Вы находитесь на странице: 1из 6

B.10.4 8th International Conference on Insulated Power Cables B.10.

EVOLUTION IN METHOD AND PERFORMANCE FOR BONDING THE


METAL SCREEN OF UG HV POWER CABLE
David DUBOIS (1), Pierre MIREBEAU (1), Pascal STREIT (1), Didier LIEMANS (1), Mohamed MAMMERI (2),
Franck MICHON(3), Minh NGUYEN TUAN (4), Aude BARRALON(5)
1 – Nexans, david.dubois@nexans.com, pierre.mirebeau@nexans.com, pascal.streit@nexans.com
didier.liemans@nexans.com
2 – Sileccable mohamed.mammeri@sileccable.com
3 – Prysmian franck.michon@prysmian.com
4 – EDF minh-2.nguyen-tuan@edf.fr
5 – RTE aude.barralon@rte-france.com

ABSTRACT In fact the limitation on maximum sheath standing


voltages put a brake to an increase of the unitary shipping
The paper presents the economical reasons for length. Some countries were limiting the maximum
expanding the cable shipping length, the different standing to values as low as 65V. Some are still. The
technical obstacles that have to be overcome and the
resulting evolution of the performances required by the graph in Fig.1 shows that keeping such limit prevents any
increase in potential stresses applied to the secondary kind of change in the maximum allowed distance between
insulation. joints. However the demand for UG transmission line
tends toward larger transmission capacity then the
Different novelties in bonding diagram such as “direct problem of standing voltages has become more and more
cross bonding” are explained, highlighting their benefit as penalising.
well as their prerequisites and drawbacks.
In France the maximum allowed standing voltage for line
The use of longer shipping lengths as well as of “direct where public access is prohibited is 400V. That particular
cross-bonding” method supposes that an accurate and feature of the French regulation makes possible the
thorough study of the electrical stress applied to joint extension of shipping lengths up to 2000m and more.
shield break is carried out as part of the basic design of
the link.
New concept of the electrical components around the
cable joint is presented and its benefits on classic design
are explained.

PRESENT AND FUTURE


Economy is leading the world. For many years the
standard shipping length for UG HV and EHV cable was
in the range of 500m, sometimes less.
This value was due to different limitations such as:
• Production equipment like impregnating tanks, take-
up units, etc.
• Testing equipment like maximum current of test
transformers or maximal capacitance of the test
object
• Transport in term of drum size and weight
• Last but not least regulation restriction on the
maximum standing voltages along the metal
sheath/screen. Fig.1 induced voltage versus the ratio of cable spacing
over metal screen diameter
By having longer lengths per shipping drum the hardware
cost, the labour cost and the civil work cost are reduced. When the obstacle of maximum standing voltage is
Costs of maintenance are also linked to the number of removed there is still to address the problem of induced
accessories along a UG power line. voltage under short-circuit condition.
• Civil work cost Combining longer lengths and short-circuit current that
It is including the cost of joint bays and associated pits can reach 63kA and even more makes necessary to take
that house the cross-bonding boxes. care of the rating of the SVL that are protecting the screen
• Labour cost interruption of joints.
Mounting joint can represent 25 percent of the total Another direction to reduce the cost of UG cable power
installation cost. line is to decrease the amount of protections put on the
• Hardware cost different joints along the route, irrespective of the section
Hardware encompasses the joints with their possible length between them. This second track has been called
monitoring system as well as the bonding leads and “direct cross-bonding”. .
cabinets with or without SVL’s.

Jicable’11 – 19 – 23 June 2011, Versailles - France


B.10.4 8th International Conference on Insulated Power Cables B.10.4

Both directions towards more economical UG power lines Evolution of the Cross-bonding design in
have the following prerequisites: France
• A very good and reliable knowledge of the network Sectionalised cross-bonding is used [3]. Cables are
(overhead lines and their design, resistance of earth transposed to limit induced voltages in neighbouring
grids, short-circuit current and duration, etc…), networks. The screen interruptions are protected by surge
• Data on impact of thunder lightnings and their effects arresters connected to the shield break joints through
(magnitude, frequency, seasonal and local variation) . coaxial bonding leads, maximum 10 m in length. These
arresters are star connected, and the neutral point is
CROSS-BONDING DESIGNS grounded. They are located in a manhole, designed to
contain the effect of an internal arcing.
Generalities Up to now, the nominal voltage was limited to 6 kV.
In order to increase shipping lengths, a study has been
Cross bonding consists essentially in sectionalizing the lead.
cable sheaths along the route into elementary sections The results confirm:
and cross connecting them so as to approximately - The possibility to use a 12 kV arrester instead of the
neutralize the total induced voltage in three consecutive 6 kV ;
sections. - The need to test equipments according to the withstand
Lightning strokes cause the propagation of surge waves in levels specified in the French standard C-33-254 [4]
underground links they are connected with. given in Table 1.
The magnitude of the overvoltages that stress the screen For impulse levels, international recommendations from
interruptions at cross-bonding locations decreases with CIGRE and IEC are given in brackets, if they are different.
the distance to the end. In addition, a.c. withstand levels are also required, and
As a consequence, the overvoltages in the middle a.c. tests are carried out as type tests
sections are likely to be lower than the withstand level of .
the screen interruption in shield break joints [1] [2] even if
not protected by SVL.

