UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT
STA R SPECIFICATION
1/16
STAR SPECIFICATION N°
\ STGPS - MR1
REV 5
STEEL STRUCTURES
GENERAL
TABLE OF CONTENTS
1 SCOPE ................................................................................................................................ 3
1.1 General ................................................................................................................................ 3
1.2 Documents ........................................................................................................................... 3
1.3 Materials .............................................................................................................................. 3
5 INSPECTION ..................................................................................................................... 15
STAR RAFINERI A.S. (STAR)
UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT 3/16
SPECIFICATION STAR SPECIFICATION N°
STGPS – MR1
REV 5
1 SCOPE
1.1 General
This specification covers the requirements for the design, fabrication and erection of Structural
Steelworks.
Any points not specifically covered by this specification or by the various codes of practice and
Standards will be resolved by good engineering practice and where necessary referred to
Engineering.
1.2 Documents
All calculation shall be on A4 size sheet except related computer out puts.
Drawing sheet sizes shall be as indicated in STGPS-A1
1.3 Materials
All steel plate and sections shall be grade St 37 in accordance with Turkish Standards,
(Standards of Turkish Institute of Standards) or S275JR according to EN10025. Steel plates of
important thickness might require higher resilience class.
For bolts nuts and welding rods Turkish Standards or EuroNorms (EN14399, EN20898, EN12072,
EN 499, EN 790) shall be followed.
Structural hollow sections shall conform to EN 10210 or EN 10219 or EN ISO 11960. Their use is
allowed upon Client approval.
Embedded steel plates shall conform to grade St 37 in accordance with Turkish
Standards,(Standards of Turkish Institute of Standards) or S275JR according to EN10025.
Different resilience class might be needed for thick plates according to EN 1993-10.
Structural anchor bolts shall conform to grade St 37 Standards of Turkish Institute of Standards)
or S275JR. If pretension is needed sleeved anchor bolts shall be foreseen and high tensile steel
is requested.
Gratings shall conform to grade St 37 in accordance with Turkish Standards, (Standards of
Turkish Institute of Standards) or S275JR according to EN10025. Galvanization shall be in
accordance to EN 1461 and the exposition classes for steel defined as per EN 12944.
2 DESIGN CRITERIA
CONTRACTOR shall refer to STGPS-R4 BD0506A_40A2 CIVIL DESIGN LOADS which covers
the loads and loading combinations to be considered in the design of foundations and concrete or
steel structures for petrochemical plants.
STAR RAFINERI A.S. (STAR)
UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT 4/16
SPECIFICATION STAR SPECIFICATION N°
STGPS – MR1
REV 5
3.1 General
CONTRACTOR shall supply the general layout plan of units on which all structures, control
house, shelters, buildings, substations, warehouses, pipe racks, cable ducts, maintenance areas,
paved areas and access roads will be shown.
General layout plan of units shall be submitted to OWNER for approval. Any revision of layout
plans shall be responsible for design and construction of all civil engineering structures not
mentioned but required for the safe and sound realization of the PROJECT.
Cranes monorails trolleys etc. shall be provided for maintenance of equipment inside or above of
the structures. Capacity shall be adequate to handle heaviest equipment component to be
removed.
A drawing of the complete mathematical model (including joint and element identification
numbers) used to represent the structure in the computer generated analysis shall be provided.
List of all loads for each loading combination (hand calculations) shall be provided (including point
of application direction and intensity etc.) separately from computer print-outs.
All the calculation inputs and outputs (joint coordinates, section properties, all applied forces, all
element forces, displacements etc. not only for critical elements or joints) shall be provided for
each loading condition.
Verification of element forces and joint displacement and beam deflections shall be included to
reports.
