage of separation. In this
case a low pressure header is provided for these wells, which bypasses the first or high
pressure separator and flows directly to a separator operating at a lower pressure.
As explained in Section 2.3, manifolding may take place at the sea bed or at the
surface, on the production support. Manifolding on the sea bed has the advantage of
simplifying the riser configuration and the associated high pressure swivel arrangements.
Manifolding on the surface, on the other hand, has the advantage of having all the
associated valves and pipework easily accessible and eliminating the considerable
expense associated with diver and ROV systems normally required for subsea systems.
The topside weight associated with manifolding on the surface is a significant item for
submersible based production systems.
The current trend is towards subsea manifolding. This is being facilitated by the
continuing development of ROVs which can undertake all the routine maintenance and
inspection work.
Even if associated gas is re-injected or used to some other purpose, a gas disposal system
must be installed to handle the full volume in the event of a production upset.
Flare booms, which are normally used on fixed platforms, are being used successfully
on production semi-submersibles. The flare on the production platform on the Argyll
field is mounted on top of the derrick.
On the Castellon FPSO, water cooled incinerators are used to burn 2 mmscf/d gas. A
ground flare installation is employed on the Cadlao FPSO to burn 6.5 mmscf/d gas. The
designers claim that designs have been completed for similar ground flares having
capacities up to 50 mmscf/d. For this quantity of throughput the stack would be 11 m
diameter and 22 m high.
Chapter 3
Existing Marginal Field Technology
INTRODUCTION
In this section we will examine those systems which have already been used to exploit
hydrocarbon deposits and which could have widespread applications to marginal field
development.
The list of developments includes fields which have permanent marginal field systems
installed as well as those which have utilised some form of marginal field technology as
an early production system. For example field developments in Brazil have incorporated
some elements of early production but since the systems used have marginal field
applications they have been reviewed for this section.
Thirty-nine field developments worldwide have been reviewed: 7 utilise or utilised a
jack-up as a production support, 19 a semi-submersible, 6 a monohull (barge or tanker)
and a further 7 utilised technologies which are relevant to marginal fields.
A data sheet and field development layout for each of the 39 fields reviewed appears
later in this section.
Before proceeding with a global examination of the fields already developed it is
perhaps opportune to review criteria for marginal field development systems. In general
such systems should incorporate all of the following features:
—early production,
—reduced capital investment,
—maximum return on investment,
—maximum flexibility for offshore development,
—proven technology,
—minimum abandonment costs,
—method to test the reservoir,
—method to produce marginally economic field.
We now proceed to an examination of the fields reviewed using the above criteria.
extensive rebuilding than had been anticipated. Statutory regulations had changed since
Drillmaster had been built and extensive modifications were required. The Pentagone
design made such changes difficult and in some cases involved cutting through decks and
bulkheads. All these factors increased costs and caused delays. Although the
modifications had been scheduled to take 11 months, Buchan Alpha was not towed out to
the field until September 1980, a year later than anticipated.
Therefore, while on average the 32 fields using conventional supports improved time
to first oil, the availability of suitable supports and a degree of experience are
prerequisites to successful operations.
Since there are few if any fixed installations associated with marginal field developments
the abandonment costs tend to be minimised. In general production supports are floating
and anchored, crude export is via tanker and not pipeline. Therefore the only fixed
installations are the subsea wellheads which can be abandoned.
Many oil company economists tend to ignore abandonment costs since in most cases
they appear only after 20 years of field life and have therefore a negligible effect on the
discounted cash flow of the project. However, abandonment costs are real and substantial
and any development system which reduces them reflects positively on project
profitability.
3.1.8 Conclusion
Technology for developing marginal offshore oilfields 92
The 39 developments reviewed for this section show that marginal field technology has
been in existence since 1971 and has been steadily evolving since that time. The 32
developments utilising some form of conventional production support have established
the technological viability of producing marginal fields while the remaining 7
developments have taken a first step in demonstrating the technologies which may be
used to develop marginal fields in the future.
Marginal fields will form an important segment of the petroleum resources of the
future whether they are located in existing oil provinces or in new areas. The technology
has now evolved to the stage where proven systems do exist which may be adapted for
use in most circumstances.
The field data sheets show the wide range of reservoirs which have to be produced
while the environments have varied from the relatively benign regions of Brazil and
Ghana to the harsh environment of the North Sea.
Riser type:
Riser data:
Export details: The crude is loaded via an export line to a conventionally moored storage
tanker (capacity 420 000 bbls)
Remarks: The production level of this field is very low; however, the quality of the crude
and the government policy towards exploitation has made production possible;
Agri-Petco have been searching for sometime for a joint venture partner in
order to implement phase II of the development which incorporates some gas
injection
Date: 1982–1984
Field: Parati
Location: Offshore Brazil
Operator: Petrobras
Environmental Water depth 94 m
conditions:
Reservoir Crude oil gravity—25–28° API, Gas/oil ratio 436 scf/bbl
characteristics:
No. of wells: 4
Well completion: 2 dry, 2 wet satellite
Well recovery:
Production rate: 7 000 b/d
Production Jack-up
support:
Support data: Petrobras III
Riser type: 1 rigid, 3 flexible
Riser data:
Export details: Crude offtake is via a floating hose from the production jack-up directly to a
conventionally moored 30 000 dwt shuttle tanker
Remarks: This was an early production system
Existing marginal field technology 97
Production Jack-up
support:
Support data: Dan duke
Riser type: Rigid, integral
Riser data: 12×3 in. flowlines 1×12 in. export line
Export details: Crude is offloaded from a 12 in. export line into a 230 000 dwt. VLCC Phillips
Enterprise via a catenary anchor leg rigid arm mooring (CALRAM); the buoy
is pin-connected to the tanker during loading
Remarks:
Date: 1984
Field: Saleh
Location: Offshore UAE, 26 miles from the coast
Operator: Gulf Oil
Environmental Water depth—100 m
conditions:
Reservoir Gross thickness of reservoir interval—145.9 m, porosity—10.9–24.9%, 17.9%
characteristics: (Avg.), crude oil gravity 45.5° API, gas/liq. ratio 4 701 scf/bbl.
No. of wells: 3
Well completion: Dry, wellhead platforms
Well recovery:
Production rate: 5 000 b/d (early 1984)
Production Jack-up
support:
Support data: Zapata Offshore’s Heron
Riser type:
Riser data:
Export details: Crude oil from the field moves through a 12 in., 21 mile pipeline to a
permanently moored storage tanker, the 230 000 dwt. Afran Zodiac
Remarks: This development constitutes an early production system for the field where
the rhythm of production should increase from 5 000 b/d (Jan. 1984) to an
anticipated 23 000–26 000 b/d (late 1984)
Technology for developing marginal offshore oilfields 100
characteristics:
No. of wells: 1
Well completion: Dry
Well recovery: 1 800 b/d
Production rate: 1 800 b/d
Production support: Jack-up
Support data: Petrobras III
Riser type: 1 Rigid
Riser data:
Export details: Oil via floating hose to permanently moored 30 000 dwt tanker.
Remarks: Two wet satellite wells are planned. These wells will be connected to the
support by means of flexible risers.
Date: 1979–1983
Field: Enchova East phase 2
Location: Brazil
Operator: Petrobras
Environmental Current 3.5 knots
conditions:
Reservoir 0.75 wt%, gas/oil ratio 477 scf/bbl, gross thickness of reservoir interval 42 m
characteristics: and 77 m
No. of wells: 4
Well completion: Test plus 3 wet subsea satellites
Well recovery: —
Production rate: 14 100 b/d
Production Semi-sub
support:
Support data: Penrod 72
Riser type: 1 tubing string inside the drilling riser plus 3 flexible bundles
Riser data: 2×4 in. flexible production lines, 3×2.5 in. flexible gas lift/kill lines, 1×8 in.
flexible export line, 1×8 in. flexible production line
Export details: Offloading of crude was accomplished through 53 000 dwt. shuttle tankers
utilising a CALM buoy
Remarks: The second phase of the development included the use of a second production
support Penrod 72 connected to Sedco 135D by a flexible line; eventually Sedco
135D and its storage tanker were removed and the field was produced using
Penrod 72 alone, production level in 1983 was 7 000 b/d
Technology for developing marginal offshore oilfields 106
Date: 1979–1981
Field: Casablanca
Location: Offshore Spain, 50 km from Tarragona
Operator: Chevron
Environmental Water depth—120–130 m
conditions:
Reservoir Crude oil gravity—34° API, sulphur 0.2 wt%, gas/ oil ratio 65 scf/bbl, gross
characteristics: thickness of reservoir interval—200 m
No. of wells: 2
Well completion: Wet, subsea
Well recovery:
Production rate: 15 000 b/d
Production support: Semi-sub
Support data: Alfortunada
Riser type: 2 flexible bundles
Riser data: 1×6 in. flexible production line, 1×4 in. flexible production line, 4×1 in.
flexible lines. 1×12 in. flexible export line
Export details: The crude is delivered via an export pipeline
Remarks: The field was developed in three phases—phase 1: early production using an
Aker H3 as support; phase 2: described above; phase 3: a fixed production
system
Technology for developing marginal offshore oilfields 110
No. of wells: 5
Well completion: 1 dry, 4 wet satellites
Well recovery:
Production rate: 23 500 b/d
Production support: Semi-sub
Support data: Sedco Staflo
Riser type: 1 rigid, 4 flexible
Riser data:
Export details: Crude offtake via a CALM buoy to 53 000 dwt. shuttle tankers
Remarks: Although this system was for early production it encompassed many
facilities associated with a full system, particularly the processing facilities
Date: 1980
Field: Pampo
Location: Offshore Brazil
Operator: Petrobras’
Environmental Water depth—120 m
conditions:
Reservoir Gross thickness of reservoir interval—38 m and 210 m, porosity 21–27%,
characteristics: water saturation 21%, crude oil gravity—21° API
No. of wells: 1
Well completion: Production via a subsea test tree and tubing string run inside a drilling riser
and BOP to a deck tree
Well recovery:
Production rate: 8 000 b/d
Production support: Semi-sub
Support data: Sedco 135D
Riser type: Tubing string inside drilling riser and BOP
Riser data:
Remarks: This system was temporary and Sedco 135D was transferred to Bicudo when
the Pampo well was incorporated into the Linguado system; replaced by fixed
platform
Date: 1981
Field: Pampo Linguado
Location: Offshore Brazil
Operator: Petrobras
Environmental Water depth—110 m
conditions:
Reservoir Crude oil gravity—20–30° API
characteristics:
No. of wells: 4
Well completion: Test plus 3 wet subsea satellites
Well recovery:
Production rate: 20 000 b/d
Production support: Semi-sub
Support data: Transworld 61
Riser type: 1 tubing string inside the drilling riser and 3 flexible bundles
Existing marginal field technology 113
Riser data:
Export details: Crude export was via a floating hose to a conventionally moored 12 000 dwt.
shuttle tanker
Remarks:
Export details: Crude is offloaded via a floating hose to conventionally moored 12 000
dwt. shuttle tankers
Remarks:
Well recovery:
Production rate: 22 000 b/d
Production support: Semi-sub
Support data: SS Petrobras XV
Riser type: 5 flexible
Riser data:
Export details: Oil via CALM buoy, gas via pipeline
Remarks: Early production system in operation since December 1983.
Well recovery:
Production rate: 12000 b/d (estimated)
Production support: Semi-submersible
Support data: Zephyr I
Riser type: 5 flexible
Riser data:
Export details: Oil via floating hose to permanently moored 30000 dwt tanker
Remarks:
Riser type:
Riser data:
Export details: Crude offtake via three 1500 tonne barges
Remarks: In 1976 two supplementary wells were drilled and barge L39 (demobilised
from Bekapi) was added as a second production support
Date: 1977
Field: Castellon
Location: Offshore Spain, 65 km from Tarragona
Operator: Shell Espana
Environmental Water depth—117 m, wind—100yr 1 min mean 40.2 m/s, 1yr, 1 min mean 24.7
conditions: m/s, waves—100yr Hmax 15.9 m. Tass 13 s, Hs 8.5 m, Tz 10.6 s.
Reservoir Crude oil gravity—35–35.5° API, sulphur 0.35 wt% viscosity 5.99cst at 38°C,
characteristics: gas/oil ratio 75 scf/bbl
No. of wells: 1
Well Wet, subsea Cameron type
completion:
Well recovery: None
Production rate: 6 000 b/d
Production Tanker
support:
Support data: 60 000 dwt.
Riser type: Flexible
Riser data: 1×4 in. production
Export details: The storage production loading tanker is moored to a single anchor leg system
(SALS) with crude transfer being effected to a second 15000 dwt. tanker moored
alongside
Remarks: The development consists of a remote subsea wellhead connected by flowline to
a manifold and thence by means of a flexible riser to a
production/storage/loading tanker; this simple type of system has demonstrated
that even a very small field located in benign environmental areas can be
economically produced
Technology for developing marginal offshore oilfields 132
Well recovery:
Production rate: 5500 b/d
Production Tanker
support:
Support data: 127000 dwt.