Nominal voltage of the link (kV) 36/63 (72,5) 52/90 (100) 130/225 (245) 230/400 (420)
Lightning impulse voltage for main insulation (kVc) 325 450 1050 1425
Screen to ground impulse withstand level (kVc) 50 (30) 50 (37,5) 50 (47,5) 62,5
Impulse withstand level for screen interruption (kVc) 80 (60) 80 (75) 100 (95) 125
Screen to ground a.c. withstand level (kV) (15min.) 20 20 20 20

a.c. withstand level for screen interruption (kV 15min.) 25 25 25 35

Table 1 : Withstand levels specified in French standard C-33-254

Direct cross-bonding INSULATION COORDINATION STUDIES


In the case of the so called “direct cross bonding”, the To compare the overvoltages likely to occur in the grid
reliability of the system is totally dependent on the with the withstand level of shield break joints; studies
integrity of the insulating shield interruption. The dielectric were carried out, using EMTP-RV software. Main features
strengths, and the ac, impulse, and switching surge and results are presented below.
withstand levels of the interruptions have to be
established and coordinated with the calculated Description of the configuration
magnitudes of ac and transient voltages for the circuit. A single-circuit siphon is considered (see Fig.2).

Span length = 400m

Network

Overhead Overhead
Line Line

Fig. 2: studied configuration

Jicable’11 – 19 – 23 June 2011, Versailles - France


B.10.4 8th International Conference on Insulated Power Cables B.10.4

The overhead line is protected by 2 sky wires with a D.C. Connections between the overhead line and the
resistance 0.24Ω/km. The towers height is 20m, the underground cable
grounding impedance is 10Ω. The withstand voltage of They were represented as lumped inductances (1 μH/m).
their insulator strings is 900kV for 225kV grid.
1600mm² Cu XLPE cables are laid in ducts in trefoil Surge arresters
formation (0.2m spacing) Surge arresters were modelled as a non-linear element
The soil resistivity is 100Ω.m. with U(I) 8/20μs characteristic of the arresters. An
The main insulation of the cable is protected by surge inductance added to the connection account for the
arresters installed at both terminals, connected by a 3m change of characteristic when steeper fronts are
long lead to the grounding electrode of the first tower. considered.
The screen interruptions are protected by 12kV surge
arresters. Surge arrester leads
Lumped inductances were used.
Modelling
The modelling follows IEC 60071.4 [5] recommendations. Lightning stroke
The CIGRE Concave [8] model was used.
Representation of the sections of the underground cable
The sections of the underground cable were represented Results
using the FDQ model [6] [7]. The upper curves show the phase to remote earth voltage
at cross-bonding locations and the lower curves display
Overhead line the voltage stressing the screen interruptions.
Spans in the vicinity of the siphon were represented using
In the first case, SVL are installed only at the 2 ending
the FDLINE model. Corona effect has not been taken into
major sections; in the second case, SVL are installed
account. Spans far from the siphon have been
within the 3 sections. The magnitude of the overvoltages
represented by single long line avoiding unrealistic
is roughly the same.
reflections.
The sheath overvoltages within the second major section
Towers were represented as loss-less lines. The
exceed 62.5kV only for lightning strokes with high
characteristic impedance is 150Ω; the wave velocity has
magnitude. One has to keep in mind that the computed
been taken equal to the velocity of light in vacuum.
overvoltages refer to the remote earth, so that
The grounding electrodes of the towers were represented
overvoltages applied to the sheath are significantly lower.
as a constant resistance, except for those just before the
The screen interruption overvoltages are lower than
underground cable, which has been represented taking
100kV, with or without surge arresters.
into account soil ionisation [2].
Results of same study for 225kV lines were published in
Air gap CIGRE Technical Brochure 283 [2]
They were represented as an ideal switch closing when
the voltage between its terminals reaches the withstand It is worthy to remind that the median lightning current
voltage of the air gap. magnitude is about 30 kA and the probability of a current
higher than is 150 kA is about 0.05 %.