All joint, base plate, anchor bolt etc. design calculations shall be provided (included strength,
dimensions, diameter and length)
STAR RAFINERI A.S. (STAR)
UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT 5/16
SPECIFICATION STAR SPECIFICATION N°
STGPS – MR1
REV 5
7) Cantilevers 1/300
Clear headroom above the platforms and walkways shall be 210 cm minimum
3.3.2 Flooring
Open galvanised metal grating shall be used for platform and walkway floor plates. This shall be
rectangular pattern pressure welded grating with 30x3 or 25x5 mm main bars and 6 mm square
twisted transverse bars. Flooring shall be supplied complete with welded-on binding bars,
necessary fixing clips and stair treads shall be complete with welded on end plates and rolled
steel dimpled nosing fitted to front edge. The ends of grating panels (and the edges of radially cut
panels) and cut-outs shall be reinforced. Fasteners for both floor plate and grating shall be
designed to be clipped to the supporting structure. Welding to or drilling through the support
beams is not permitted. Toe boards are required around openings where the normal clearance
between the edge of the plate and the equipment is greater than 75 mm.
3.3.3 Handrails
For typical details refer to steel standards BD0506A-0000-46-001. Reference norm is EN 14122.
3.3.5 Stairways
For typical details refer to steel standards BD0506A-0000-46-001. Maximum vertical rise in a
single flight shall be limited to 4.0 m with landings 0.9 minimum length. Open galvanised metal
grating shall be used for all stair treads. Reference norm is EN 14122.
2. A general arrangement drawing of each structure showing all section sizes and mark numbers
together with sufficient dimensions and elevations to enable it to be used as the erection
drawing shall be supplied.
3. Shop drawings showing fabrication details of all members, splices and connections. These
drawings shall preferably be based on the use of the bar method in which each member is
detailed as a separate prior written approval of OWNER.
4. All drawings and details of structures shall be prepared in accordance with calculation
assumptions and calculation results.
5. Details shall show proper reinforcement required in beams at large blocks by adding web
plates or slotted flange plates.
6. The amount of torque which will be applied to high tensile friction bolts at erection shall be
listed on drawings. The minimum size of bolts shall be 20 mm. diameter, except where flanges
prohibit the use of 20 mm. diameter size.
7. Beam to column connections shall be arranged to facilitate erection without tilting of columns.
8. All material showed on a drawing shall be numbered and listed in material list.
10. The tops of columns for open frame structures and pipe support yard racks shall be cut
square with the top of the highest beam framing into the column to facilitate future additions.
11. At all anchor bolt holes in beams for equipment, provide 10 mm. thick stiffener plates at the
anchor bolt hole site of the web, stiffener plates at the anchor bolt hole side of the web,
stiffeners to straddle anchor bolts. On beams 250 mm. and smaller, a stiffener shall be for the
full depth of the beam web. For beams 300 mm. and larger, stiffener length shall be one half
of the nominal depth of the beam with the top milled to bear against the underside of the top
flange of the beam.
12. At equipment support beams with bolsters, provide stiffeners in the web to match the
stiffeners in the bolster above the beam, stiffener length shall be one-half of the nominal depth
of the beam with the top milled.
13. At horizontal or vertical bracing's holes in gussets shall be arranged to eliminate eccentricity.
The minimum thickness of gussets shall be 8 mm.
STAR RAFINERI A.S. (STAR)
UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT 10/16
SPECIFICATION STAR SPECIFICATION N°
STGPS – MR1
REV 5
14. On welded or bolted trusses, splices to ship the largest possible section as shop assembled
units shall be detailed. Splices for bolted joints shall be detailed. Field welding is not to be
used as splices.
The Fabricator shall be responsible for the design of all connections not specifically detailed on
the arrangement drawings. Loads indicated in chapter 2 shall be used in design. Moreover,
capacity design approach must be strictly followed. General indications according to DBTYBHY
and Eurocode 8 shall be implemented in design.
Design shall include any stiffeners required to carry the forces through the connection and the
connected members and in fully compliance with local codes and standards. Moreover, particular
attention shall be placed to surface preparation and accessibility for painting.
