Вы находитесь на странице: 1из 6

EPSP 078 1

Capacitor Placement in a Distribution


System for Power Factor Correction:
An Optimization Approach
S.Neelima#1, Dr. P.S.Subramanyam*2, Prof. A. Srinivasula Reddy#3

 drawback of this problem is increase in the network losses and


Abstract— The industrial power distribution networks of the AP reduction in the voltage level. Low voltage profile leads to
Discom would have inductive loads at low power factor. These malfunctioning or reduction in the lifetime of electric devices
distribution networks experience increase in power losses and increases the internal losses of cables and motors; hence
especially during the peak summer period. Low power factor is decreases the efficiency. Shunt capacitors have been
most commonly corrected by connecting shunt VAR commonly used to provide reactive power compensation in
compensation such as shunt capacitors bank at the desired
power distribution network. They are provided to minimize
location to perform the power factor correction. The power
factor correction using shunt capacitors bank produce economic power and energy losses, maintain best voltage regulations for
saving in capital expenditures through the reduction of power load buses and improve power network security. The amount
losses through the distribution network. This paper presents a of compensation provided is very much linked to the
practical case study of power factor correction for an 11 kV placement of capacitors in the distribution network which is
industrial distribution network in the AP Discom. The network essentially determination of the location, size, number and
model has been developed using EDSA professional power type of capacitors to be placed in the system [1]. A large
system software. The energy after adding the shunt capacitors variety of research work has been done on capacitor placement
(i.e. after power factor correction) has been determined from the problem in the past [2],[3], and [7].
power flow solutions. The on-site measurements have been
conducted and the measurements have been verified by the
network model that is developed by EDSA software. The main objective of this study is to design an energy saving
. scheme for an industrial distribution network in A.P.. This can
be achieved by decreasing the network losses and improving
Keywords: VAR compensation - Placement of Capacitor – Power the main electric load operation to a better efficiency level.
factor correction - Distribution system - EDSA The designed scheme is concerned with improving the power
software. factor of the distribution network by adding shunt capacitors
to the network at optimal size and location. Load flow
I. INTRODUCTION modeling is used to simplify the network and to calculate the
Industrial power distribution networks experience increase network losses and the voltage profile. The network model
in power losses during summer period [1],[4]. This is mainly parameters are collected through field measurements and then
related to the excessive use of air conditioning system and implemented in Electrical Distribution Software Analysis
motor drives which reflects an increase in the electric load. (EDSA) program 6. After that, the EDSA modeling is
Such increase in this type of load is accompanied with low validated by comparing load flow results with power flow
power factor (~ 78%) which leads to huge transfer of reactive field measurements. The size of the capacitor (VAR
power from the utility through the network. The main compensation) is determined and is verified using EDSA
software. The designed VAR compensation system will
reduce the overall network losses. The field measurements,
software analysis, designed VAR compensation system, and
overall energy saving are presented in this paper.

II BENEFITS OF POWER FACTOR CORRECTION

Loads on electric power networks include two components:


active power (measured in kilowatts) and reactive power
S. Neelima is with the Department of EEE, Vignana Bharathi Institute of (measured in kilovars). Active power has to be provided by
Technology, Aushapur, Ghatkesar Mandal, R.R. Dist. A.P., India, Phone: +91 power plants, whereas reactive power can be provided by
-94409-23151; (e-mail: neelimarakesh@ gmail.com). either power plants or shunt var compensation such as shunt
Dr.P.S. Subramanyam, is with the Department of EEE, Vignana Bharathi
Institute of Technology, Aushapur, Ghatkesar Mandal, R.R. Dist. A.P., India,
capacitors bank. It is a well-known fact that shunt power
(e-mail: subramanyamps@gmail.com). capacitors are the most economical source to meet the reactive
Prof. A. Srinivasula Reddy is with the Department of EEE, Vignana power requirements of inductive loads and transmission lines
Bharathi Institute of Technology, Aushapur, Ghatkesar Mandal, R.R. Dist. operating at a lagging power factor.
A.P., India, (e-mail: svas_a@rediffmail.com).
EPSP 078 2

Economic Justification for Capacitors Benefits due to Reduced Energy Losses


The annual energy losses are reduced as a result of
When reactive power is provided only by power plants, each decreasing copper losses due to the installation of capacitors 4.
system components (i.e., generators, transformers, The conserved energy can be expressed as given in Eq. (2).
transmission lines and distribution feeders, switch-gear, and
protective equipments) has to be increased in size accordingly. QC ,3  R(2S L ,3 sin   QC ,3 )  8760 kWh/yr (2)
Capacitors can mitigate these conditions by decreasing the ACE 
1000 VL L
2

reactive power demand all the way back to the generators 4.