Fig 3: Study for a 400kV siphon – 3 major sections.

Jicable’11 – 19 – 23 June 2011, Versailles - France


B.10.4 8th International Conference on Insulated Power Cables B.10.4

POWER FREQUENCY ISSUES through the earthings do not lead to excessive


overvoltages at the cross-bonding points of cross-
Basic features bonded links.
For trefoil cables, the voltage of each screen to earth • In 225 and 400kV links between two substations, EPR
during a 3-phase symmetrical fault (external to the cables) are not excessive provided that earth resistances in
is given by the well-known formula Electra 28 [9] or 128 the substations are low and similar (typically less than
[10]: 4Ω).

ω.μ  2.S  • In 225 and 400kV systems involving an underground


E= .Ln .L.I link connected to a substation and an overhead line, or
2.π  d  a siphon, excessive overvoltages are likely to occur at
the faulted underground link to overhead line
where ω is the circular frequency, μ is the magnetic transition, if the fault current is close to the nominal
permeability of vacuum, d is the screen mean diameter, S value.
is the spacing between cables, L is the length of minor
sections and I is the short-circuit current. In this latter case, the installation of an earth continuity
conductor is an efficient solution to limit overvoltages that
Voltages between screens which stress joints screen can appear on sheath SVL.
interruptions are equal and are given by √3 times the
voltage of each screen to earth E. However, in 400kV links, EPR at underground link to
overhead line transitions lead to overvoltages on cable
In case of phase to phase fault, the theoretical maximum oversheath and joint covering exceeding their rating, if the
voltage between screens is 2 times E [9], but, in practical fault current flowing through the overhead line is higher
situations screen currents flow in the screens and reduce than about 30kA. It is then possible to limit the metal
the screen voltages below this level [10]. sheath potential rises by reducing significantly the length
of minor sections.
During a single phase earth fault, external to cables,
screen to earth voltages depend strongly on the earthing The above conclusions do not apply to underground links
resistances at the ends of the circuit which determine the connected to an overhead line without skywire. In such a
return current path, but voltages between screens may be configuration, excessive overvoltages may occur even if
easily derived since the return current through the screens earth resistances are low.
divides between the 3 screens in parallel. In that case the
maximum voltage is simply E. NOVELTIES IN BONDING DIAGRAM
Electra 128 states that, in case of single phase to earth
Cross-bonding design is usually made by concentric
fault, internal to cables, the maximum voltages between
bonding leads with each conductor connected to each
screens do not exceed those due to external fault.
cable screen in screen interruption HV joints and
This is more or less in line with the CIGRE Brochure 347 connected to a cross-bonding link box.
[11] which states that the maximum voltage may be larger
The link boxes can be either installed underground
than the voltage occurring in three -phase faults if:
(directly buried or inside a dedicated manhole) or on a
• The screen resistance is “high”. frame above the ground (which is not recommended).
• The fault is fed mainly by one side. Each of these link boxes is equipped with surge arresters
which are here to limit over voltage either on outer sheath
• The magnitudes of the 3-phase and the phase to earth or on joint screen interruption.
short-circuit currents are similar.
So, for design purpose, the highest power frequency
voltage between screens can generally be taken as √3.E.

Earth Potential Rises


As already mentioned, the calculation of the screen to
earth voltages which stress joints coverings and SVL is
easy only in case of 3-phase faults.
Electra 128 and CIGRE Brochure 347 point out some
configurations where earth potential rises may lead to
excessive screen to earth voltage with respect to the
withstand level of SVL if they are star connected with the
star point earthed.
Power-frequency over-voltages likely to occur during
single-phase to earth faults in the French HV and EHV
networks were determined with the Complex Impedance
Matrices method, as presented in CIGRE Brochure 347.
Fig. 4. Standard cross-bonding connection with concentric
The following conclusions were drawn: bonding leads
• In 63 and 90 kV links, as the single-phase short-circuit
current is smaller than the three-phase short-circuit
current, EPR caused by the fault current flowing
4

Jicable’11 – 19 – 23 June 2011, Versailles - France


B.10.4 8th International Conference on Insulated Power Cables B.10.4

Advantages: • Fault localization is more difficult as a test made on


outer sheath integrity change from one phase to
• Short lengths of cable outer sheath can be tested another phase at each shield break joint.
separately (between each shield break joint)
• Easy fault localization (by screen disconnection inside To avoid this drawback the following departures are
link boxes) applied
Disadvantages: • For very long links, in order to divide the link in shorter
segments some earthed joints with screen interruption
• Requires SVL maintenance have to be used. The 6 single-core bonding leads
• Above ground link boxes can be easily damaged (concentric cables can be used as well) are connected
• Risks in case of link box internal arcing to earth via an earthing box.