The Fabricator shall prepare and take full responsibility for the accuracy of all shop detail
drawings. Shop details shall be in strict accordance with arrangement drawings and
specifications. The practices outlined in this Job Specification shall be incorporated in the shop
details. Shop details and shop fabrication drawings of structural steel shall be done by the
structural steel Fabricator. Contractor Engineer will spot check the shop drawings details.
Moreover, connections, fabrication and erection shall be in accordance with EN 1990 and
EN12944.
All members both before and after fabrication shall be straight and true, free from twist and
corrosion and in accordance with the profile specified on the drawing.
Prior to fabrication of all members, actual dimensions are to be checked for variations from the
nominal dimensions due to over-rolling. This is particularly important to ensure that correct
alignment of top faces of members which support equipment or steel flooring, especially if seating
cleats are being used. Setting out of beam to column bolts shall generally be measured from the
top of the beam.
Shop connections shall be either bolted or welded. Unless noted otherwise site connections shall
be bolted. Bolts shall not protrude more or less than two threads from the nut. Welding of
brackets, either in shop or field, which tends to prevent the structure from being dismantled at any
time after erection will not be permissible.
All stairways, cat ladders, walkways and platforms shall conform to OWNERS Standard Drawings.
Cat ladders and cages shall be shop assembled and supplied complete or in sections for field
bolting to supporting clips or beams.
Connections shall normally have a minimum of two bolts except for items such as lacing or sag
rods. Departures from this rule may be permitted but only by express permission of OWNER.
Steel flooring shall be supplied complete with manufacturer’s standard clips or other fixings. All
known openings for piping will be marked on the drawings prior to fabrication of the flooring and
these openings are to be cut and reinforced in the shop.
STAR RAFINERI A.S. (STAR)
UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT 11/16
SPECIFICATION STAR SPECIFICATION N°
STGPS – MR1
REV 5
Crane girders for overhead gantry type cranes shall be attached to the roof leg of their supporting
stanchions by means of diaphragms which shall be as nearly as possible to the full depth of the
girder. Suitable packings are to be provided to permit horizontal and vertical adjustment of the
girder. Crane rails shall be bolted to the girders and rail joints shall be staggered from girder joints
by at least 1 m. All bolted connections are to be provided with anti-vibration lock washers.
Where underslung-type cranes are called for, anti vibration lock washers are to be used on all
bolted connections.
At joints in continuous trolley-beam, a dowel shall be inserted in the bottom flanges to ensure
proper alignment.
At the ends of all runway beams, crane girders and the like, adequate stops shall be provided to
prevent running-off by the hoist or crane.
Where friction grid bolts (high strength bolts) are noted, these shall be of load indicating type and
extra care shall be taken in the fabrication of steelworks.
The members with their end plates shall be fabricated to exact lengths. The end plates shall be at
right angles or such other angle noted on the drawings to the axis of the members.
The end plates shall be in one piece and of sufficient thickness to prevent distortion when welded
to members. Any distortion that may occur shall be rectified by machining faces of end plates.
Even so the requirement for exact length must be complied with.
The two contact surfaces to a joint shall be brought together in the shop to check for perfect
seating and the required angle between members.
Shop weldings shall be performed by submerged arc process (MIG/MAG) according to EN 1011.
Each welding shall be qualified according to EN ISO 15607, 15609, 15614 Parts 1 & 2.
CONTRACTOR shall ensure that the welders used are qualified to perform the work involved in
accordance with EN ISO 287. Moreover, Shop firm shall be certified according to EN ISO 3834.
Standard EN ISO 5817 shall be used by DESIGNER, as reference norm, to define welding quality
acceptance levels to be agreeded with OWNER. If not expressely stated quality level C is
assumed.
The OWNER reserves the right, through the inspector to call for the welders to re-perform the
appropriate tests.
The minimum size of weld to be used on stressed connections is 5 mm fillet.
Electrodes shall comply with AWS and the make may require to be approved by OWNER.
Consumables shall comply with EN 790 and EN 499.
