Вы находитесь на странице: 1из 9

SITE INSTRUCTION NO.

C-001 DATE : 27/03/2011 G

SITE INSTRUCTIONS

Contract No. 20931060/00


Project Title : NEW 110/13.8 KV Al-Andulus-2 Substation
Contractor Name AL-GIHAZ COMPANY
Attention: PROJECT MANAGER, AL-GIHAZ COMPANY
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR.ALI BAGSHAN ,PROJECT MANAGER,DTA,SEC-WOA,JEDDAH
ENGR.Abdul Moshin Otaibi,PROJECT ENGINEER,DTA,SEC-WOA,JEDDAH

URGENT
SUBJECT : Three week schedule

GENTLEMEN,

It has been observed that as per agreed in weekly meeting to submit the three week schedule by contractor
on Saturday but still not yet submitted. It is directed to submit the same as early as possible to not delay
the project activities.

This is for your immediate attention and further necessary action.

REGARDS

SEC/SATECH
Contractor: AL-GIHAZ CO.
Prepared By: Issued By:
Name: Mohammed Hassan Bidri Mohd Akhtar
Job title: CIVIL ENGINEER SITE CIVIL ENGINEER
Signature:
SITE INSTRUCTION NO. C-002 DATE : 28/10/2009 G

SITE INSTRUCTIONS

Contract No. 4/00/01/5003/01/30


Project Title : NEW JIZAN INDUSTRIAL 132/13.8 KV SUBSTATION
Contractor Name AL-GIHAZ COMPANY
Attention: PROJECT MANAGER, AL-GIHAZ COMPANY
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR.MAJID ALFAIYA ,PROJECT MANAGER,DTA,SEC-SOA,ABHA
ENGR.MUNAWWAR HASHMAT,PROJECT ENGINEER,DTA,SEC-SOA,ABHA

URGENT
SUBJECT : Shortage of Manpower at site
GENTLEMEN,

It has been observed that the sub-contractor is decrees the manpower at site today. When question to him
he replied the problem of invoice is pending with Al-gihaz so we don’t have the labor payment that is the
reason. Shuttering & rebar for ground floor slab & foundation of transformers is in progress the work is
delay at site due to the decrees of manpower.
It is directed to arrange the manpower immediately and solve the problem to expedite the work on site.

This is for your immediate attention and further necessary action.


REGARDS

SEC/SATECH
Contractor: AL-GIHAZ CO.
Prepared By: Issued By:
Name: GEORGE MARANO Bidri Mohd Akhtar
Job title: CIVIL ENGINEER SITE CIVIL ENGINEER
Signature:
SITE INSTRUCTION NO. C-001 DATE : 19/06/2011 G

SITE INSTRUCTIONS

Contract No. 21031044/00


Project Title : NEW Salamah-2 110/13.8 KV S/s Jeddah
Contractor Name ABB contracting Company
Attention: Engr. Abdul kareem PROJECT MANAGER, ABB contracting Company
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR. Al-taiyyar ,PROJECT MANAGER,DTA,SEC-WOA,JEDDAH
ENGR. Abdul mohsin otaibi, PROJECT ENGINEER,DTA,SEC-WOA,JEDDAH

URGENT

SUBJECT : Site Mobilization

GENTLEMEN,

It has been observed that the site mobilization still not completed. Still there is no any facility for telephone,
fax and internet on site it not accepted. There are no approved drawings available on site and ABB staff is
not as per organization chart on site. It is directed to submit the revised baseline schedule and three week
time schedule at site and approved Mix design for concrete to expedite the work at site without any delay
to the project.

This is for your immediate attention and further necessary action.

REGARDS,

SEC/SATECH
Contractor: ABB CO.
Prepared By: Issued By:
Name: EDGAR RIVERA Bidri Mohammed Akhtar
Job title: CIVIL ENGINEER CIVIL ENGINEER
Signature:
SITE INSTRUCTION NO. C-002 DATE : 23/06/2011 G

SITE INSTRUCTIONS

Contract No. 21031044/00


Project Title : NEW Salamah-2 110/13.8 KV S/s Jeddah
Contractor Name ABB contracting Company
Attention: Engr. Roshan Ali PROJECT MANAGER, ABB contracting Company
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR. Al-taiyyar ,PROJECT MANAGER,DTA,SEC-WOA,JEDDAH
ENGR. Abdul mohsin otaibi, PROJECT ENGINEER,DTA,SEC-WOA,JEDDAH

URGENT

SUBJECT : Earthing mesh level below the Raf

GENTLEMEN,

It has been observed that the level for ear thing mesh below the raft foundation is not clear mention in the
overall substation grounding layout so please rectify the same as early as possible and without any delay of
excavation on site.

This is for your immediate attention and further necessary action.

REGARDS,

SEC/SATECH
Contractor: ABB CO.
Prepared By: Issued By:
Name: EDGAR RIVERA Bidri Mohammed Akhtar
Job title: CIVIL ENGINEER CIVIL ENGINEER
Signature:
SITE INSTRUCTION NO. C-003 DATE : 27/06/2011 G

SITE INSTRUCTIONS

Contract No. 21031044/00


Project Title : NEW Salamah-2 110/13.8 KV S/s Jeddah
Contractor Name ABB contracting Company
Attention: Engr. Roshan Ali PROJECT MANAGER, ABB contracting Company
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR. Al-Taiyyar ,PROJECT MANAGER,DTA,SEC-WOA,JEDDAH
ENGR. Abdul mohsin otaibi, PROJECT ENGINEER,DTA,SEC-WOA,JEDDAH

SUBJECT : Trail mix

GENTLEMEN,

It has been observed that the trail mix done by ABB without information to a consultant on site it will not
accepted. Any activity regarding the project should be inform earlier to concerned project consultant by RFI
with supporting drawing or document in future then only the activity will accepted.