As described in the previous section this design needs to


remain on first major section on each end of long
underground cable links.
But studies have shown that such cross link boxes can be
avoided between the 2 extreme major sections by doing a
so called "direct cross-bonding".
This design consists to use single core bonding leads to
make joint screen cross-bonding directly from one joint to
the others inside the joint-bay.

Fig. 6 Bonding to earth through earthing box using


concentric leads with possible disconnection
Practical experience with direct cross bonding has been
achieved on 2000mm² Alu XLPE 150kV links as shown in
Fig. 5 Direct cross-bonding connections figure 7. The shield break joint has been successfully
tested according IEC 60 840 tests of outer protection
One positive feature of the standard cross-bonding (Annex H) where the sheath sectionalizing insulation has
system is that owing the different link boxes it is easy to been submitted to 150kVp impulses level instead to
locate sheath fault. A fully direct cross-bonding system 75kVp.
would not provide easy fault location because:
• Outer sheath tests cannot be segmented.

Fig 7. Earthing System using Direct Cross Bonding

Jicable’11 – 19 – 23 June 2011, Versailles - France


B.10.4 8th International Conference on Insulated Power Cables B.10.4

NEW CONCEPT FOR ACCESSORIES


The use of the direct cross-bonding system makes
necessary new types of accessory as shown on the
following schematic diagram

Shield Shield Shield Shield Shield Shield


Earthing break Earthing break break
break break break
joint joint joint
joint joint joint joint joint

Cross bonding
Cross bonding

cabinet
cabinet

Earthing Earthing
cabinet cabinet

Cross bonding
cabinet

Unit section repeated N times

Fig. .8. Schematic diagram of a UG power cable line featuring some direct cross-bonding sections [12]

Sections between A to D and G to J are with a standard GLOSSARY


cross-bonding system. Sections between D and G use the UG: Underground
direct cross-bonding system. Three different types of HV-EHV: High Voltage, Extra High Voltage
joints and their associated hardware are represented: SVL: Surge Voltage Limiter or surge arrester.
• Joints with direct connection to earth EPR: Earth Potential Rise
• Joints with cross-bonding connections : the screen
interruption is protected with SVL’s REFERENCES
• Joints with direct cross-bonding connections : the [1] A.Gille et al “Double 150 kV link, 32km long, in
screen interruption is not protected against Belgium : design and construction” - 2004 – CIGRE
overvoltages. report B1-305
Different technological solutions can be applied to
address the functional requirements listed above. Three [2] CIGRE Technical Brochure 283 Special Bonding of
different specifications for bonding leads are identified: High Voltage Cable Oct. 2005
• Single core bonding lead directly connected to earth [3] CIGRE 2000 Dorison et al - 400 kV underground links
• Single core bonding lead to connect two joints for bulk power transmission. New developments in
• Coaxial bonding lead for classic cross-bonding the field of XLPE insulated cables
connection between joint and cross-bonding box. [4] French standard NFC 33.254 Insulated cables and
These three types have a different technical specification their accessories for power systems
based on their functional requirements. [5] IEC 60071.4 – “Computational Guide to Insulation
In principle they have to feature the same performances Co-ordination and Modelling of Electrical Networks”
as the different components which they are bonded to. 2004
[6] EMTP-RV online documentation
CONCLUSION
[7] Hermann Dommel – EMTP Theory Book
To achieve more economical long HV UG lines on the [8] CIGRE 63 brochure – Guide to procedures for
French network the design rules have been studied to estimating the lightning performance of transmission
cover longer cable length between accessories and less lines
protection hardware for the screen interruptions.
Meanwhile the performances of the material has been [9] The design of specially bonded cable systems
improved and so the tests to check them. Namely a.c. against sheath overvoltages – Electra 28 – 1973
voltage is now part of the test program. [10] Guide to the protection of specially bonded cable
systems against sheath overvoltage – Electra 128–
To verify that the incurred increase of potential stresses 1990
on the joints remains acceptable thorough studies of the
induced voltages under surges conditions were [11] CIGRE Technical Brochure 347 Earth Potential Rises
necessary. in specially bonded systems - June 2008
[12] French dispositions for bonding the metal screen of
RTE is currently studying their optimisation to the French UG HV power cable – RST part 7 – October 2010
power transmission system.

Jicable’11 – 19 – 23 June 2011, Versailles - France

Вам также может понравиться