Riser type: Flexible
Riser data: 2×6 in. production 2×6 in. service
Export details: Offtake is by tandem (bow to bow) tanker berthing
Remarks: The production/storage/loading tanker on this field is held on station by a rigid
yoke attached to a single buoy storage system (SBS) which is itself anchored by
6 in. chains connected to pilings driven into the sea bed; after field depletion this
system can be relocated to another similar field
Date: 1983
Field: Central Cormorant
Operator: Shell UK Exploration
Environmental Water depth—152 m
conditions:
Reservoir Crude gravity—35° API, sulphur content—0.6–1.1%, wax 7.2%, gas/oil ratio—
characteristics: 500–600 scf/bbl
No. of wells: 9–5 production, 4 injection
Well completion: Wet TFL subsea, satellites, McEvoy on the manifold, Vetco for the satellites
Well recovery: Water injection planned
Production rate: 50 000 b/d (planned)
Production Underwater manifold centre (UMC)
support:
Support data: Weight 2200 tonnes, dimensions 52×42×15 m
Riser type:
Riser data:
Export details: Two 8 in. production lines carry crude from the underwater manifold centre
(UMC) to the Cormorant A platform; because the UMC and the platform are so
far apart a special insulated pipe has had to be developed to prevent the oil in
the pipeline from cooling too much, causing wax and hydrate formation
Remarks: Central Cormorant is the first practical demonstration of subsea manifold
technology developed by Exxon in the SPS (subsea production system)
programme of the late 1970 s; another important aspect of this development is
the incorporation of TFL (through flowline) servicing of the wells
Existing marginal field technology 141
Date: 1984
Field: North East Frigg
Location: 2 20 E, latitude 60 N, 18 km NE of Frigg
Operator: Elf Norge
Environmental Water depth—100 m
conditions:
Reservoir Gross thickness of reservoir interval—200 m, porosity—28%, permeability—
characteristics: 1250 md, con-densate/gas ratio—1 bbl/mmcfg (single welldata)
No. of wells: 6
Well completion: Wet, cluster; each well is connected to a subsea gas manifold
Well recovery:
Production rate: 5MMm3/day of gas
Production Articulated column
support:
Support data: Designed by EMH, normally uninhabited
Riser type:
Riser data:
Export details: Gas is exported to the TCP 2 Frigg field platform via a 16 in. gas line
Remarks: North East Frigg is a marginal field whose recoverable reserves are not
sufficient to justify the costs involved in a traditional development scheme; the
scheme adopted leans heavily on technology already developed by Elf at their
Grandin test station in Gabon; field life is estimated to be 5 years
Existing marginal field technology 145
Export details: Oil is piped via two flowline bundles to the Claymore platform for
processing
Remarks: Total cost of this development is £150 m
characteristics: interval—131.3 m and 47.2 m, sulphur 0.3 wt%, gas/oil ratio—140 scf/bbl
No. of wells: Initially 3
Well completion: Wet, cluster, subsea
Well recovery: Water injection and gas lift planned
Production rate: Initially 13 500 b/d
Production Subsea manifold
support:
Support data: Weight 100 tonnes, 140×45×30 ft
Riser type: N/A
Riser data: N/A
Export details: 5 lines are planned between the field and the near-by (14 km) Tartan platform,
one 12 in. for bulk crude, three 3 in. for test crude, gas lift and water injection
and a 4 in. utilities line
Remarks: Highlander is due for installation in early 1985 with limited production
beginning late in the second quarter of the year; production should eventually
rise to 20 000 b/d and the recoverable reserves have been estimated at 30
million barrels
Technology for developing marginal offshore oilfields 148
In Chapter 2 we discussed the various separate elements that may be incorporated into a
marginal field development system. To a large extent, within the design parameters of the
particular field, these are interchangeable (e.g. the various types of production supports
may be used in conjunction with different types of riser systems etc.). However, in order
to appreciate the interaction of the various elements it is useful to consider the technology
in terms of the overall systems which may be employed in an offshore development.
In this chapter we will consider the various production concepts which are currently
being employed in marginal field type applications in moderate water depths (150 m) and
harsh environments (North Sea or equivalent). We will also review several promising
concepts/designs which are currently being proposed for marginal field applications in
deepwater environments.
Systems which may operate quite satisfactorily in the tropics may be quite unsuitable
when considered for duty in a North Sea type environment. North Sea type installations
must be designed to withstand higher maximum waves. They must also be capable of
operating in an environment which experiences waves of significant height for most of
their design life without suffering from fatigue problems. Different design wave heights
for various offshore areas are shown in Table 4.1. A comparison between North Sea and
Gulf of Mexico wave environment is shown in Fig. 4.1.
If one ignores the field developments which employ ‘conventional’ technology (i.e.
steel template jackets or gravity concrete or steel platforms with pipelines to shore etc.)
the most common production concept used in the North Sea type environment is based on
the semi-
TABLE 4.1
Comparison of 50 Year Design Wave at Different
Offshore Locations
Celtic Sea North Sea Campos Spain Tunisia Philippines
Kinsale Hd. Buchan Bicudo Castellon Tazerka Cadlao
Hmax (m) 26 26 12 15 18 17
Water 100 112 140 117 140 90
depth
(m)
sub production support. Other concepts in current use employ subsea production, the
articulating column and the tension leg platform. A system employing a converted jack-
Technology for developing marginal offshore oilfields 150
up rig was used successfully for a period on the Ekofisk development. Production tanker
based concepts have not as yet been used in North Sea environments. However, the use
of tankers for crude oil storage and for transportation to shore is now commonplace.
When one reviews the concepts which are currently being proposed there is a plethora
of ideas, varying from minor modifications of existing systems to quite futuristic
proposals. The concepts which are reviewed
When the Argyll production facility was installed on the field it was not intended as a
permanent production facility—rather it was considered a production test facility. Its
design was the result of drilling experience with semi-submersibles and the production
support consisted of a converted drilling unit. The Buchan field development can be seen
as the natural successor to Argyll. While similar in concept, it represents the extension of
the floating production principle to a field with more subsea completions, but no radical
departures in new technology. In terms of field size, however, it comes close to the limit
of what can be achieved by the conversion of a standard drilling rig.
The Balmoral field, which is currently being developed by Sun Oil in block 16/2/A in
the North Sea, is scheduled to commence production in 1986. This represents a further
development of the semi-submersible production concept. A purpose built production
platform based on Gotaverken Arendal GVA 5000 semi-submersible has been designed
with process facilities of 65000 b/d capacity. The Balmoral production platform is
intended to provide processing facilities for the satellite Glamis structure and possibly
other oil reservoirs in the area also. The Balmoral development is significant in that it
demonstrates the significant topside weight capacity that is now possible with current
semi-submersible designs (up to 5000 tons on the GVA 5000 series). The GVA 5000 has
two twin decks which will house process facilities and water injection equipment as well
as providing for future gas lift compressors.
The Balmoral field development is significant in that it will be the first time that
flexible production risers will be used in a severe North Sea type environment. The
flexible riser offers significant attractions over the rigid riser to operators using a semi-
submersible production support. There are advantages at the vessel/riser interface where
the necessity for heave compensation equipment is eliminated and almost instantaneous
disconnection is possible without difficulty. The flexible risers do not need to use the
moonpool, leaving it free from workovers which can be accomplished without
interrupting production. In addition the flexible riser places less demands on deck space
and loading. Unlike the rigid system it needs no tensioning, thereby increasing available
topside weight capacity. A flexible riser should never need to be stored on board which
further increases available deck space and weight capacity. (See Chapter 2 for details of
the Balmoral riser and see Chapter 3 for a description of the Balmoral field
development.)
Thus the Balmoral development should provide a significant advance to the semi-
submersible production concept and useful operational experience of the behaviour of
flexible risers in harsh environments.
New proposals for further development of the basic production semi-sub concept are
tending to concentrate on increasing deck load capacity, simplifying the riser system and
improving the mooring and offloading systems.
m water depth range. The unit has been designed to maximise ease of fabrication and
minimise construction time while meeting all North Sea safety regulations and
maintaining motion characteristics which are comparable with other semi-submersibles.
The unit incorporates an integrated truss type deck of the ‘Hideck’ type which is
designed for wet mating of the hull and deck in a similar manner to that of the Hutton
field TLP in 1984. The large deck area is a significant advantage since it reduces the
height of the topsides and so optimises the location of the centre of gravity which in turn
maximises the deck loading capacity. Table 4.2 shows the main characteristics and
criteria which have been established for a vessel, with production payload of 6000
tonnes, operating in 150 m water depth in the North Sea.
The topsides of the vessel contain all the production facilities, services and
accommodation. The deck sides are cladded with lightweight panels for weather
protection. Accommodation is designed for 80 persons in single or two berth cabins and
hotel facilities. Outside the Norwegian sector, this can be upgraded to 120 persons
without change to the major structure, as a result of the less onerous accommodation
requirements outside Norway.
A moonpool is located in the centre of the deck. It is designed for handling workover
and side track drilling and control umbilical
TABLE 4.2 Highlander 6000 Main Characteristics
and Criteria
Number Dimensions Height
Columns 8 10 m dia. 24.6 m
Pontoons 2 12.8 m width×75 m long 6.4 m
Deck Main+cellar 75 m×55 m 10.0 m
Dry Operating
Deck weight (tonnes) 7500 10000
Hull weight (tonnes) 7800 21000 (inc. ballast etc.)
Transit Operating Survival
Displacement (tonnes) 20300 31000 27100
Draught (metres) 6.1 20.0 15.0
Design operating conditions 100 year storm survival conditions
Waves (Hs×period) 9.4 m×12.4 s 16.6 m×16.6 s
Surface Current (knots) 1.6 2.6
Hour Mean Speed (knots) 51.0 73.0
tensioning equipment. The main deck of the structure contains the following items:
—workover derrick,
—wellhead workshop,
Technology for developing marginal offshore oilfields 154
A conventional 12 line 95 mm chain catenary mooring with high holding anchor piles is
designed to keep the unit on location within the allowable offsets even in storm
conditions. Hydraulically operated mooring chain tensioning systems are located on the
columns. Riser disconnections should not be required in any intact condition.
The Highlander concept of a large conventional semi-submersible production platform
is not unique. Several other similar designs have been proposed by designers and
contractors. These include:
—the Gotaverken Arendal 5000 series and 12000 series (with 12500 tonnes topside
capacity);
—the EPM—T2000 ‘Cybele’ design;
—the CFEM five legged ‘Penta 7000’ floating production platform;
—the Santa Fe ‘Sea hawk’ design.
TABLE 4.3
Some Production Semi-Submersible Designs
System name Seahawk Penta 7000 Cybele
Designer Santa Fe CFEM EPM
Assumed field data
Water depth 100–500 m 200–550 m 150 m plus
Oil production 40000 b/d 120000 b/d 10000 b/d
Gas production 90 mmscfd 140 mmscfd
3
GOR 1200 ft /bbl
Current and future marginal field development concepts 155
See Table 4.3 for details of these current production semi-submersible designs. Indeed, it
is worth noting that semi-submersible designs exist which are proposed as being suitable
for quite large fields in very deep water—the Santa Fe drilling DP-120 vessel concept
would have a deck load capacity of 7000 tonnes and a production capacity of 100000-
240000 b/d in water depths of 300–1600 ft.
Technology for developing marginal offshore oilfields 156
The IMFP 300 vessel can be anchored by its own conventional mooring system in a
variety of water depths from 100 m to 500 m, thus facilitating redeployment. Mooring
lines are composed of short sections of chains with wire ropes. Mooring winches are not
provided for. Lines are pulled with jacks and stoppers are used. Table 4.4 shows the main
characteristics and criteria for one version of the unit.
The top sides of the vessel and central shaft contain all the production facilities,
services and accommodation for 40 personnel. The available production capacity depends
on the reservoir characteristics but is illustrated by the following options:
—oil production (b/d)—25000;
Current and future marginal field development concepts 157
The basic production system consists of a conventionally moored tanker which houses
the production facilities and which is linked to a subsea system by a single point mooring
(see Chapter 2). The subsea equip-ment consists, typically, of a number of satellite wells
feeding to a manifold and riser.
TABLE 4.4
IMFP 300 Main Characteristics and Criteria
Number Dimensions Height Storage
Central shaft 1 13.0 m dia. 65.0 m
Peripheral cylinders 8 7.8 m dia. 62.0 m 105000 bbl
Deck 30 m×30 m
Total height (without flare) 107 m
Flare height above deck 34 m
Weights and draught Number Dimensions Height Storage
Deck weight (tonnes) 1500
Total dry weight of structure and 12500
equipment (tonnes)
Displacement (tonnes) 40000
Draught (m) 77.0
Environment Annual return period 100 year storm survival
conditions
Waves (Hs×period) 5.0 m×9.5 s 7.6 m×11.1 s
Surface current (knots) 2.3 3.3
Bottom currents (knots) 0.2 0.2
Oil flows to the processing facilities on the tanker, where the oil is degassed, and
buffer storage is provided on the tanker. Offloading of the oil is by shuttle tanker which
takes oil from storage to shore.
The concept has several inherent advantages:
—Accelerated production from the reservoir, since the wells can be predrilled in advance
of the production installation being taken offshore.
—The tanker conversion can be completed in shipyards or inshore thus avoiding
expensive offshore construction and hook-up.
—The production unit may also house very large storage capacity and afford a stable
terminal for offloading the produced oil into shuttle tankers.
Current and future marginal field development concepts 159
—Offshore loading from tanker storage is less prone to the weather and mechanically
induced down time which has plagued some loading systems in harsh offshore
environments.
—The large deck areas and virtually unlimited deck load capacity of tanker based
production units eliminates the problem of topside weight control, which remains one
of the main problems in the design of semi-submersible type units.
—The unit can be taken inshore for inspection and repairs.
—The tanker and its topside facilities can be redeployed once the reservoir is depleted.
Thus the tanker has all the advantages of the semi-sub concept with the addition of
providing oil storage and being an integral offloading terminal. The related production
equipment considerations are about the same as for those of a semi-submersible.