Where:
Line currents are reduced from capacitors locations all the way
ΔACE = annual conserved energy, kWh/yr
back to the generation equipment. As a result, losses and
loadings are reduced in distributions feeders, substation QC ,3 = three-phase reactive power due to corrective
transformers, and transmission lines. Depending upon the capacitors applied, kvar
uncorrected power factor of the system, the installation of R = total resistance to load center,
shunt capacitors can increase generator and substation S L,3 = original, i.e., uncorrected three phase load, kVA
capability of additional load at least 30 percent, and can
increase individual circuit capability, from the voltage sin θ = sine of original (uncorrected) power factor angle
regulation point of view, approximately 30 to 100 percent. V = line to lien voltage, kV
L-L
Furthermore, the current reduction in transformer and
distribution equipment and lines reduces the load on these The annual benefits due to the conserved energy can
kilovolt ampere-limited apparatus. In general, the economic be calculated as given in Eq. (3).
benefits force capacitor banks to be installed on the primary
distribution network rather than on the secondary. The $ ACE  ACE  EC
methods used by the utilities to determine the economic (3)
benefits derived from the installation of capacitors vary from
company to company, but the determination of the total Where:
installed cost of a kilovar of shunt capacitors is easy and Δ$ACE = annual benefits due to conserved energy, $/yr
straightforward. In general, the economic benefits that can be EC = cost of energy, $/kWh
derived from capacitor installation can be summarized as 1, 4:
▪ Benefits due to released generation capacity Benefits due to Reduced Voltage Drops
▪ Benefits due to released transmission capacity
The following benefits can be derived from the
▪ Benefits due to released distribution substation capacity
installation of capacitors from into a circuit:
▪ Benefits due to reduced voltage drops (voltage
improvement)
▪ The effective line current is reduced, and consequently
both IR and IXL voltage drops are decreased, which
▪ Benefits due to released feeder capacity results in improved voltage regulation.
▪ Benefits due to reduced energy losses ▪ The power factor improvement further decreases the
Therefore the total benefits due to installation of capacitor
effect of reactive line voltage drop.
banks can be summarized 4 as given in Eq.II. (1).
ENERGY
REDUCTION The approximate value of the percent voltage rise along
the line can be calculated as given in equation (4):
 $  $ G $ T  $ S  $ F  $ ACE  $ GBCE (1 Q l (4)
%VR  C ,3
) 10  VL2 L

I. DEM Revenue
AND Increase
Also, an additional voltage rise phenomenon through
Reductio
every transformer from the generation source to the capacitors
n occurs due to the application of capacitors, which is
independent of load and power factor of line, and can be
Where: expressed as:
Δ$G = annual benefits due to released generation capacity, $/yr
Δ$S = annual benefits due to distribution substation capacity,  Q l 
$/yr %VRT   C ,3  xT (5)
 S 
Δ$F = annual benefits due to released feeder capacity, $/yr  T ,3 
Δ$ACE = annual benefits due to conserved energy, $/yr
Δ$GBCE = additional annual revenue due to increase kWh Where:
energy consumption, $/yr % VRT = percent voltage rise through transformer
Δ$T = annual benefits due to released transmission capacity, ST ,3 = total three-phase transformer rating, kVA
$/yr
xT = percent transformer reactance (approximately equal to
transformer’s impedance)
In our work, we will discuss the benefits of the
installation of shunt capacitors from the perspective of
reduced energy losses and reduced voltage drops.
EPSP 078 3

III. PRACTICAL CASE STUDY: POWER FACTOR IMPROVEMENT transformers that feed the industrial customers through 12 kV
FOR AN INDUSTRIAL 11 KV SUBSTATION feeders. The single-line diagram of the substation is shown in
Figure 1. Here, the bus1, which is supplied by utility grid, is
The power factor correction using shunt capacitors treated as generation bus for making further calculations and
have been applied to an existing 11 kV substation. This simulations easier and convenient.
substation is a part of power distribution network of A.P.
power system. The 11 kV substations have two 66 kV/33 kV