For major welded details such as full strength splices in frames, the OWNER reserve the right to
ask the CONTRACTOR to outline his proposed welding procedure for each joint, including the
following information:
1. The type, size and classification of the electrode.
The proposed procedure thus outlined shall be approved by OWNER before fabrication proceeds.
Before giving such approval, OWNER reserves the right to call for specimens to be prepared in
the presence of OWNER or his representative inspector and using the proposed procedure. The
inspector may, if the considers it necessary, call for these specimens to be etched, trepanned,
bent, radiographed, or otherwise tested to ensure its soundness. The cost of preparation and
testing of such specimens shall be borne by CONTRACTOR.
The preparation of fusion faces may be by shearing, machining grinding or automatic gas cutting.
Where hand gas-cutting is used, the cutter shall be accurately guided so that the edge is uniform.
Welding shall not be carried out on surfaces which are wet, greasy, oily or otherwise
contaminated.
When the ambient temperature is less than 5 Deg C, fusion faces and the adjacent metal shall be
preheated warm to the hand before welding.
Regardless of ambient temperature, preheating shall always be considered where welding of thick
sections is being carried out. The necessity for preheating and/or post-heating shall be approved
as part of the overall welding procedure as outlined in related paragraphs above.
Sections to be joined shall be securely held in position during welding. The faces of sections
being butt-jointed shall not be out of alignment by more than 25 of the thickness of the material up
to 6 mm or more than 2 mm for thicker sections.
Welding procedures shall be so arranged that distortion is minimized
All welds shall be subject to approval by OWNER or by his representative inspector and no major
weld or the adjacent steelworks shall be coated until the inspector has approved the weld.
Temporary protection by coating with boiled linseed oil is, however permissible. He shall reserve
the right to reject any weld which shows evidence of porosity, slag inclusions, cavities, cracks or
lack of proper fusion. In the event of such rejection, CONTRACTOR shall carry out such
measures of repair, reinforcement, or replacement of the defective joint as OWNER may direct, all
at no extra cost.
Steel structures will be erected such that deviation from vertical axis shall not exceed 1 mm per
meter of the structure height in any direction and it will not be more than 2 cm in total. Necessary
measurements shall be carried out with CONTRACTOR and OWNER together for plumbing
checks. Particular care and detailed erection sequence study shall be issued for important lattice
and truss beams.
Protective coatings shall be in accordance to the Job specification STGPS-N1
Fireproofing shall be in accordance to STGPS-N2. Fireproofing shall be noted F.P. on the
arrangement drawings and on erection drawings. Before fireproofing required elements, all
secondary pipe supports shall have been erected and connected to the structure.
STAR RAFINERI A.S. (STAR)
UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT 13/16
SPECIFICATION STAR SPECIFICATION N°
STGPS – MR1
REV 5
Where possible, Contractor will provide the Fabricator a 3D model to be used into preparing
erection and shop drawings. Erection plans shall be drawn by the Fabricator with erection marks
shown thereon in letters at least 3 mm. high.
Each structure shall have an index sheet. On small jobs, the index may be added into the erection
plan, where convenient. An Erection bolt list specifying the numbers, size, type of connectors, grip
and ordered length of connectors for each connection shall be furnished by the Fabricator. This
list shall be broken down by categories and tiers, as outlined below:
1. Beam to column connections.
2. Beam to beam connections.
3. Column splices.
4. Bracing to column connections.
5. Bracing to beam connections, etc.
A summary of all field connectors by size and length shall also be included.
Where a standard bill of material form is not an integral part of the detail drawing, separate bills of
material listing all main material and fittings with space for convenient "weighing up" of the
structure shall be furnished by the Fabricator.
Beams marks shall be stamped on beams at the same end as they are shown on plan view of the
Fabricator's erection plan. The numerical portion of the beam mark shall identify the floor or tier
thus: beam 1 to 199 on first or lowest tier, beams 200 to 299 on 2nd tier, 300 to 399 on third tier,
etc.
On a structure having one or both dimensions over 30 m. in plan view, all erection marks shall be
suffixed with the derrick suffix letter shown on the arrangement drawing.