However, the concept also has a number of significant drawbacks when considered in the
context of North Sea type environments. These principally relate to the mooring and the
riser systems.
The tanker itself may be moored in a spread mooring of multiple fixed anchor points
on the sea bed. This type of arrangement fixes the orientation of the tanker and can be
used only in shallow, protected waters where mild winds, waves and currents prevail.
The alternative method of mooring a tanker is by its bow or stern with a single point
mooring. The single point mooring system (SPM) (see Chapter 2) minimises the
environmental load on the tanker by allowing it to weathervane to the orientation of least
resistance to the combined forces of wind, wave and current. This, of course, results in
the possibility of the ship rotating freely about its mooring. Consequently any continuous
delivery of fluids through a pipeline or hoses to, or from, the ship must pass through the
buoy and, in fact, be concentric with respect to the axis of rotation of the whole system to
avoid interferences or entanglements.
The piping conduit itself must also be equipped with a swivel to permit the tanker to
weathervane. If multiple conduits are required, they must have multiple concentric
swivels. Swivels to accommodate multiple concentric passages have been developed.
Similar systems have been used for many years for loading and unloading crude oil
tankers at terminals. However, these several hundred existing SPM systems were
designed for handling tanker-ready crude at terminals. The use of a SPM moored tanker
as the production support facility for early or marginal field production systems presents
an entirely different set of circumstances. In this situation the live well bore fluids of gas,
oil, water and sand is being handled. The gas and oil may both be sour (i.e. contain H2S).
The pressure may be the well flowing pressure of several thousand pounds per square
inch. This is all in contrast to the stabilised and treated crude oil at a maximum pumping
pressure of 200 psi normally seen in tanker loading service.
There are a considerable number of offshore developments which employ a converted
tanker as production support (see Chapter 3 for the technical details and information on
their operating history). However, without exception, these are all currently operating in
moderate offshore environments. Nevertheless, tanker based systems for a North Sea type
environment are being proposed and built as we shall see below.
Technology for developing marginal offshore oilfields 160
TABLE 4.5
PTS Production Test Ship
Assumed field data
Water depth 100 m to 600 m
Oil production 2850 tonnes/day
Water cut Up to high % (if required)
Export system Offloading to shuttle tanker, over stern
PTS characteristics and
criteria
Dimensions 209 m long×32 m width
Draught 10 m
Displacement 50910 tonnes
Oil storage capacity 188700 STB of crude oil
Ground flare 30.5 mmscfd
capacity
Mooring 8×1600 m long K-4 class anchor chains with 13.6 tonne anchors
Dynamic positioning DP systems with hydroacoustic reference to transponders at seafloor.
DP to provide heading control and reduce peak mooring line loads on
turret system. 2×5600kw controllable pitch main thrusters.
4×1500kw fixed transverse thrusters, two forward and two aft.
The PTS has been designed to survive and remain on station in a North Sea storm of
100 year return period. The owners of the PTS intend to lease the vessel out to operators
of offshore fields. It has been reported (August 1985) that Norske Hydro intend to charter
the Petrojarl to carry out extended production trials on two wells on the Oseberg field
offshore Norway. The PTS is a logical development of the production tanker concept
from the mild offshore environments of the Mediterranean and Far East. Items of special
interest, when extending the concept to North Sea type environments, involved fatigue
loading, the mooring and riser systems and the topside arrangements.
The vessel does not have a drilling capability. The exploration or appraisal wells are
completed in a conventional manner by a drilling vessel and the wellheads are capped
with a SWOPS re-entry hub. The
TABLE 4.6
SWOPS System
Assumed field data
Water depth 75–200 m
Oil production (b/d) 3 000–15 000
Gas production (mmscfd) 6
Water production (b/d) 4000
Max. shut-in pressure 5 000 psi
Water/gas injection None
Max. no. producing wells 2
Wellhead fluids Negligible H2S, 10% weight max. wax content. 0°C
pour point
SWOPS main characteristics and criteria 251.5 m× 37.0 m width× 19.8 m depth
Dimensions
Displacement (at 11.0 m design draft) 76 440 tonnes
Tanks’ capacity crude oil storage 51 000 m3
ballast 39 000 m3
slops 6 500 m3
heavy fuel oil 2 600 tonnes
Transit speed 12–14 knots
Riser pipe
OD ×24.7 lb/ft Grade E SMLS API 5A drill
pipe
Riser operating tension 90 000 lb/ft
Number of tensioners 4
Max. travel of tensioners 50 ft
Max. riser angle ±15°
Max environmental criteria for production
Significant wave height, Hs 4.5 m
Winds 36.5 knots
Technology for developing marginal offshore oilfields 164
rigid riser, which incorporates a wellhead re-entry connector, is lowered to mate with the
wellhead when the SWOPS vessel is on station.
The design permits re-entry and connection of the production bore with the riser
whatever the rotational orientation of the riser connector. The wellhead hydraulic controls
are simultaneously connected with the production bore and riser. Oil produced from up to
two wells can be comingled at the base of the riser.
The rigid, tensioned riser consists of a series of conventional jointed tubulars with a
universal joint at the lower end and a high pressure swivel at the upper end. Riser stresses
are minimised by the universal joint which permits the vessel to oscillate under DP
control. The riser is designed to permit production to continue in severe weather
conditions, limited only by heave and the station keeping capability of the ship. The rigid
riser is a less expensive option than a flexible riser. However, it requires much tighter DP
control plus extra deck storage, space and a derrick and moonpool arrangement.
Nevertheless, the rigid riser does permit wireline entry to the wellhead.
The depth limitation of the current SWOPS design is more a function of the specific
applications which BP have in mind for this vessel than an inherent limitation of the
concept. A SWOPS vessel, designed for 500 m water depth, has been proposed by the
designers.
The installed production equipment has a design capacity of 15000 barrels a day. It is
housed below the main deck and adjacent to the moonpool. The two-stage production
process is straightforward. Incoming crude oil is cooled and its pressure reduced to
separator conditions. At the first stage separator up to 80% of its gas content is removed
and conditioned to fuel gas quality to feed the ship’s power generation system. After the
second stage separator the crude is cooled to storage specifications and led directly to the
ship’s cargo tanks. Produced water is fed to the oily water separation system where
natural separation takes place. Any remaining gas is flared.
The SWOPS vessel has a storage capacity of some 42000 tonnes of crude oil. The
vessel will have a displacement of about 76000 tonnes. BP did consider converting an
existing tanker (of about 50000 dwt.) as an alternative to a purpose built vessel but
rejected the conversion option as they considered it to be unsatisfactory, both technically
and commercially. The purpose built vessel also permitted BP to optimise their design.
However, the economics of other small fields may dictate the use of a converted tanker
deploying a flexible riser over the side or bow of the vessel.
The SWOPS vessel which has now been commissioned will incorporate the rigid riser
configuration described above. However, an alternative flexible riser design has also been
proposed by BP for future applications of the concept.
—Two conventional barge shaped hulls, one supported beneath the other, leaving an
interhull gap.
—A turret mooring system with six catenary mooring lines which permits the unit to
weathervane.
—Multiproduct high pressure swivels in the turret to permit transfer of all well fluids to
the process system.
—A tensioned leg riser tower with subsea manifold which can be maintained by divers in
the air diving range.
The floating oil patch concept attempts to overcome the limitation of the current
generation of floating production and storage vessels while still capitalising on the best
features of the systems currently available. Converted tankers have the advantage of high
payload capacity and large deck area. However, the mooring and riser systems pose
problems in severe wave environments and, despite the availability of surplus tankers,
few are suitable for conversion. Semi-submersibles have the advantage of satisfactory
motion characteristics but they are expensive to build or convert and they tend to be
weight sensitive. Jack-up units have the advantage of providing a stable platform but they
are limited in regard to water depth and deck load capability. A sketch of the floating oil
patch is shown in Fig. 4.5.
A notable feature of the concept is the tandem hull design. The supporting members in
the interhull gap are designed to promote conflicting currents and vortices in the water
entrained between the hulls. The large power sink, thus created, consumes the wave
energy thereby reducing the pitch, heave and roll motions of the vessel. Vessel motions
are further dampened by a passive motion suppression system developed by the London
Centre for Marine Technology and licensed by BPP Ocean Technology Ltd. This system
consists of a series of open bottomed tanks along the sides of the upper hull which are
valved to ensure that the natural frequency of the vessel is altered so that it never operates
in the range of its two roll resonant states. The tandem hull design also reduces the water
plane ratio of the vessel and so further reduces the motions, just as the same principle
forms the basis of the steadiness characteristics of semi-submersible vessels. Periodic
maintenance and inspection of the upper hull and interhull structures is facilitated by
deballasting the lower hull for dry access to these areas.
Process, utility and power generation equipment and systems are located on the main
and lower deck levels and a ground flare is located at the aft end of the platform. Deck
loading should not be a problem as the unit could accommodate up to 15000 tonnes
payload.
The subsea flowlines and control lines from production and injection wells are laid to
anchor blocks below the tension leg riser tower and flexible transitions connect them to
the rigid risers in the tower. The tower is tensioned by a buoyancy tank which is
surmounted by a subsea manifold which can be maintained by divers in the air diving
range. The flowlines are then routed down to sea-bed level where they are connected to a
flexible riser system.
Technology for developing marginal offshore oilfields 166
TABLE 4.7
The Floating Oil Patch
Assumed field data
Water depth 150 m
Oil production (b/d) 20000 (36° API)
Gas production (mmscfd) 60
Water cut 33%
Gas/oil ratio 300 scf/bbl
Max. shut in pressure 2000 psi
Number of subsea wells 6
Export system 6 in. transfer to existing pipeline
Dimensions
Upper hull 124.0 m×33.0 m×9.0 m deep
Lower hull 131.0 m×28.0 m×8.0 m deep
Interhull gap 3.5 m
Depth of subsea manifold 45.0 m below LAT
No.of mooring chains 6
Deck payload capacity 15000 tonnes
Environmental criteria
The unit is designed to maintain normal operations in Beaufort force 8/9 weather conditions in
Block 30 of the UK Sector North Sea and to survive the 100 year storm.
TABLE 4.8
TAPS System
Assumed field data
Water depth 300 m 100 m
Oil production (b/d) 70 000 45 000
Gas products (mmscfd) 22.4 22.5
Produced water (b/d) 60 000 48 000
Gas oil ratio (scf/bbl) 320 500
Max. shut in pressure (psig) 5 000 5 000
Water injection rate (b/d) 90 000 65 000
Gas injection rate (mmscfd) 20 20
Technology for developing marginal offshore oilfields 168
—Risers from a seabed template pass through the turret where they are checked and
manifolded on the turret before passing through a medium pressure swivel to the
process plant.
— Export is by shuttle tanker using a tandem loading system (although pipeline export is,
of course, also feasible).
—The riser is designed to remain connected to the unit even through the survival storm.
A sketch of the TAPS system is shown in Fig. 4.6. The system has been
designed for a range of water depths. The first design was for a field west of Shetland in
300 m but the latest design is for a unit for a field SE of Shetland in 100 m water depth.
—New connect and disconnect systems are being developed to permit operations in
iceberg prone areas and to permit tankers to stay on station and to re-connect at much
higher sea states.
—Improved mooring systems and DP systems are being developed to enable tankers to
weather the most extreme offshore environments.
The basic production system consists, typically, of a converted drilling jack-up unit
which houses the production facilities with wellheads situated on the jack-up unit. Oil
flows to the processing system and thence to a storage facility aboard an adjacent tanker.
The jack-up has several inherent advantages:
—The stable platform provided by the jack-up eliminates all the difficulties associated
with the heave and lateral motions of floating units.
—The units may be deployed at short notice and are ideal for early production systems.
—The conversion to a production facility can be completed inshore, thus avoiding
expensive offshore construction and hook-up.
However, jack-up production units have several limitations which may become critical
when considering them for duty in severe wave environments:
—Jack-up units must, by their nature, be able to jack their deck into position above the
prevailing waves. Thus the jacking capacity has a critical influence on the topside
facilities which can be accommodated on the unit.
—Most drilling jack-up designs are based on a combination of maximum wave, wind and
gravity loads and, as such, are not entirely governed by fatigue considerations due to
the variations in water depth, environmental conditions and operating loads
experienced during the life of the unit. While the cyclic stresses may be high, the
number of cycles at any given location on the leg will be low. Thus, a jack-up
designed essentially for exploratory drilling will have a shorter fatigue life if it is
operated at a single location for a long period of time. This is especially true in severe
wave environments.
—Jack-up units, being bottom founded, have quite strict depth limitations, especially in
severe wave environments.
—Jack-up units do not have any oil storage capability and so require an associated
storage/transportation vessel or a pipeline to shore.
Several fields worldwide currently employ converted jack-up units for production duties
(see Chapter 3). However, only one such unit has been used in the North Sea. This was
the Gulf Tide jack-up unit which was deployed on the Ekofisk field between 1971 and
1974. The unit is understood to have suffered fatigue damage during this—comparatively
brief—period.
A new class of harsh environment jack-up units have recently entered the North Sea
drilling market. These units, which are designed for drilling, not production, give an
Current and future marginal field development concepts 171
indication of the largest type of jack-up which is currently available. A sketch of the unit
is shown in Fig. 4.7 and the main characteristics of these units are shown in Table 4.9.
The reinforced and prestressed concrete caisson is the foundation base for the overall
structure. When ballasted, it helps provide the necessary stability for operations in severe
environments. During production operations the caisson, through the application of the
oil/water displacement principle, is used for storing the produced crude oil, while during
tow, installation and retrieval operations, it provides the controlled buoyancy to
accommodate the total topside load, including the jack-up.