This is for your immediate attention and further necessary action.

REGARDS,

SEC/SATECH
Contractor: ABB CO.
Prepared By: Issued By:
Name: EDGAR RIVERA Bidri Mohammed Akhtar
Job title: CIVIL ENGINEER CIVIL ENGINEER
Signature:
SITE INSTRUCTION NO. C-004 DATE : 03/07/2011 G

SITE INSTRUCTIONS

Contract No. 21031044/00


Project Title : NEW Salamah-2 110/13.8 KV S/s Jeddah
Contractor Name ABB contracting Company
Attention: Engr. Roshan Ali PROJECT MANAGER, ABB contracting Company
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR. Al-Taiyyar ,PROJECT MANAGER,DTA,SEC-WOA,JEDDAH
ENGR. Abdul mohsin otaibi, PROJECT ENGINEER,DTA,SEC-WOA,JEDDAH

URGENT

SUBJECT: Site Mobilization, Mix Design, Approved Drawings, Saudi


Security guards.

GENTLEMEN,

It has been observed that the site mobilization still not completed. Still there is no any facility for telephone,
fax and internet on site. There are no approved drawings available on site and ABB staff is not as per
organization chart on site and also there are no Saudi security guards at site for security. It is directed to
submit the revised baseline schedule and three week time schedule at site and approved Mix design for
concrete to expedite the work at site without any delay to the project.

This is for your immediate attention and further necessary action.

REGARDS,

SEC/SATECH
Contractor: ABB CO.
Prepared By: Issued By:
Name: EDGAR RIVERA Bidri Mohammed Akhtar
Job title: CIVIL ENGINEER CIVIL ENGINEER
Signature:
SITE INSTRUCTION NO. C-005 DATE : 06/07/2011 G

SITE INSTRUCTIONS

Contract No. 21031044/00


Project Title : NEW Salamah-2 110/13.8 KV S/s Jeddah
Contractor Name ABB contracting Company
Attention: Engr. Roshan Ali PROJECT MANAGER, ABB contracting Company
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR. Al-Tayyar ,PROJECT MANAGER,DTA,SEC-WOA,JEDDAH
ENGR. Naeem qurashi,PROJECT ENGINEER,DTA,SEC-WOA,JEDDAH

URGENT

SUBJECT: Temporary Site facility

GENTLEMEN,

It has been observed that the site mobilization still not completed. Still there is no any facility for telephone,
fax and internet on site. So arrange alternate by internet USB, Mobile and scanner for the site co-ordination
with SEC and complete the balance mobilization immediately. There are no Saudi security guards at site for
security. It is directed to submit the revised baseline schedule and three week time schedule at site and
approved Drawings and Mix design for concrete to expedite the work at site without any delay to the
project.

This is for your immediate attention and further necessary action.

REGARD,

SEC/SATECH
Contractor: ABB CO.
Prepared By: Issued By:
Name: EDGAR RIVERA Bidri Mohd Akhtar
Job title: CIVIL ENGINEER SITE CIVIL ENGINEER
Signature:
SITE INSTRUCTION NO. C-006 DATE : 09/07/2011 G

SITE INSTRUCTIONS

Contract No. 21031044/00


Project Title : NEW Salamah-2 110/13.8 KV S/s Jeddah
Contractor Name ABB contracting Company
Attention: Engr. Roshan Ali PROJECT MANAGER, ABB contracting Company
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR. Al-Tayyar ,PROJECT MANAGER,DTA,SEC-WOA,JEDDAH
ENGR. Naeem qurashi,PROJECT ENGINEER,DTA,SEC-WOA,JEDDAH

URGENT

SUBJECT: Without information of activity at site

GENTLEMEN,

It has been observed that the sub contractor site civil Engineer is start excavation for earthing without
approved drawing, level of raft etc and without permission of ABB civil Engineer and the site civil consultant
Engineer also it is not accepted and SEC giving first warning if any one violating the instruction then he will
send out from site.

This is for your immediate attention and further necessary action.

REGARD,

SEC/SATECH
Contractor: ABB CO.
Prepared By: Issued By:
Name: EDGAR RIVERA Bidri Mohd Akhtar
Job title: CIVIL ENGINEER SITE CIVIL ENGINEER
Signature:
SITE INSTRUCTION NO. C-007 DATE : 09/07/2011 G

SITE INSTRUCTIONS

Contract No. 21031044/00


Project Title : NEW Salamah-2 110/13.8 KV S/s Jeddah
Contractor Name ABB Contracting Company
Attention: Engr. Roshan Ali PROJECT MANAGER, ABB contracting Company
ENGR.TAREQ.S.MIRZA,DIVISIONAL,MANAGER,DTA,SEC-WOA,JEDDAH
CC: ENGR. Mohd Al-Tayyar,PROJECT MANAGER,DTA,SEC-WOA,JEDDAH
ENGR. Naeem qurashi,PROJECT ENGINEER,DTA,SEC-WOA,JEDDAH

URGENT

SUBJECT: Non approved staff

GENTLEMEN,

It has been observed that the civil Engineer and safety officer are not approved from Sec so leave the site
and please bring the approval of SEC then only you can enter the site. These are the following names of ABB
non approved staff.
1.Edgar rivera (site civil engineer)
2.Syed masroor ali (safety officer)

This is for your immediate attention and further necessary action.

REGARD,

SEC/SATECH
Contractor: ABB CO.
Prepared By: Issued By:
Name: EDGAR RIVERA Bidri Mohd Akhtar
Job title: CIVIL ENGINEER SITE CIVIL ENGINEER
Signature:

Вам также может понравиться