G+2 ARBOR SCHOOL

LONG LEAD APPROVED MATERIALS TRACKING DELIVERY SCHED

S/N REF. NO. DESCRIPTION Proposed Make

ELECTRICAL
1 ARJ/PJ237/EL/MS-10 STRUCTURED CABLING SYSTEM OPTERNA

CENTRAL BATTERY SYSTEM


2 ARJ/PJ237/EL/MS-12 NAFFCO
( Emergency Lighting System )

3 ARJ/PJ237/EL/MS-14 FIRE ALARM W/ VOICE EVACUATION SYSTEM SIMPLEX- USA

4 ARJ/PJ237/EL/MS-16 GENERATOR & ASSEMBLIES PERKINS

5 ARJ/PJ237/EL/MS-18 LV SWITCH GEAR SWITCHGEAR

6 ARJ/PJ237/EL/MS-19 ATS PANEL ASCO - USA

7 ARJ/PJ237/EL/MS-23 CCTV SYSTEM HONEY WELL

8 ARJ/PJ237/EL/MS-24 ACCESS CONTROL SYSTEM HONEY WELL


9 ARJ/PJ237/EL/MS-25 MASTER CLOCK SYSTEM BODET

10 ARJ/PJ237/EL/MS-26 LIGHTING CONTROL SYSTEM QLITE

HVAC
1 ARJ/PJ237/AC/MS-01 CHILLERS TRANE

2 ARJ/PJ237/AC/MS-02 FAHU / AHU VTS CLIMA

3 ARJ/PJ237/AC/MS-03 CHW PUMPS EBARA

4 ARJ/PJ237/AC/MS-04 FAN COIL UNITS ( FCU ) VTS CLIMA

5 ARJ/PJ237/AC/MS-05 VENTILATION FANS S&P

6 ARJ/PJ237/AC/MS-22 PRESSURIZATION UNIT EBARA

WATER BIRD WATER TREATMENT


7 ARJ/PJ237/AC/MS-23 CHEMICAL DOSING POTS
CHEMICALS .L.L.C
PLUMBING
1 ARJ/PJ237/PL/MS-03 SUMP PUMP GENERAL PUMPS SPAIN

2 ARJ/PJ237/PL/MS-16 SOLAR WATER HEATER & CALORIFIER SOLAHART - AUSTRALIA

DOMESTIC PUMPS
3 ARJ/PJ237/PL/MS-17 LOWARA
(CIRCULATION/BOOSTER/TRANSFER PUMPS)

4 ARJ/PJ237/PL/MS-18 SILVER COOPER IONIZATION UNIT CULLIGAN INTERNATIONAL

5 ARJ/PJ237/PL/MS-21 GRP WATER TANK SOLICO

FIRE FIGHTING
1 ARJ/PJ237/FF/MS-02 FIRE FIGHTING SPECIAL SYSTEMS SHIELD UK

FIRE FIGHTING PUMP


2 ARJ/PJ237/FF/MS-03 NAFFCO
( Electric -Diesel - Jockey )

3 ARJ/PJ237/FF/MS-04 FOAM SYSTEM SHIELD UK

FIRE FIGHTING SYSTEMS ( Fire Hosereel Cabinet & Fire


4 ARJ/PJ237/FF/MS-05 NAFFCO
Extinguisher )

5 ARJ/PJ237/FF/MS-06 FM 200 & CLEANAGENT SYSTEM FIKE

6 ARJ/PJ237/FF/MS-07 HYDRANT SYSTEM SHIELD UK


2 ARBOR SCHOOL BUILDING

LIVERY SCHEDULE ( ARBOR SCHOOL )


Date
SUBMISSION EXPECTED
SUPPLIER
DATE RCVD DATE STATUS DELIVERY DATE

LAN & WAN 19.10.17 22.10.17 B 24.01.18

NAFFCO 07.11.17 19.11.17 B 05.02.18

SIBCA ELECTRONICS LLC. 30.10.17 09.11.17 B 07.02.18

CASABLANCA 10.10.17 29.10.17 B

ARJ SWITCHGEAR 08.11.17 14.11.17 B

ASCO POWER TECHNOLOGIES 29.08.17 11.09.17 B

LAN & WAN 04.12.17 16.12.17 C

LAN & WAN 01.11.17 15.11.17 B


LAN & WAN 10.10.17 18.10.17 B 15.02.18

SABID TECH. 06.12.17 13.12.17 B 08.02.18

TRANEBVBA 14.10.17 18.10.17 B 10.03.18

VTS CLIMA GULF FZCO 13.11.17 14.11.17 B 05.02.18

AL AWTAAN TRADING 05.12.17 10.12.17 B

VTS CLIMA GULF FZCO 09.11.17 12.11.17 B 10.02.18

LEMINAR 04.10.17 12.10.17 B 03.02.18

AL AWTAAN TRADING 09.11.17 16.11.17 C

WATER BIRD 21.11.17 03.12.17 B 20.01.18


LEMINAR 11.11.17 12.11.17 B 15.02.18

ECOVAL TRADING LLC 06.12.17 13.12.17 C

ARJ WATER TECHNOLOGY 29.11.17 03.12.17 B 28.02.18

CULLIGAN INTERNATIONAL 11.12.17 23.12.17 B

SOLICO 14.10.17 18.10.17 B 10.01.18

NAFFCO 28.10.17 07.11.17 B 10.01.18

NAFFCO 28.10.17 05.11.17 B 05.01.18

NAFFCO 21.12.17 23.12.17 B

NAFFCO 28.10.17 07.11.17 B 15.01.18

NAFFCO 21.12.17 23.12.17 B

NAFFCO 23.11.17 04.12.17 B 25.01.18


4/9/2018

REMARKS

After DEWA Approval

After DEWA Approval

After DEWA Approval

After Sample approval by client

After Sample & Drawings Approved


Approval by ( Green Building & Leed )
After approval by client