For the North Sea type environment, the Seaplex concept incorporates two additional
and separate elements for assisting in developing marginal fields. One is the unitised
subsea drilling/production template for predrilling wells during the construction stage of
the Seaplex; and the other, a truss type steel tower structure that provides both lateral and
vertical support for the risers and well conductors.
Jack-up payloads tend to be limited to something less than that usually desired by
production personnel. However, by attaching the jack-up legs to the concrete caisson and
Technology for developing marginal offshore oilfields 174
by welding off the legs to the hull structure, the Seaplex is able to accommodate a 50–
150% greater payload than the free standing jack-up. The elevating units may be removed
from the structure to provide additional payload capacity or left in place as a possible
back-up to the welded connections. Typical specifications for the Seaplex class 500–4 are
shown in Table 4.10.
TABLE 4.10
Seaplex Class 500–4 Typical Specifications
Water depth (m) 122 152
Max. wave height×period 28 m×17.5 s 31 m×17.5 s
Current (surface) 2.72 knots 2.72 knots
(bottom) 0.0 knots 0.0 knots
Oil production (b/d) 50000 50000
Maximum oil storage (bbl) 500000 500000
2
Available deck space 4088 m 4088 m2
Deek load (all fixed and variable) 27215 tonnes 18144 tonnes
The manifold on the riser top module is situated 50 m below the water surface. This
depth has been selected to ensure low dynamic excursion of the riser due to current
induced vortex shedding. The vortex shedding forces are also reduced by the selection of
four long slender buoyancy chambers and a lattice type structure. The subsea manifold
can be accessed by air divers to accomplish simple and rapid operations (e.g. replace any
piece if necessary, connect flexible to rigid lines, etc.).
The system consists of an articulated column which is used to provide a high integrity
fluid path from the well bore to deck level. By rating all the equipment on this fluid path
at full reservoir pressure it is possible to locate all well control valves and chokes on the
deck of the column. Safety on/off valves remain subsea, to be controlled by discrete
hydraulics. The topsides production facilities and utilities require some form of support
structure, i.e. either a semi-submersible, a purpose-built barge, or a converted tanker. The
most appropriate structure to use for any particular development would depend largely on
physical field parameters, and also on economic criteria.
Taywood Engineering suggest that the following factors have the greatest influence on
the decision to adopt a particular development system:
—peak production,
—gas/oil ratio,
—number of wells required,
—requirements for gas injection,
—number of drilling centres required for correct well distribution.
TABLE 4.11
MACC—Manifold and Control Column
Assumed field data MACC with MACC with Semi-sub
tanker
Oilfield Gas condensate field
Water depth 119 m 158 m 105 m
Oil production (b/d) 58000 50000 50000
GOR (scf/bbl) 310 500 6000
CO2 — — 25%
No.wells production 10 15 15
Gas injection — — 270 mm scfd
No.wells injection 8 10 13
Water injection (b/d) 45000 50000
Total effective down time claimed by designers compared with other systems
Down time Column moored Fixed platform Semi-sub with
semi-sub tensioned riser
Weather 0.5% 0.0% 25%
Repair/maintenance 0.5% 0.5% 1%
Total 1.0% 0.5% 26%
Average daily production 49500 49750 37250
(b/d)
Down time Column moored Fixed platform (no Semi-sub with
tanker storage) tensioned riser
Weather 1.5% 0.0% 0.0%
Repair maintenance 0.4% 0.6% 1.2%
Export 1.5% 25.0% 25.0%
Total 3.4% 25.6% 26.2%
Average daily production 48300 37200 36900
4.4.6 CONAT
Bilfunder & Berger, in cooperation with MAN and Tyssen, developed the CONAT
(Concrete Articulated Tower) production system for water depths of 300–400 m. It is
Current and future marginal field development concepts 179
built of reinforced concrete, also sharing the skirt pile principle which is said to simplify
installation, ensure protection against sea bed erosion and provide a heavy duty base for
the ball joint.
The heart of the articulated tower unit is an assembly which consists of a central
universal tie joint inside a 1-atmosphere chamber formed by a twin hemispherical shell,
with one half sliding within the other and
allowing a movement of up to 20°. The weight of the column is taken by the outer shell
bearing against the inner, supported by PTFE bearings and lubricated by a closed-circuit
100 bar oil flow system with ‘dry run’ capability.
Access for maintenance personnel is provided inside the ball and a pneumatic sealing
system with multiple inflatable seals provides security. The joint maintains the correct
hemisphere clearance and prevents rotation. The joint has been tested in the North Sea
and offers maintenance free operation with the opportunity for access should any
attention be required.
Technology for developing marginal offshore oilfields 180
CONAT designs come in several different forms, including the multi-column offshore
production platform (OPP) which exploits the parallel linkage in order to keep the
platform level as it moves sideways under the influence of waves, wind or current.
CONAT is applicable to various offshore requirements including single point
moorings and loading terminals, production towers, yoke towers for production tankers,
and control towers. The permanent negative buoyancy maintains a downward force on
the ball joint and this ensures that, even should the joint break, the tower cannot float
away.
As oil discoveries are made in ever deeper waters new systems to produce these fields are
constantly being proposed. Obviously fields in very deep waters and in iceberg and
icefloe infested areas may be very large by the standards of more hospitable areas and
still be in the marginal category because of the technological developments required to
produce them or because of the huge cost involved. There are currently many concepts in
various stages of refinement for developing these fields. The following is a selection of
some of them.
Dia.92 in.
Weight 3500 tonnes
Extreme Environmental Conditions
Wave 65 ft (19.8 m) 13.5 s
Wind (1 min.) 80 knots (41.2 m/s)
Current (surface) 2.6 knots (1.34 m/s)
The design includes six steel floatation tanks 110 m long and 12.5 m diameter. They are
located inside the tower with the top end 20 m below the still water level. The steel tower
is a hexagonal tubular truss frame with six main vertical legs on a 28 m radius.
Extended well test systems (EWT), for the extended flow testing of individual wells,
have been used extensively in Brazil and Spain. The systems have produced up to 20000
b/d for up to one year without shutdown, albeit in calmer waters than North Sea
conditions. The systems utilise proven and readily available equipment. The major
advantage from the operator’s point of view is the additional reservoir and well
productivity information which can only be obtained from extended testing of the
reservoir. As discussed above the viability of marginal reservoirs is critically dependent
on adequate knowledge of the reservoir and its production mechanism. However, in areas
such as the North Sea, national authorities—who exercise a major degree of control
through the licensing process—have traditionally considered that extended well testing
should be limited to a period of less than 90 days, or about half a million barrels, in order
to ensure that the overall recovery of a reservoir would not be affected by precipitate
production. As a result extended well tests in the North Sea have been limited to satellite
structures to fields which were already in production. There have been no stand alone
extended well tests in the North Sea to date. This is likely to change in the near future as
the fields under consideration get smaller, and less able to support a programme of
delineation drilling.
An extended well production test can be rapidly deployed: 25 to 30 weeks from
commitment to proceed to start if production is feasible. A typical project schedule is
shown in Table 4.12.
Technology for developing marginal offshore oilfields 186
TABLE 4.12
Typical Extended Well Test Project Schedule
Weeks
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Commit EWT system ×
Install process ×
Deliver subsea tree ×
Deliver mooring ×
Set SPM mooring ×
Well completion ×
Install loading hose ×
Moor tanker ×
Test system ×
Start production ×
TABLE 4.13
A List of Typical Equipment for an Extended Well
Test
Equipment Availability (days)
1. Semi-sub drill rig 30
2. Subsea test tree with safety shut-in controls 45
3. Tubing to surface 30
4. Surface test tree 30
5. Manifold 45
6. Separator (15000 b/d) 45
7. Surge vessel 45
8. Pipeline 30
9. Gas burner 30
10. Safety shut-in control 30
11. Layout on drill rig 30
12. Tanker loading connection 30
Current and future marginal field development concepts 187
INTRODUCTION
Despite the fact that marginal field technology has been used extensively for many years
(see Chapter 3) it is only comparatively recently that these systems have been used in
North Sea type environments. As yet there is little operational experience of tension leg
platforms (Hutton) or underwater manifold and control centres (Central Cormorant, NE
Frigg). However, there are currently two floating production systems in the North Sea
(Argyll and Buchan) which have been in production now for several years. It is
worthwhile taking a fairly close look at the development and operating history of these
two fields. Both fields illustrate the flexibility and adaptability of floating production
systems and give a good insight into the phased development which is possible when
using this type of technology. It is also instructive to look at how these systems have
behaved in practice and the down time and reliability which has been experienced with
these systems operating in North Sea conditions.
The Argyll field was discovered in 1971 in Blocks 30/24 and 30/25A, 190 miles south
east of Aberdeen. The field has recoverable reserves of approximately 60 million bbl
including the Duncan and East Duncan structures to the west of the main Argyll field.
The field is situated in water depths of 76 m. Statistics relating to the Argyll field are
shown in Table 5.1.
TABLE 5.1
Argyll Field Statistics
Block: 30/24 UK North Sea
Operator: Hamilton Oil Great Britain PLC
Partners: 28.8% Hamilton Oil Great Britain PLC
7.2% Hamilton Brothers Petroleum (UK) Ltd
25.0% RTZ Oil and Gas Ltd
12.5% Blackfriars Oil Co. Ltd
Technology for developing marginal offshore oilfields 190
phase of development of the Argyll field. The programme was designed to place the field
in production with minimum investment and to yield reservoir information required to
determine future development policy. At the same time, this production test would yield
sufficient revenue to assure profitable initial operation of the field. When Argyll came on
stream estimated recoverable reserves were put at ‘between 10 million and 25 million
barrels’ and its planned life was just five years. The system for the Argyll field stage I is
shown in Fig. 5.1.
Three subsea completions were initially connected by submarine flow-lines into a riser
base system. Well fluids flowed by way of a subsea manifold through individual 4 in.
nominal diameter lines in a production riser assembly, up to a gas-oil separation plant
mounted on the deck of a semi-submersible rig. Separated gas was flared and the
degassed crude pumped back to the sea bed through the 10 in. nominal diameter central
riser member, then through a 7500 ft long, 10 in. submarine sales line. The 10 in. line was
connected by a pipeline end manifold and 12 in. submarine hose which interfaced to a
standard deepwater design CALM type SPM. Floating hose, tapering from 20 in. to 6 in.
nominal bore, conveyed the crude from the SPM into export tankers for offloading at
United Kingdom ports. The floating production facility was converted from the drilling
rig (Transworld 58) into a production facility in a period of only six weeks. Some of the
drilling equipment remained but drilling capability no longer existed after conversion. All
available deck space was used for production equipment, separators, pumps, meters, etc.
Plant layout was checked for weight and centre of gravity, so the vessel’s trim would not
be adversely affected.
Technology for developing marginal offshore oilfields 192
The gas/oil separation plant on the Transworld 58 was quite conventional. However,
certain features were peculiar to this installation; vessels were insulated and heat traced to
maintain a minimum operating temperature of 55°F at a designed maximum throughput
of 70000 b/d. An inert gas generator provided the ability to purge the process vessels and
pipework with an inert gas blanket whenever production was shut in.
A special dual burner flare system with water spray cooling was developed to flare gas
in normal service and burn off crude pumped out of the process plant in an emergency to
achieve extreme storm survival status.
The subsea trees incorporate a manual master valve that can be closed by a diver. The
purpose of this valve is to give secondary closure of the tubing string in case of cutting in
valve seats of automatic valves or to close the tubing for adjustments in the automatic
system. The valves of the tree are designed to be diver replaceable. Above the manual
valve is a hydraulically operated master valve and a similar wing valve. All hydraulically
operated valves are opened and closed from the semi-submersible. These valves, like the
downhole safety valve, are failsafe; they close if control pressure is released. Other
valves in the system provide access to the annulus between the tubing and the casing.
Three subsea wells (2, 3, 5) produced through the system from June 1975. Well number 6
was completed in 1976 giving four producers. Argyll was able to support an almost
continuous programme of drilling and maintenance. The semi-submersible drill rig
Ocean Kokuei conducted a long-term drilling programme of a few wells each year.
As the early wells started to produce water, and oil production dwindled, a programme
of recompleting wells in the less prolific reservoirs was undertaken. As further producing
wells were discovered these were completed and tied into the Argyll manifold. Up to 7
satellite wells were producing at Argyll in the period prior to 1980. Of the seven wells
currently producing only one of them was among the original four wells.
All submarine flowlines laid in the Argyll field were initially heavy wall steel pipe
with a coal tar/fibreglass coating incorporating a heavy duty woven outer wrap. Lines
were laid directly on the sea bed without trenching or burial, since it was considered that
self burial would occur because of the nature of the sea bed. However, in two separate
incidents in 1981 two 3 km flowline bundles due to tie in a new satellite well sank during
tow to the field from Scotland. The cause has never. been made public although it was
widely rumoured to have been connected with the use of spiral welded carrier pipe. Since
then, Hamilton has made extensive use of flexible pipe.
The field shuttle tankers have been modified for self mooring and bow loading using a
constant tension traction winch and 21 in. circumference nylon mooring line. Hoses are
made fast for loading (after grappling the line) using Cam-Lock connectors. Mooring line
and hose remain connected to the buoy when no tanker is on the SPM. The maintenance
boat is not required to assist the tanker in mooring to the tanker loading buoy.
