Customer :

Turbine :
Contract No :

Subject: Mechanical Run Test of the Turbine

Instruments /
Sl. Equipments/ Acceptance
Activity Remarks
No. Precaution to be Criteria
taken
Test Bed Preparations
1 Turbine is to be placed in position
on the test bed
2 Steam inlet and exhaust pipe is Ensure that there
connected with proper steam joints is no reverse
pulling on the
turbine
3 Tighten all foundation bolts in
sequence
4 Ensure normal oil level in the base
plate
5 Connect cooler to the turbine
6 Connect cooling water to the cooler
7 Electrical connection to be made to Direction of
AOP, Solenoid valve and pressure rotation of AOP
switches is to be confirmed
8 Gauges are fitted on to the junction Calibrated
plate to record values of bearing oil pressure gauge /
pressure, relay oil pressure, AOP temperature
discharge pressure, Exhaust pressure gauges /
and also bearing / water temperature indicators are to
be used
9 Switch on the AOP Ensure no oil Lub oil
leakages from the control
pipes / joints. pressure as
Check for cooling per the
water circulation design
by observing the recommend
cooler outlet line ation
10 Check for sub assemblies For Alternately
independent sub
testing of assemblies
sub may be
assemblies approved on
refer to WI turbine by
no: QA
ASY/05/353

Page 1 of 3
Customer :
Turbine :
Contract No :
Instruments /
Sl. Equipments/ Acceptance
Activity Remarks
No. Precaution to be Criteria
taken
11 Open all steam drain valves of
turbine

Testing of Turbine
12 Open the steam inlet valve Drain steam till
dry steam is
obtained in line
13 Close the drain valves
14 Engage throttle valve / Stop and Wait for warming
Emergency valves up
15 Open steam inlet valve gradually till Check for undue
rotor rotates at around 200 rpm vibration / noise
16 Increase the speed of the turbine to Recheck for
500 rpm undue vibration /
noise
17 Trip turbine by operating manual Check for
trip lever stopping of
the turbine
18 Re-start the turbine, gradually Check for
increase the speed in steps of 10 – governor take
15% of the rated RPM over speed
19 Measure speed at Governor take Calibrated Ensure
over tachometer governor
take over
speed of
60-110% or
85-115%
20 Ensure AOP cut in/out Pressure switch Design
specs
21 Set over speed trip Ensure for total QA to Keep the
stoppage of approve the steam inlet
turbine after over over speed stop valve
speed trip trip settings in open
condition
22 Close the stop vale and reset the
governor to minimum position
23 Engage throttle valve, open stop and
emergency valve, open steam inlet
stop valve

Page 2 of 3
Customer :
Turbine :
Contract No :
Instruments /
Sl. Equipments/ Acceptance
Activity Remarks
No. Precaution to be Criteria
taken
24 Run the turbine at rated speed Vibration meter Maximum Vibration
allowable parameters
velocity not to be
to exceed measured by
4mm/sec QA
25 Give back pressure (if applicable No leakages QA to
only in case of back pressure subject to approve
turbines) arresting of
gland / joint
leakages
26 Roll the turbine continuously at Three
rated speed till the bearing oil consecutive
temperature stabilizes ½ hour
readings
shall be
constant
27 Trip the turbine Manual trip /
Hand trip
28 Close the steam inlet stop valve;
open the drain valves on the turbine
and supply lines
29 Run AOP for 2 hours, switch off
AOP, Close cooling water
circulation

Responsibility: Assembly Engineer

Approving authority: Quality Assurance Engineer

Records: MRT Log sheet QAP/03/200