All unsymmetrical beams, girders, or trusses, shall have a direction painted on one end,
preferably north or east.
All members to be marked "top", where possibility of erecting the member inverted exists.
All columns to have the mark painted on the outside face of the flange and marked "North" or
"East". Column marks shall carry a tier suffix for spliced columns.
On vertical bracing the mark shall be painted on the lower end.
Where a member is shipped in two or more pieces, each piece shall have a different mark.
The use of R or L suffixes for opposite hand marks will not be permitted.
Examples of typical marks for a structure prefixed "A" is given below.
A-B402 Beam 402 in 4th tier
A-D-6 (0-2) Column at coordinate D-6, from grade to 2nd tier
A-C1-NW Column 1 (not coordinated since no hyphen between C&1), with
derrick suffix NW (northwest) for a large square structure
A-G17, B Girt 17 in a long structure with derrick suffix B
STAR RAFINERI A.S. (STAR)
UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT 15/16
SPECIFICATION STAR SPECIFICATION N°
STGPS – MR1
REV 5
All marks shall be painted on the steel in legible fashion, with letters and figures a minimum of 37
mm. high.
All rods, turnbuckles, clevises, etc., are to be tagged and marked with the tag wired firmly to the
member.
All bolts, washers, etc. shall be shipped in kegs or crates and tagged clearly marked as to size,
diameter and length.
On duplicate units, color coding shall be used where called for on the arrangement drawing.
Where color coding is required, the Fabricator shall paint a one inch wide band all around each
member at one end, including kegs, or crates, etc., in the color designated by the arrangement
drawing.
Galvanized members shall be tagged with a metal plate having raised letters so that the mark
shall be visible after galvanizing. This metal plate shall be tack-welded to the member prior to
galvanizing. The fabricator may submit alternate proposal for marking galvanized members,
subject to Contractor written approval.
As alternative fabricator may propose different marking system, which can be used only after
Contractor written approval.
5 INSPECTION
CONTRACTOR shall satisfy OWNER that the fabrication of the steelworks has been carried out in
accordance with the terms of this specification and the various standards quoted herein. To this
end CONTRACTOR shall provide OWNER such co-operation and facilities as may be necessary,
including the right of access to CONTRACTORs work.
OWNER shall dimensionally and visually check the steelworks in so far as he deems it necessary,
with special attention of main members, equipment bolt drillings etc. in this event, shop assembly
is to be carried out in the presence of OWNER, and to his satisfaction.
No material is to be erected until OWNER has either waived or given his approval.
Approval by OWNER shall not absolve CONTRACTOR from responsibility for the adequacy of his
designs, draughting or fabrication or for their compliance with the terms of this specification.
The material and workmanship covered in this specification can be subjected to inspection in the
field or shop by a qualified Inspector. However, such inspection shall not relieve the Contractor of
his responsibility to furnish materials and workmanship in accordance with the contract
requirements. The Inspector shall have the option to make, but shall not be limited to, the
following typer of tests and inspections:
Determine chemical composition of steel;
Determine mechanical properties of steel;
Inspect shop-fabricated structural steel members and assemblies for conformance with the
requirements specified;
Inspection of shop assembled;
Make inspection of shop welds as follows:
o Visual inspection of all shop weld;
o Liquid penetrant inspection;
STAR RAFINERI A.S. (STAR)
UNIT N°000
AEGEAN REFINERY
PROJECT (ARP) SH/OF
GENERAL PROJECT 16/16
SPECIFICATION STAR SPECIFICATION N°
STGPS – MR1
REV 5
Extent and cost charge for testing shall be specified in the relevant Contractor Material requisition.
All shipments, including partial shipments, shall be accompanied by sufficient bolt or connectors
of the proper size and length to erect the material shipped with each shipment.
Prior to shipment, the Fabricator shall transmit the necessary detail and erection drawings
Ladders with ladders cages, handrails, platforms and trusses shall be shop assembled as
permitted by shipping limitations and with assurance of no damage.