There is a 4–5 day turn-around of the tanker leaving and returning to the buoy
depending on the UK port of discharge. In January 1979, a crack developed in the subsea
manifold in the 10 in. sales flowline pipe. The crack was located just below the upper
frame in an area that prevented repair or replacement of the damaged pipe by divers.
Apparently, the crack was caused by cyclical loads acting on the 10 in. flowline. Rig
motions were transferred through the tensioning system and export riser to the riser
connector on the manifold. The riser connector was supported on the manifold frame by a
short 10 in. spool assembly which was bolted to the upper frame structure. These bolts
Construction and operating history of north sea floating production systems 193
had loosened causing the 10 in. flowline below the upper frame to flex resulting in
fatigue and ultimately a stress crack. A new manifold was designed by Sedco-Hamilton
which was lighter and less complex than the original design. It was installed during the
latter part of 1979.
combined production stream by a subsea bulk line to the TW 58 production facility which
was already processing Argyll crude (see Fig. 5.3).
The Duncan manifold does not include a drilling template. Connection modules
containing the valving systems, which control the flow of oil and water to and from the
wells, are positioned around the manifold. They are designed as a single unit which can
be installed or, if necessary, replaced by divers. Up to 23 modules can eventually be
accommodated on the manifold. All maintenance on the manifold and wellheads will be
undertaken by divers.
All flowlines are flexible pipe. This was partly due to the thermal
TABLE 5.2
Statistics for the Drill Rig Deepsea Saga (prior to
its Conversion to Production Platform Deepsea
Pioneer)
Construction Built by Aker Group Bergen, Norway, 1974
Performance Water depth: 1250 ft
Drilling depth: 25000 ft
Construction and operating history of north sea floating production systems 195
Accommodation 90 persons
Helideck 84 ft diameter
Dimensions Length: 355 ft
Breadth: 221 ft
Depth: 130 ft
Total variable load 2869 tonnes
Storage Bulk mud and cement 8500cu. ft
Liquid mud 1280 bbl
Fuel 16326 bbl
Water for drilling 10200 bbl
Potable water 2300 bbl
Drilling equipment National 1625 DE 3000 HP
Pumps: 12-P-lbs Triplex
Prime Movers: 4 Berger 8 800 hp
Rotary Table: National C495
Derrick: EMSCO 160 ft
Cranes 2 No. National 52.5 tonnes @ 30 ft
Mooring 4 National E-500 Double Windlass
26000 lb Stevin Anchors
Positioning Honeywell RS 505
Remarks Self propelled
Source: Ocean Industry Directory of Marine Drill Rigs, September 1981.
insulation which can be incorporated into these lines, avoiding the necessity of burial and
preventing oil becoming viscous during the numerous shutdowns which will be
experienced. All operations are controlled hydraulically from the Argyll production
platform. The flow-line and test line were added to the existing Argyll riser system.
Duncan is currently (November 1984) producing from four wells; two further production
wells and one water injection well are planned for 1985.
phase of work for Duncan called for installation of a new manifold (built by Merpro)
beneath Deepsea Pioneer, and a flexible riser and flowlines for water injection.
The modification of the Deepsea Pioneer for duties as a production installation
included the following:
—removal of mud pumps and tanks,
—retention of derrick (needed for riser handling),
—upgrading of safety systems,
—upgrading of firewater systems,
—installation of single separation train and oil water handling facilities,
TABLE 5.3
Argyll, Duncan (& Innes) Major Contractors
Project Engineering: Bechtel
services
Platform Design: Kerr McGee Corporation
Contractors: Dover Oil & Gas, Aberdeen (TW 58)
Conversion: Wilson Walton, Teesside (TW 58) Peterhead Engineering at
Invergordon Service Base (Deepsea Pioneer)
Loading CALM Buoy by SBM Inc. Modified, SBM Rotterdam, installed at Argyll October
buoy 1982.
Source: Scottish Petroleum Annual, 1975.
Construction and operating history of north sea floating production systems 197
A special riser arrangement, attaching it directly to the subsea tree, was adopted at Innes.
This involves a frame-to-transfer
riser stressed from the top of the tree to the wellhead below, avoiding the need for a
separate base to handle the riser. Further wells may be possible at Innes although no
decision has yet been made. The oil will be processed by TW 58, and then piped via a 6
in. coflexip line, to the Argyll manifold where it will go straight on to the loading buoy
(see Fig. 5.7).
The Buchan field was discovered in 1974 in a deep reservoir 154 km east-north-east of
Aberdeen. The reservoir is a very dense fractured sandstone with recoverable reserves of
over 50 million barrels, by conventional
Construction and operating history of north sea floating production systems 203
TABLE 5.5
Buchan Field Statistics
Block 21/1A UK North Sea. Also extending into Block No. 20/5A which is
100% licenced by Texaco North Sea UK Ltd.
Operator BP Petroleum Development Ltd
Partners 24.58% BP Petroleum Development Ltd
12.71% Transworld Petroleum (UK) Ltd
5.76% Tricentrol Oil Corp. PLC
4.54% Goal Petroleum PLC
12.71% Clyde Petroleum PLC
12.71% Sulpetro (UK) Ltd
4.14% Charterhall Oil Ltd
0.90% Lochiel Exploration Ltd
12.71% Charterhouse
9.23% Texaco
Discovery date August 1974. BP became operator on the Block in May 1977.
Water depth 118 m (390 ft)
Sea bed Thin varying sand
Reservoir depths 2 900 m (9 600 ft) 3 200 m (10 500 ft)
Recoverable reserves 58 million barrels (original) 29 million barrels (remaining) (31/12/83)
(original)
Recovery factor 10–30%
API gravity 33.5°
Gas/oil ratio 300 scf/bbl
Sulphur content 0.8%
Platform installation September 1980
Production start May 1981
Peak production 47 000 b/d
Oil production, in 0.9—1981, 1.4—1982, 1.6—1983
millions of tonnes
Average gas flaring in 9 million cubic feet/day
1983
Source: BP
Technology for developing marginal offshore oilfields 204
TABLE 5.6
The Buchan Installations
Platform
(Light) displacement 13000 tonnes
Overall height 94.3 m
Drill deck to base of pontoons 45.5 m
Lower deck to base of pontoons 34.8 m
Normal draught 20.22 m
Survival draught 18 m
Operational displacement 19.404 tonnes
Deck area 2 326 m
Pontoon size 22 m dia.×7.5 m deep
Anchors
Number of anchors 10
Length of mooring wires 3400 m
Diameter of wires 70 mm
Min. breaking load (new) 340 tonnes
Subsea
Height of wellhead 10.3 m
Dimension of template 17.8×14.8 m
Distance of template to wells 1.6 km
B7 and B8
B4 2.5 km
CALM buoy
Distance from platform 1.67 km
Length of underbuoy hose 128 m
Height of buoy 4.57 m
Diameter 15 m
Displacement 506 tonnes
Number of anchors 6
Length of anchor chains 400 m
Length of mooring hawser 69 m
Construction and operating history of north sea floating production systems 205
Tankers
Length 271 m
Dead weight 100700 tons
Capacity 76000 tonnes
Source: BP
methods, plus an additional 8–10 million barrels by gas lift. The field is situated in water
depths of 112–118 m (see Tables 5.5–5.7).
The key factors which influenced the development for Buchan were the complexity of
the field’s geology, the relatively small amount of recoverable oil, the high probability
that the field would have a relatively short life-span, and the requirement to commence
production as quickly as
TABLE 5.7
Buchan Major Contractors
Project services Matthew Hall
D&S Petroleum Consultants
Worley Engineers Ltd
Platform Design—semi-sub Drillmaster, Pentagone design Conversion—Lewis
Offshore, Stornaway Modification for gas lift—Howard Doris, Loch
Kishorn
Template Design and fabrication—William Press Production Systems
CALM Design and fabrication and installation—Press IMODCO/Comex Houlder
Topsides Design—Matthew Hall
Fabrication—Aker etc.
Steel BSC
Installation Template—Wharton Williams
Flowlines—Santa Fe Marine Operations
Hook- Aker Offshore Contracting, BP
up/commissioning
Production services Sedco Hamilton Production Services
Source: Scottish Petroleum Annual, 1985.
possible. There were only two realistic options to be considered. First, the conventional
method of a fixed production platform with wells drilled after installation. Second, a
floating production platform with subsea wells drilled before the arrival of the platform.
The second method had the advantage of low construction costs, of being able to go into
production as soon as the platform was on station and, at the end of the field’s life, low
abandonment costs.
Technology for developing marginal offshore oilfields 206
The other major choice was in the method of transporting the oil from the field. Again
there were only two real options: first, a pipeline connection from Buchan to the Forties
pipeline system 46 km away or, second, an offshore tanker loading system. Cost was the
determining factor in this choice and the tanker system was selected. The development
comprises the following installations:
—A floating oil production platform converted from Pentagone design semi-submersible
exploration rig.
—A production/export riser system to carry the oil to and from the platform consisting of
one 12 in. export riser surrounded by eight
—A 12 in. submarine pipeline, 1.9 km long from the manifold on the template to the
pipeline end manifold (PLEM) under the CALM buoy. The PLEM is connected to the
buoy by a flexible hose.
—Two 100000 ton tankers, especially modified for bow loading and dedicated solely to
off-loading from the field. Tankers moored to the CALM buoy by a 21 in. diameter
hawser. Oil loaded through a 12 in. floating hose.
Cooled, processed oil from Buchan Alpha is delivered to a tanker via the export riser
to the export pipeline, through the pipeline end manifold (PLEM) and underbuoy hose to
the CALM buoy, and via a floating hose to the moored tanker. The specially modified
tankers are fitted with SPM mooring equipment and bow loading units.
Loading at the maximum rate of 70 000 b/d, it would take a week to fill each of the
100 700 ton tankers (their capacity is reduced to 76 000 tonnes by their having segregated
ballast tanks to eliminate the risk of pollution from discharge of oily ballast water). A
converted anchor handling tug/supply vessel is on station to provide marine support,
CALM buoy access for maintenance and the statutory safety/standby role.
6.1.1 Uncertainties
Uncertainty is the great enemy of marginal field developments. Uncertainties occur in the
area of costs and in the type and level of reserves and productivity. Despite industry’s
determination to use proven technology where possible, the operator of a marginal
offshore field will expect to break some new technological ground. Such pioneer work
can be expected to be associated with some cost over-run. It is reflected in the statistics of
the early North Sea developments where dramatic capital cost over-runs were
commonplace (see Tables 6.1 and 6.2). Such levels of over-expenditure cannot be
tolerated in a marginal field development, nor indeed should they be expected on quite
that scale. Likewise the degree of confidence in recoverable reserves and productivity
levels is more critical in a marginal field than in larger and more profitable fields. This
can create a problem since it is difficult to justify costly delineation drilling and data
collection on a reservoir which is clearly in the marginal category.
TABLE 6.1
Cost Increases (excluding Drilling) for Some Early
North Sea Developments
Projects Date Start estimate Costs £000000 Cost increase
£000000
Forties May 1972 296 715 142%
Brent July 1973 148 1140 670%
Sept. 1974 (393) (190%)
Beryl Early 1973 70 161 130%
Ninian Sept. 1975 585 1048 82%
Buchan June 1977 129.7 73%
March 1978 (135) 225 (66%)
Sum (incl. first est. for 1228 3289 168%
Brent)
Source: SINTEF. Note: numbers in parentheses refer to revised cost eStimates. These major cost
increases were due in large measure to the innovative developments which were required by the
harsh North Sea environment. Project cost increases of this magnitude are not unexpected when
innovative technology is being developed. Such cost increases would be currently quite exceptional
in the North Sea. Indeed several of the largest recent projects have been completed on schedule and
within budget. Innovative technological developments for marginal field applications would be
expected to experience some cost over-runs initially.
Marginal field economics and costs 211
TABLE 6.2
Major Causes of Cost Increases Based on Cost
Analysis of North Sea Oil and Gas Developments
in the Early 1970 s Carried Out by SINTEF for
Norwegian Petroleum Directorate
6. Weakness in project execution
5. Increased operator requirements
4. New government requirements
3. Unforeseen inflation
2. Under estimation
1. Start estimate
TABLE 6.3
Budget Estimate of Rental While Operating
Item $/day
Rig w/people 38000a
Process equipment 2700
Subsea tree 500
Tanker and mooring 9300
System maintenance 3000
Miscellaneous 1500
Total $55000
Note: Operator to provide boats/helicopter/fuel/well maintenance etc. during producing stage.
Excludes rig time for well completion costs and based on rental, test tree and production process
equipment.
a
Based on North Sea labour costs.
Source: Sedco Inc.
be justified. The costs of logging, coring and production testing is always minimal when
field development decisions are to be made. Thus thorough programmes for well data
acquisition are normally undertaken as a matter of policy by operators.
There are, however, particular cases where not only is productivity a problem but
where recovery factors are in doubt or where reservoir limits are best established by an
extended well test. Operation costs for an extended production test facility are considered
in Tables 6.3 and 6.4. On the basis of the figures projected for such a scheme a sustained
production of as little as 3000 b/d could be self financing on a day-to-day basis. Thus
many uncertainties associated with recovery factors and productivity could be resolved at
little cost beyond the delineation well. A disadvantage could be a delay in field
development due to the extended test itself.
The most promising route for reducing capital costs significantly would probably involve
the use of floating production/storage/export facilities instead of separate semi-
submersible production and floating storage units. As discussed in Chapter 3 this method
of production is not currently operational in North Sea type environmental conditions.
However, the technology is available and floating production/storage facilities will be
available shortly for North Sea duties.
