Академический Документы
Профессиональный Документы
Культура Документы
PERT + TIME
ESTIMATES + COMMUNICATIONS
(P + 4M + O)/ 6 Pessimistic, Most Likely, Optimistic
PERT Budget Estimate --> ´-10% a +25%
Triangular Distribution:
Definitive Estimate --> ´-5% a +10%
(P + M + O)/ 3
Variance (Project) (∑(Standard Deviation)^2)square root PTA (Point of Total Assumption) ((Ceiling Price - Target Price)/Buyer's Share Ratio) + Target Cost
SPI (Schedule Performance Index) EV / PV Net Income Before Taxes (NEBT) / Total Sales or
ROS (Return on Sales)
BAC / CPI Net Income After Taxes ( NEAT ) / Total Sales
FINANCIAL
AC + ETC -- Initial Estimates are Flawed NEBT / Total Assets or
EAC (Estimate At Completion) ROA (Return on Assets)
AC + BAC - EV -- Future Variance are Atypical NEAT / Total Assets
AC + (BAC - EV) /SPIxCPI -- Future Variance Would be Typical NEBT / Total Investment or
ROI (Return on Investment)
ETC (Estimate To Complete ) EAC - AC NEAT / Total Investment
EARNED VALUE
Percentage Complete (EV / BAC)x100 Working Capital Current Assets - Current Liabilities
VAC (Variance At Completion) BAC - EAC Discounted Cash Flow Cash Flow x Discount Factor
Values for the TCPI index of less then 1.0 is good because it
indicates the efficiency to complete is less than planned. How
TCPI (To Complete Performance Index) efficient must the project team be to complete the remaining Savings = Target Cost – Actual Cost
work with the remaining money?
( BAC - EV ) / ( BAC - AC )
CONTRACTS
NPV (Net Present Value) Bigger is better…
Less is better…
Payback Period
Net Investment / Avg. Annual Cash Flow
BCWS PV Total Cost = Actual Cost + Contract Cost
BCWP EV
ACWP AC