TABLE 6.4
Budget Estimate of Capital Investment
Item $
A. Prepare rig for process equipment and subsea test tree
Equipment mobilisation 500 000
Rental services 100 000
Pipe/valves 40 000
Miscellaneous equipment 100 000
Labour 100 000
Safety gear 80 000
Miscellaneous contingency 80 000
Subtotal $1 000 000
B. Tanker loading equipment
Loading hose $1 000 000
Tanker mooring 600 000
Tanker modifications 100 000
$1 700 000
C. System abandonment $1 000 000
Total capital $3 700 000
Note: Excluding rig time and well completion costs and based on rental, test tree and production
process equipment.
Source: Sedco Inc.
the costs of each separate element is provided. By selecting the required options for a
field scenario and summing this, a total cost can be derived.
In any offshore development the main capital expenditure elements are:
—drilling and completion of production and injection wells,
—flowlines, subsea template, manifold and riser,
—offshore production facility with associated equipment,
—export system,
—dismantling costs at end of field life.
The other main cost element for any offshore development is the annual operating
expenditure.
Let us now consider each of these costs in turn.
TABLE 6.5
Drilling and Completion Unit Costs
Item Unit costs ($)
Template tree 0.7–1.0 m
Satellite tree 0.9–1.2 m
6 well template 7.0–11 m
10 well template 9.0–13 m
20 well template 16–20 m
8 bore rigid riser 3.0 m
20 bore rigid riser 5.0 m
8 bore flexible riser 2.0 m
20 bore flexible riser 4.0 m
Wellhead (18 3/4 in.×10 000 psi) 0.3–0.5 m
Control system 4.0–6.0 m
Workover system 2.0–4.0 m
Drilling cost (45–60 days per well) 60 000–75 000 per day
semi-submersible drilling units, with their more restricted deck load capacity and less
stable motion characteristics, are obviously considerably cheaper to purchase or lease.
The drill rig Deepsea Saga, an Aker H3 design built in 1976, was purchased in 1983 by
Hamilton Bros Oil & Gas Ltd for production duty on the Argyll field (See Chapter 5) for
a reported £19 million.
Order of magnitude costs for the production and process equipment and for power
generating equipment for installation on the drill unit are shown below. Clearly these
costs are closely related to the amount of processing required, the reservoir parameters,
power requirements for water injection and the suitability of the associated gas for power
generation. Whether new equipment for power generation, life saving, safety, flare,
utilities, etc. is required will depend on the age and condition of the equipment which is
already installed on the unit. The Transworld 58 (Innes field) and Buchan Alpha (Buchan
field) production units still use their original diesel generating equipment.
A typical SPM arrangement for harsh environments would consist of (1) an export line
from the production unit to the SPM; (2) one of the following SPM options: a CALM
buoy, a SALM, an ELSBM, a SPAR or an ALP; (3) a shuttle tanker arrangement to
transport the stabilised crude to shore. Unit costs for each of these items are given in
Table 6.7.
The Deepsea Pioneer (Argyll field) production unit had new gas turbines installed.
The gas lift package installed on Argyll in June 1985 cost a reported £5 m. See Table 6.6
for process and power equipment estimating costs.
Modification costs are notoriously difficult to predict despite the considerable
numbers of units which have already undergone conversion. Cost over-runs are generally
not due to the new process or generating equipment; they relate principally to the
difficulties which are encountered if the rig is not exactly as shown on drawings etc. or if
the condition of part of the structure or equipment requires unforeseen alterations to be
undertaken. Modification costs and durations can be
TABLE 6.6
Process and Power Equipment Costs
Throughput Production equipment ($ Generating equipment if required ($
(b/d) million) million)
20000 18.0 5.0
30 000 25.0 9.0
60000 39.0 14.0
optimised by careful selection of the rig in terms of rig power, variable deck load and
deck arrangement.
—Sedco Hamilton, who designed the conversion of the drill rig Transworld 58 for use on
the Argyll field, claimed that the installation of the modularised process equipment on
the units’ deck, in 1975, took only six weeks.
Marginal field economics and costs 217
—The conversion of the drill rig Drillmaster for the Buchan field took 22 months (see
Chapter 5). However, that conversion included several major delays that would not be
typical or expected.
—The conversion of the drill rig Deepsea Saga for use on the Argyll field took six
months during 1984. This timescale would be considered to be a realistic estimate for
most conversions.
—The cost of installation of gas lift on Buchan Alpha, plus inspection and maintenance
of that Pentagone semi-submersible, cost a reported £11.8 m in April 1985.
Costs of towage to site and installation costs depend on distance and duration of tow as
well as any special installation operations which may be required. Transworld 58,
Buchan Alpha and Deepsea Pioneer employ a conventional and unmodified anchorage
system. Many of the newer
TABLE 6.7
Unit Costs for Typical SPM Options in Harsh
Environments
10 in. Export line to SPM
Item Cost ($000)
Cost of line 66/km
Lay cost 154/km
Survey 45
Umbilical 300
CALM buoy
Item Cost ($million)
Buoy 6
Install 5
Piled anchorage (if required) 4
Note: Piled anchorages are not employed in the Argyll or Buchan fields.
designs (see Chapter 4) provide for piled anchorages which would be considerably more
expensive to install.
SALM
Technology for developing marginal offshore oilfields 218
SALM for operation in a North Sea type environment would be dependent on the size of
tanker and water depth. See the description of the Fulmar SALM in Chapter 2.
Costs would be of the order of $60–$80 m/unit for a Fulmar type SALM/yoke
installed. A Thistle type SALM would cost $20–$25 m installed.
ALP
Articulated loading platforms are large steel or concrete units (see Chapter 2) which are
site specific. Cost estimates for these units would be of the order of $60–$80 m.
Shuttle Tankers
The size and type of tanker employed would depend on
—daily production rate,
—time to shuttle to and from offloading points,
—environmental conditions at the SPM.
The number of tankers employed will depend on the type of SPM used. Two dedicated
shuttle tankers are normally used for CALM, SALM, ELSBM and ALP type offloading
systems. A single tanker can be used for SPAR and SALM/yoke type systems.
The options are to refurbish existing tankers or build new vessels. Cost of
refurbishment, survey and adapt for shuttle duties would depend on the conditions of
vessels purchased. Assume a five-year-old vessel costing $6–$7.5 m plus $2.2 m
conversion costs.
TABLE 6.9
Projected Cost of Complete Removal of Fixed
Platforms
Water depth (m) Average cost ($m, 1983)
Mild environment Severe environment
0–40 1–4 8
40–75 1–4 20
75–150 180
150–250 N/A 200
250 75 N/A
Source: E&P Forum—Paper OTC 5076, 1985.
Technology for developing marginal offshore oilfields 220
10%–12% of the field development costs, excluding the export system. However, this
may not be the most appropriate approach for a floating production system. An
alternative, showing suggested operating costs excluding the export system versus oil
throughput, is shown in Table 6.11.
Current operating costs for the Buchan field are reported to be £24 m (1984). This
includes the cost of leasing and operating shuttle tankers,
TABLE 6.11
Operating Costs for Floating Production Systems
Oil production (’000 b/d) Annual operating costs ($m)
10 25.0
20 27.0
40 33.0
60 36.0
80 38.0
Operating costs excluding the export system (i.e. costs of shuttle tankers).
£6.5 m. Ongoing capital costs have averaged £6.5 m/year excluding the major
modifications which were undertaken in 1984/1985 which were associated with the
installation of gas lift equipment on the installation.
Chapter 1
Carneiro, F.L.L.B., Ferrante, A.J. and Brebbia, C.A. Offshore Structures Engineering, Pentech
Press, 1977.
‘Development of the Oil and Gas Resources of the United Kingdom 1984’, UK Department of
Energy, HMSO.
‘Early Marginal Field Production Systems’, Fluor Corporation Report, July 1984.
‘Esso Offshore Technology’, Exxon Production Research Co., 1984.
‘Floaters Stage a Comeback in Cost Conscious Climate’, Offshore Engineer, May 1984, pp. 50–55.
Floating Production, Veritas Offshore Publication, DnV 1985.
Harris L.M. An Introduction to Deepwater Floating Drilling Operations, Petroleum Publishing Co.,
1972.
History of Petroleum Engineering, A Publication of the API, 1961.
‘Marginal Field Development—A Discussion Paper’, John Brown Engineering and Construction,
July 1984.
Parkinson, S.T. and Saren, M.A., ‘Offshore Technology: A Forecast and Review’, Financial Times
Business Information.
Ratzer, J.P.L., ‘The North Sea—The Future Outlook’, RINA Conference on Developments in
Floating Production Systems, London, 1984.
Shell Briefing Service, ‘The Offshore Challenge’.
Snowden, D.P., ‘Floating Production Systems for North Sea Marginal Fields’, Offshore
Technology Conference, May 1984.
‘The North Sea and British Industry: The New Opportunities’, The Economist Intelligence Unit,
April 1984.
Chapter 2
Production Supports
Biess Haar, A., ‘The Design Aspects of Production Facilities on Floating Production and Storage
Units’, Proceedings of Marginal Field Conference, London, 1983.
Booth, D., ‘Extending the Margins’, The Oilman, March 1983.
Booth, D., ‘The Gorilla is Born’, The Oilman, November 1983.
Carter, J.H.T. and Foolen J.A., ‘Tanker Based Floating Production Systems for Deep Water’, Deep
Offshore Technology Conference, 19–22 October 1981, Palma de Mallorca.
Carter, J.H.T. and Foolen, J.A. ‘Evolutionary Developments in Advancing the Floating Production
Storage and Offloading Concept’, Journal of Petroleum Technology, 35(4), 695–700, April
(1983).
Eykhout, F. and Foolen, J.A., ‘An Integrated Floating Production Storage and Offloading—
SALS—in 380 Feet Water Depth’, SPE 3142, Offshore Technology Conference, Houston,
Texas, 1978.
Bibliography 224
‘Floaters Stage a Quick Comeback in the Cost Conscious Climate’, Offshore Engineer, May
(1984).
Klein, P.J., ‘The Development of the SALS Floating Storage Cum Production Facility Offshore
South East Asia’, Conference, 21–24 February 1978.
McCloud, W.R. and Smulders, L.H., ‘An Analysis of Tanker-Based Floating Production Systems
for Small Offshore Fields,’ Journal of Petroleum Tech., 34 (8), 1871–9 (1982).
Magni, M. and Poldervaart, L., ‘SALS Unit for NILDE field’, Offshore, December 1979.
Montoya, L.S. and Lopex-Fanjul, G.M., ‘Dorado Field Production System—A solution to
individual permanent vertical access to several wells from a semi-submersible’, October 1981,
4041.
Morrison, D.G., ‘Guyed Tower with Dynamic Mooring Properties’, Journal of Structural
Engineering, 109 (11), November (1983).
‘Multi-well Tazerka Raises Marginal Development Hopes’, Offshore Engineer, March 1983.
Perrett, G.R., ‘Floating Production Systems’, The Oilman, January 1983.
Patel, M.H., ‘Technical Assessments of Floating Production Systems,’ Marginal and Deepwater
Oilfield Development Conference, London 1984.
Quintela, C. and Smulders, L.H., ‘Single Anchor Leg Storage/Production Terminal Offers
Attractive Alternative to Production Platforms Offshore. Brazil’, 1978.
Remery, G. and Beare, A., ‘Tanker Based Production’, The Oilman, January 1975.
Smulders L. and Klein, P.J., ‘Castellon Sea bed Wells Flow to Process and Storage Tanker’, Oil
and Gas Journal, 1 January 1978.
Smulder, C.H. and Remery, G.F., ‘The Mooring of a Tanker to a Single Point Mooring by a Rigid
Yoke’, OTC 3567 Offshore Technology Conference, Houston, Texas, 1979.
Van Dam, J., ‘Alternative Production Facilities for Offshore Development’, Offshore North Sea
Technology, Stavanger, 6 September 1978.
Vosper, K.W. and Stevens, B.G., ‘Development Options for Small Gas Fields’, EUR 344 European
Petroleum Conference, London, 25–28 October 1982.
Williams, L.H. and Smulder, C.H., ‘The Cadlao Floating Production Storage and Offloading
System (FPSO): A New Concept in Offshore Production’, Offshore South East Asia—
Conference, 9–12 February 1982.
Williams, L.H. and Pierce, D.M., ‘FPSO 11—A Second Generation Floating Production System for
Offshore Philippines’, October 4274 Offshore Technology Conference, Houston, Texas, 1982.
Risers
Cornelson, D.J. and Lawson, J.E., ‘New Approach to Riser Couplings Could Turn Weakness into
Strength’, Offshore Engineer, March 1981.
Dareing, D.W. and Huang, T., ‘Marine Riser Vibration Response Determined by Model Analysis’,
Petroleum Engineer International, May 1980.
Dumay, J.M. and Bouvard, M., ‘Introduction to the Concept of Flexible Risers’, Coflexip
publication.
Dumazy, C., ‘Articulated Column as a Production Riser in 300–400 m Water Depth’, The Oilman,
September 1984.
‘Flexible Risers’, The Oilman, September 1984.
‘Flexible Steel Pipe for the Oil and Gas Industry’, Coflexip publication.
Muller, D., Castela, A. and Schawann, J.C., ‘Production Riser is Key to Deep Sea Operations’, Oil
and Gas Journal, 5 May 1980.
Pettanati, C. and Dumay, J.M., ‘Flexible Dynamic Riser for Floating Production Facility in the
North Sea’, Offshore Europe, 6–9 September 1983.
Wybro, P.G. and Davies, K.B., Journal of Petroleum Technology ‘The Dorada Field Production
Risers’, 34 (12) (1982).
Bibliography 225
Subsea Equipment
Arendt, H. and Brands, K., ‘Subsea TFL Systems—A Technological Update’, Offshore
Technology Conference, 1979, OTC 3449.
Booth, D., ‘Extending the Margins’, The Oilman, March 1983.
Brands, K.W. et al., ‘The Insert Tree Completion System’, Offshore Technology Conference, 1981,
OTC 4043.
Burkhardt, J.A. and Anderson, R.E., ‘Submerged Production System—Progress Report of Offshore
Pilot Test’, Offshore Technology Conference, 1977, OTC 2823.
Calder, I.D., ‘Subsea Equipment Design to Enable Completion to a Floating Production Platform’,
OE 1981, SPE 10398.1.
Coltharp, E.D. and Coffelt, D.E., ‘Experience with Subsea Well Control Systems’, Offshore
Technology Conference, Houston, 1981, OTC 4038.
Ladedcy, V.H. et al., ‘Grondin Experimental Station—Diverless Experiments’, Offshore
Technology Conference, Houston, 1981.
‘Le Champ Frigg Nord-Est’, Elf publication.
Morton, A.W., ‘New Concepts Used in the Murchison Field Submerged Production System’,
Offshore Technology Conference, 1981, OTC 4040.
‘N.E.Frigg—Subsea Production Nears as Column Floats Out’, Offshore Engineer, July 1983.
Reimert, L.E., Gray, D.J. and Machado, Z.L., ‘A Ten Well Subsea Production System for the
Enchova Field’, Offshore Technology Conference, Houston, 1979, OTC 3448.
‘Shell Looks to 600 m’, The Oilman, September 1984.
‘Subsea Completion’, Vetco publication.
‘Subsea Production Systems’, Vetco publication
‘The N.E.Frigg Project’, Elf publication.
‘The Skuld Project’, Elf publication.
Wilson, R., ‘Subsea Satellite Wells Development and Practical Operational Experience in the North
Sea’, Offshore Technology Conference, Houston, 1980, OTC 3731.
Loading Systems
Buyzen, J.P.M., ‘Operational Experience with the Offshore Loading Units AUK—ELSBM and
BRENT—SPAR’, Offshore Europe, Aberdeen, 1979, OE-79 SPE 8175.1.
Chauvin, J.M., ‘Single Point Mooring Systems’, China Oil, 1983.
Chauvin, J.M., ‘EMH Single Point Mooring Systems’, Offshore Australia, October 1984.
Dallas, M., ‘Offshore Loading Systems Shuttle Tanker Installation’, European Offshore Petroleum
Conference, London, 1980, EUR 209.
Dupont, B. and Simon, J.M., ‘Packaged SPM and FPSO Units’, EMH 165.
Eylshourt, F. and Foolen, J.A., ‘An Integrated Floating Production Storage and Offloading
System—SALS in 380 ft Water Depth’, Offshore Technology Conference, Houston, 1978, SPE
3142.
Gahtani, B.M. et al., ‘Five Years Optimising and Problem Solving at Saudi Arabia’s Tu’aymah
SPM Terminal’, Offshore Technology Conference, 1979, OTC 3563.
Gruy, R.H. and Kidg, W.L., ‘Marginal Field (Early Production): Options for Offshore Loading’.
Gruy, R.H. et al. ‘The Loop Deepwater Port: Design and Construction of the Single Anchor Leg
Mooring (SALM) Tanker Terminals’, Offshore Technology Conference, Houston, 1979, OTC
3562.
Hays, D.L. et al., ‘Operation of an Articulated Oil Loading Column at the Beryl Field in the North
Sea’, Offshore Technology Conference, 1979, OTC 3563.
Klein, P.J., ‘The Development of the SALS Floating Storage Cum Production Facility’, Offshore
South East Asia, Singapore, 1978.
Bibliography 226
McNamara, J.F., ‘Offshore Export Systems’, New Technology and Offshore Oil, Dublin, April
1981.
Maari, R., ‘Offshore Mooring Terminals’, SBM Inc.
Mack, R.C. et al., ‘Fulmar, The First North Sea SALM/VLCC Storage System’, Offshore
Technology Conference, Houston, 1981, OTC 4014.
Magni, M. and Poldervaart, L., ‘SALS Unit Tapped for NILDE Field’, Offshore, December 1979.
Marcello, J.T., Schneider, R. and Flory, J.F., ‘Tenth Anniversary Report—Single Anchor Leg
Mooring Technology’, Offshore Technology Conference, Houston, 1980, OTC 3802.
Miller, J.L., Hughes, H. and Dyer, R.C., ‘First Year’s Operation Experience of the Deepest SPM in
the World’, Offshore Technology Conference, Houston, 1979, OTC 3561.
Poranski, P.F., Gillespie, A.M. and Smulders, L.H., ‘The First Yoke Mooring for a VLCC in Open
Ocean’, Offshore Technology Conference, Houston, 1979, OTC 3564.
Quintela, C. and Smulders, L.H., ‘Single Anchor Leg Storage/Production Terminal Offers
Attractive Alternative to Production Platforms’, Offshore South East Asia, 21–24 February
1978.
Rees, T.E., Reber, M.A. and Seery, J.R., ‘Design, Installation and Field Operations of Offshore
Tandem Loading System—Nido Field, Offshore Philippines’, Offshore Technology
Conference, Houston, 1981, OTC 4012.
Schultz, A.R. and Brown, R.J., ‘SPM and Floating Production System Technology Aids Marginal
and Deepwater Developments’, R.J.Brown Associates publication, October 1980.
Smulders, L.H., ‘The First Single Anchor Leg Storage/Production Terminal System’, Moscow
Symposium, October 1978.
Smulders, L.H. and Klein, P.J., ‘Castellon Seabed Wells Flow to Process and Storage Tanker’, Oil
and Gas Journal, January 1978.
Smulders, L.H. and Remery, G.F., ‘The Mooring of a Tanker to a Single Point Mooring by a Rigid
Yoke’, Offshore Technology Conference, Houston, 1981, OTC 3567.
Vilain, R.H., Pinto, J.L. and Guillaume, D.M.J., ‘A New Type of Single Point Mooring Developed
and in One Year’, Offshore Technology Conference, Houston, 1980, OTC 3806.
Chapter 4
Abbot, P.A., Tulurea, D. and Hashins, J., ‘The Highlander 6000 Floating Production Vessel’,
Conference on Marginal and Deepwater Oilfield Development, London, April 1983.
‘Advanced Concepts are Tailored to the Task’, The Oilman, August 1985.
Behan, I., ‘IMFP 300—A Second Generation of FPSO’, Conference on Marginal and Deepwater
Oilfield Development, London, April 1983.
Carter, J.H.T. and Foolen, J.A., ‘Evolutionary Developments Advancing the Floating Production,
Storage and Offloading Concept’, Journal of Petroleum Technology, April 1983.
‘Cybele Semi-Submersible Production Platform’, EPM/Technique 2000.
Denise, J.P., ‘A Compliant Riser System for Floating Production Platforms’, Conference on
Marginal and Deepwater Development, London, 1985.
‘Dorada Hosts Unique Subsea Unit’, Offshore, August 1980.
‘Floating Production Services’, Det norske Veritas, April 1985.
‘Floating Production System for Deep Hostile Environment’, Ocean Industry, June 1983.
Hammet, D.S. and Johnson, J.S., ‘First Floating Production Facility—Argyll’, OTC Paper No. 282,
Offshore Technology Conference, 1977.
Hart, V.A., Montgomery, J.I. and Worley, M.S., ‘The Economic Evaluation of Hull Forms for
Floating Production’, Paper SPE 13154 1984, SPE Technical Conference, Houston, 1984.
Bibliography 227
Haynes, A.P., Jones, B. and Foster, K., ‘A Tanker Based Development Scheme for the Central
North Sea’, Seminar on Design and Operational Aspects of Floating Production Systems,
London, 1984.
Homer, A., ‘Floating Units Cut Production Costs’, Offshore, May 1983.
‘IMFP 300—A New Concept of Proven Technology’, Integrated & Modular, 1984.
Machado, E., ‘Petrobras Experience in Offshore Early Production Systems’, International Meeting
on Early Production Systems, Rio de Janeiro, 1982.
‘Nippon Kokan Wins Contract for Offshore Oil Production Tanker’, Veritas, November/December
1984.
Pass, H., ‘The Development of a Mobile Production System Incorporating a Compliant Production
Riser’, Oyez Seminar, London, 1984.
‘Penta 7000, Designed with IFP, Floating Production Platform’, CFEM.
‘Santa Fe’s Deepwater Floating Production Systems’, Ocean Industry, June 1984.
‘Sea Plex Class 500–4 For Hostile Environments’, Sea Plex Corporation; ‘Sea Plex Retrievable
Production Platform’; Sea Plex UK Ltd.
‘Sedco—Marginal Field Development Contractor’, Sedco Inc.
‘Semi Platform Planned for Balmoral Field’, Offshore, September 1983.
‘Severe Weather Jack-up’, The Oilman, May 1984.
Smith, J.R. and Jordan, P.A., ‘Barge Mounted Production Systems for Floating Production Units’,
Conference on Marginal and Deepwater Oilfield Development, London, 1985.
‘SWOPS Considered for Norwegian Sector’, Offshore Engineer, September 1984.
‘T 2005-C Mobile Jack-up Drilling Platform’, CFEM.
‘The Gorilla is Born’, The Oilman, November 1983.
Worley, M.S. and Montgomery, J.I., ‘A New Concept in Floating Production Systems’, Seminar on
Design and Operational Aspects of Floating Production Systems, London, September 1984.
Also SPE 12986 European Petroleum Conference, London, October 1984.
Chapter 5
Argyll Field
‘Argyll, Hamilton Adapts to Exploit UK’s First Oil Field’, Offshore Engineer, January 1975.
‘Argyll’s Innovative Production Riser System’, Petroleum Engineer, October 1975.
Bifani, R. and Smith, C.A., ‘The Argyll Field after a Decade of Production’, Offshore Europe,
1985.
Elwes, P.J.G., ‘Argyll Field Development’, Petroleum Review, pp. 323–7.
Haggard, M.E., ‘Argyll SBM Production’, Offshore Services, November 1975, pp. 84–6.
Kirkland, K. and Johnson, J., ‘The Production Riser for the Argyll Field’, OTC Paper No. 2327,
May 1975.
Offshore Engineer, January 1984.
Petroleum Times, 20 February 1976, pp. 8/22/23.
‘Producing Oil from a Semi-Submersible’, Ocean Industry, May 1975, pp. 59–64.
Scottish Petroleum Annual, 1975, p. 39.
The Oilman, March 1984.
World Oil, September 1983.
Buchan Field
‘Buchan “Experiment” Termed Worthwhile’, Drilling Contractor, July 1984.
Bibliography 228
Darnborough, E., ‘The Buchan Field Development’, Paper EUR 230, European Offshore Petroleum
Conference, 1980.
Logan, B.L. and Rothwell, E.G., ‘Buchan Development Project—Conversion of a Drilling Rig into
a Floating Production Platform’, Paper OTC 3958, Offshore Technology Conference, 1981.
Mieras, A.A., ‘Operational Experience of the Buchan Field Floating Production and Offshore
Loading System’, Paper SPE 12433, 5th Offshore South East Asia Conference 1983.
Scottish Petroleum Review Annual, 1985, p. 51.
‘The Buchan Oil Field’, BP Petroleum Development Ltd.
Williams, P.W., ‘Buchan—The First Nine Months’, Paper EUR 277, European Petroleum
Conference, 1982.
Chapter 6
Bayly, C.H. and Cox T.F., ‘Conditions for Development of Smaller Discoveries in the North Sea’,
European Petroleum Conference 1982.
Hall, J.D., Conversion Techniques—Enhancing Recovery and Profitability of Marginal Offshore
Fields, Marginal Oilfield Development Conference 1983.
Kemp, A.G. and Rose, D., North Sea Economics Revised—Petroleum Economist April 1982.
Moe, J., Technological Development and Cost Uncertainties, Offshore Gotenburg Marine
Technology Conference 1981.
Montague Smith, D.A., Finance for Marginal Oilfield Development—Enhancing Recovery and
Profitability of Marginal Offshore Fields, Marginal Oilfield Development Conference 1983.
Morrison, D.D. and Jolliffe, V., ‘North Sea Tax and Economics’, European Petroleum Conference
1982.
Noroil July 1982 p. 21 North Sea Field Development.
Noroil August 1982 p. 67 UK Field Development.
Offshore, 1979, The Economics of Wet and Dry Subsea Completions.
Offshore, March 1980 p. 61, Economical Marginal Fields.
Parkinson, S.T. and Saren, M.A., Offshore Technology, A Forecast and Review, Financial Times
Business Information.
Smith, J.R., Carruthers R., Enhancing Recovery and Profitability of Marginal Offshore Fields,
Marginal Oilfield Development Conference 1983.
Appendix 1
Conversion Factors
The units of measurement used in the text reflect the amalgam of oilfield and engineering
units which constitutes the accepted usage in the offshore industry.
Length: 1 mm=3.937×10−2 in.
1 m=3.281 ft
1 km=6.214×10−1 miles (statute)
=5.306×10−1 miles (nautical)
Area: 1 mm2=1.55×10–3 in.2
1 m2=10.76 ft2
Volume: 1 cm3=6.102×10−2 in.3
1 m3=35.31 ft3
Barrels (oil)=42.0 gallons (oil)
Mass: 1 kg=2.205 lb
1 tonne=1000 kg=0.984 imperial ton
Approximate equivalents: 1 tonne oil=425 therms
Blowout An uncontrolled flow of well fluids from the wellbore either at the wellhead or
into the formation. Blowout preventers enable the driller to prevent damage at the
surface while restoring the balance between the pressure exerted by the column of
drilling fluid and formation pressure.
Bottom hole assembly (BHA) The lower end of the drill string comprising the drill bit,
drill collars, heavyweight drill pipe and ancillary equipment.
Bumper sub A unit placed in the drill string of a floating rig to compensate for heave or
vertical motion.
Bundle A group of several parallel cables, hoses, lines, or tubing leading from platform
controls to remote actuating units.
Choke A gauged restriction inserted into a fluid flowline in order to restrict the flow rate.
Compensators Hydraulically operated equipment that compensates for the upward and
downward motion (heave) of a floating installation.
Connectors Hydraulically controlled clamps to mate and secure marine riser segments,
and choke and kill lines. One connector joins the lower ball joint of the marine riser to
the BOP stack, and another secures the BOP stack to the wellhead. The use of
connectors reduces the need for diver assistance.
Christmas tree The assembly of valves, pipes and fittings—usually high pressure—used
to control flow of oil and gas from the casing head.
Directional drilling Although wellbores are normally planned to be drilled vertically,
many occasions arise when it is necessary or advantageous to drill at an angle from the
vertical. Controlled directional drilling makes it possible to reach subsurface points
laterally remote from the point where the bit enters the earth.
Downhole safety valve A valve fitted to the production tube of a well some distance
below the sea bed in order to permit flow to be stopped in an emergency.
Down time Time during which no production is possible due to adverse weather
conditions, while downhole equipment is being changed, during well logging etc.
Dry tree A subsea wellhead where the equipment is enclosed in a watertight chamber.
Dynamic positioning The method of maintaining a floating offshore structure on
location over the well by means of computer-controlled thruster motors, thus obviating
the need for anchors and allowing production in water depths too great for anchoring.
The motors respond constantly to any changes in the wind, currents, waves etc. to
maintain the unit in a constant position.
Appendix 2 231
Flare An open flame used to burn off unwanted gas; see Flaring.
Flare stack The steel structure on a rig or platform from which gas is flared; see Flaring.
Flaring Burning off of gas produced in association with oil which, for technical or
economic reasons, cannot be re-injected or shipped ashore.
Gas-to-oil ratio (GOR) The volume of gas at atmospheric pressure produced in
association with a unit volume of oil.
Heave compensation Counteraction of vertical movement of the riser string. Heave
compensators have a typical stroke of 5.5 m.
Hundred year storm A combination of storm conditions (wave height and sustained
wind speed) that should, on average, only occur once every hundred years in a
particular area. Offshore structures are designed to withstand such storms.
Manifold centre An arrangement whereby production from several wells may be
combined in any way desired for forwarding through one or more pipelines. They are
commonly used offshore in order to minimise the length of individual well flowlines
while permitting the selection of individual wells for testing, segregation of different
types of oil, or other purposes.
Marine riser The pipe which connects an exploration rig, drilling platform or production
platform to a subsea wellhead or subsea pipeline during drilling or production
operations.
Module The box or ‘package’ containing equipment for installation on a production
platform. These modules, which may weigh up to 2000 tons each, are constructed
ashore and installed as self-contained units on the structure, each one serving a
specific purpose, e.g. crew module, control module, generator module etc.
Multiphase flow Simultaneous flow of two or more fluid phases (e.g. gas, oil, water) in
the same flow channel, whether pipeline, well tubing or reservoir rock. Because of the
pseudo-elastic interfaces between phases, multiphase flow is relatively inefficient, e.g.
with a given pipe and pressure difference, the flow rate of a mixture of oil and water is
less than it would be with either alone (assuming similar viscosities).
Pig A piece of equipment that is inserted into a pipeline and is carried along by the flow
of oil or gas; used to clean or monitor the internal condition of the pipelines or to mark
an interface between two different products.
Pressure maintenance Injection of gas or water into a reservoir in order to maintain
pressure. The aim is to maintain production rates, although the fluids injected often
sweep additional oil to the wells, thus increasing recovery from an oil reservoir.
Processing plant Special plant installed on a production platform or at a pipeline
terminal to separate gas, oil and water from a mixture containing some or all of these
components; also called treatment or separation plant.
Proven reserves The estimated quantities of hydrocarbons which geological and
engineering data demonstrate with reasonable certainty to be recoverable in future
years from known oil and gas reservoirs under existing economic and operating
conditions.
Pumps Mechanical devices to transport liquids or gases from one vessel to another along
pipelines. There are a wide variety of pumps of three general types: reciprocating, gear
and centrifugal. The choice depends on the height to which the liquid is to be pumped
(delivery head), quantity and nature of the liquid (viscosity, corrosive nature, etc.) and
availability of prime movers (electric motors, turbines, etc.).
Appendix 2 232
Refractory Materials which can stand high temperatures and resist corrosion and
abrasion. Particularly used for furnace linings.
Reservoir A stratum in which oil or gas is present.
Reservoir pressure The fluid pressure in an oil or gas reservoir.
Saturation diving Diving for a length of time which results in a diver’s body absorbing a
maximum of inert gases used in breathing at a given pressure level. Decompressing
time and equipment are required.
SBM Single buoy mooring, used for loading oil into tankers in the open sea. Also
sometimes called single point mooring (SPM). The principle is that the tanker can
moor to load oil whatever the direction of wind or current and swing at its mooring to
present the least resistance to the prevailing conditions. ELSBM stands for exposed
location single buoy mooring: a large SBM specially designed for exposed locations.
Semi-submersible rig A floating drilling platform that is supported by underwater
pontoons; generally used for exploration purposes but may be used for production.
Shuttle tanker An oil tanker which makes regular round trips between a producing field
and an onshore terminal or refinery.
Significant waves Wave heights observed and recorded by experienced seafarers. A
significant wave is equal in height to the average of the one-third highest waves under
the same sea conditions.
SPAR A type of single buoy mooring developed by Shell, incorporating storage
facilities, so that in the event of weather conditions temporarily preventing tanker
loading, production need not be shut off.
Spread mooring A system of multiple anchors and lines distributing the loads imposed
by currents, waves and winds. Pretensioning of anchor lines determines the initial line
loadings. A continuous monitoring of individual line loads and automatic adjustments
in tension increase the effectiveness of this station-keeping system.
Subsea completion (sea bed completion) A method of completing a well or wells
whereby equipment controlling oil-flow, normally mounted in a surface platform, is
housed in a special construction on the sea floor.
Subsea wellhead A wellhead installed on the sea floor and controlled remotely from a
platform or floating production facility or from land.
Template A design pattern with built-in guides for specific equipment and structure to
assure their usefulness. Examples: template for installing well-conductor pipe;
platform jacket with well slots, guides, sleeves for installation of piles; subsea
production system with spacing to accommodate the wells it will produce.
Tensioners Equipment used to maintain tautness or constant pulling stress on marine
risers, guide lines, drill string, and applications of wire and control lines on floating
vessels. Heave compensation is accomplished through air pressure vessels, control
panel, air compressor, air dryer units, and idler sheaves.
Thruster propeller A small propeller mounted underneath a floating structure or vessel
to enable it to change or maintain its position.
Turret A roller-mounted structure beneath the derrick of a floating drilling vessel to
which anchor lines are attached. The vessel can be revolved 360° around the mooring
plug by the bow and stern thrusters.
VLCC Very large crude carrier: i.e. tanker between 160000 and 319 999 dwt.
Appendix 2 233
Water drive A recovery process in which oil or gas is driven out of a reservoir by the
pressure of underlying water.
Water injection A process whereby treated water is pumped into the reservoir rock in
order to maintain the reservoir pressure.
Wax Solid hydrocarbon which is present in some crude oils, especially in paraffinic
crudes. Wax deposits in pipelines and equipment can cause mechanical problems.
Weather window The part of the year when the weather can normally be expected to be
suitable for carrying out offshore operations such as pipeline laying or platform
installation.
Wellhead The control equipment fitted to the top of a well casing, incorporating outlets,
valves, blowout preventers, etc.
Wellhead cellar In sea bed completions, a dry, steel structure enclosing the wellhead.
The inside of the structure is at atmospheric pressure. To service the equipment,
engineers are lowered in a capsule from a support vessel (the capsule also at
atmospheric pressure), which docks with the cellar. The engineers can work in the
cellar in shirt-sleeve conditions with fresh air and electrical power supplied by
umbilical cord from the support vessel.
Well logging A comprehensive record of all data collected during the drilling of a well,
enabling a highly detailed picture of the strata to be built up.
Wet tree A subsea wellhead where the equipment is exposed to the sea.
Wireline Any line of wire or cable used for downhole operations. Two types are usually
distinguished: piano and electric wireline. The former is a thin single-strand line of
high tensile steel used to lower instruments or tools into a well, and/or to install,
retrieve or operate ‘wireline equipment’, e.g. failsafe safety valves installed in tubing.
Electric wirelines are normally used for surface recording instruments, e.g. those used
for making electric logs.
Workover The process whereby a completed production well is subsequently re-entered,
and any necessary cleaning, repair and maintenance work done.
Index
Cadlao
field, 168
process, 95
Caisson vessel, 222–3
CALM (catenary anchor leg mooring) buoy, 30, 31, 75–9, 248, 249
Campos Basin riser system, 51
Capital
costs, 255
investment, 255, 265
Casablanca
field, 132
riser system, 51–2
Castellon
field, 59, 164
FPSO, 96
SALS, 87–9
Catenary anchored tower (CAT), 91
Catenary Anchor Leg Rigid Arm Mooring (CALRAM), 28
Cayo Arcas fixed tower, 92–3
Central Cormorant
field, 178
underwater manifold centre (UMC), 64–5
Christmas trees, 58
Commercial fields, 1
CONAT (concrete articulated tower) production systems, 220–2
Concrete gravity platforms, 23
Control systems, subsea, 67
Conversion factors, 275
Corvina field, 148
Cost(s), 251–65
drilling and completion, 257
elements, 256–65
field operating, 255, 263–5
increases, 253
parameters, 252–6
process and power equipment, 259
production support, 257
Dan Duke, 28
Decommissioning costs, 262
Deepsea Pioneer, 238, 240, 241, 259, 260
Deepsea Saga, 237, 258, 260
Deepwater
gamma tower, 223–4
gravity tower, 223–4
production concepts, 222–5
Denmark, future fields and prospects, 14
Development options, 251
Deviated drilling, 22
Dorado
field, 128
Index 237
riser system, 47
Drilling costs, 257
Drillmaster, 30, 100, 248, 260
Duncan field, 71, 235–8
Dynamic positioning (DP), 203
Economics, 251–65
Ekofisk field, 27, 106, 212
Electrical control systems, 67
Emilio field, 176
Enchova
field, 103
Leste I, 124
Leste II, 126
riser system, 48
Equipment leasing, 265
Espoir field, 28, 114
Exploration drilling, 16–17
Export system, 261
Exposed location single buoy mooring (ELSBM) system, 75, 80, 261
Extended
production test facility, 255
well test systems (EWT), 227–30
general scenario, 229–30
severe environments, in, 265
Exxon submerged production system (SPS), 63–4
Fixed
production platforms, 3, 22–4
tower, 91–3
Floating
concrete caisson vessel, 222–3
concrete monotower, 223
drilling techniques, 21
oil patch, 205–7, 258
Flowlines, 25, 94
Frigg North East field, 24, 36, 37, 64, 182
Fulmar SALM, 85–6
Garoupa
field, 68
North field, 130
subsea production system, 60–2
Garoupinha field, 144
Gas
production, 19–25
treatment and disposal, 96
Gathering system (manifolding), 94–5
Gotaverken Arendal GVA 5000 semi-submersible, 191–2, 258
Grondin subsea experimental station, 62–3
Gulf Tide, 27, 212
Index 238
Pampo
field, 136
Linguado field, 137
Parati
field, 112
RJS-194, 154
Phillips Enterprise, 28
Piled steel structures, 23
Pipeline(s), 25
diameter versus throughput, 262
end manifold (PLEM), 30, 249
size and unit costs, 262
Pirauna field, 150
PLEM (pipeline end manifold), 30, 249
Poseidon concept, 65–6
Processing facilities, 93–6
Production
test ship (PTS) Petrojarl/Golarnor, and, 200–2
headers, 94
support, 26–41
barge based, 32–3, 208–10
characteristics of, 40
costs, 257
design criteria for, 39–41
factors affecting choice of, 41
jack-up, 27–9, 211–15
semi-submersible concepts, 190–8
tanker based, 31–2, 198–210
future development of, 210
Productivity, 254, 255
Riser(s), 41–56
alternative designs, 52–4
articulated column, 53
bundle, 42
catenary flexible with subsea tower, 54
comparative assessment of, 54–6
composite systems, 43
connection package (RCP), 44
definition, 42
design criteria, 44–5
flexible, 45, 48, 49–52
joint, 43
lines within system, 43
operational requirements and systems, 45–9
ribbon, 52–3
stand, 43
test stump, 44
tower, subsea, 215–16
RJS-90 Viola field, 156
RJS-150 field, 118
RJS-236 field, 152
manifold, 60
production technology, 70
riser tower, 215–16
template, 57–8
Sul del Pampo field, 134
SWOPS oil production system, 202–4, 258
UK Continental Shelf, 4
UK offshore discoveries and development prospects, 5
Uncertainties, 252
Uncommercial fields, 1
Yoked tower, 91