Figure 1 Single-Line Diagram of 11 kV substations

00.9
.922

00.9
.900

00.8
.888

00.8
.866

00.8
.844

00.8
.822

00.8
.800

00.7
.788

00.7
.766

00.7
.744

44/7
/7/2
/2000077 2
233:5
:59
9:0
:00
0 (H:M
(H:M:S)
:S) 4 /8 /2 0 0 7
11:5
:500:0
:000.0
.00000 PM
PM 44 Hours
Hours/Div
/Div 1 :4 9 :0 0 .0 0 0 PM

Figure 2(a). Time trends of power factor over 24 hours (summer condition)

00.9
.955

00.9
.900

00.8
.855

00.8
.800

00.7
.755

11/3
/311/2
/2000088 2
233:5
:58
8:4
:40
0 ((H:M
H:M:S)
:S) 2 /1 /2 0 0 8
33:2
:211:0
:000.0
.00000 PM
PM 44 Hours
Hours/Div
/Div 3 :1 9 :4 0 .0 0 0 PM

Figure 2(b). Time trends of power factor over 24 hours (winter condition)

.
EPSP 078 4

The case study consists of three steps: Computer Simulations


EDSA power flow program 6 has been used to
▪ Measurements using power quality analyzer calculate the total network power losses. Power flow
(AMEC 3945 PQ Analyzer)) solution has been obtained using Newton-Raphson method.
▪ Computer simulation using professional power The power flow with shunt capacitors is shown in Figure 4.
system analysis software (EDSA software). From Figure 4, it can be observed that the power factor has
▪ Calculation of Energy Saving been improved to 0.9478. The kvar rating of the shunt
capacitors have been determined to improve the power
Measurements factor at each feeder to 95% lagging. The calculated kVar
The power quality analyzer has been used to of each shunt capacitor is shown in Figure 4.
measure all the values that needed to simulate the network
for power factor correction using EDSA software. The PQ Simulation without adding shunt capacitors
analyzer has been left on the substation for 24hrs recording. EDSA power flow program has been used to
The recorded 24hrs power factor at the secondary 11kV calculate the total network power losses. Power flow
secondary side of the transformer is shown in Figure 2(a) solution has been obtained using Newton-Raphson method.
and 2(b). The measurements of MW and MVar loads The solution of the power flow without shunt capacitors is
connected to the 11 kV feeders are shown in Figure 1. shown in Figure 3. From Figure 3, it can be observed that
the power factor of the network at bus 2 is 0.79. The value
From Figures 2(a) and 2(b), it can be seen that of 0.79 power factor is a poor power factor and the target is
power factor of the substation is considered a poor power to improve it to 0.95.
factor (0.75 to 0.87). The objective of this study is to
improve the power factor to 0.95 to minimize the power The summary of power flow results without shunt
losses (saving energy) and to reduce the voltage drops capacitors are given in Table 1.
(improve voltage profile). The selection of the shunt
capacitors for power factor improvement is determined and
it is verified by the EDSA software simulations.

Figure 3. Power flow solution without shunt capacitors


EPSP 078 5

Table 2 Summary of Total Generation and Demand


Table 1 Summary of Total Generation and Demand With Shunt Capacitors
Without shunt capacitors P(MW) Q(MVAR) S(MVA) PF(%)
P(MW) Q(MVAR) S(MVA) PF(%) Swing
Swing Buses 10.977 8.986 14.186 77.38 10.965 4.034 11.683 93.85
Buses
Generators 0 0 0 0 Generators 0 0 0 0
Shunt 0 0 0 0 Shunt 0 4.792 4.792 0
Static Load 10.95 8.468 13.842 79.1 Static Load 10.95 8.468 13.842 79.1
Motor Load 0 0 0 0 Motor Load 0 0 0 0
Total Loss 0.036 0.526 Total Loss 0.024 0.356
Mismatch -0.009 -0.008 Mismatch -0.009 0.001

From Table 1, the total power losses in the network are From Table 2, the total power losses in the network are
0.036MW (36kW). 0.036MW (36kW). The losses decreases from 0.036 MW
(36kW) to 0.024 MW (24kW)
Simulation with adding the shunt capacitors
EDSA power flow program has been used to Energy Saving Due Power Factor Improvement
calculate the total network power losses. Power flow The total reduction in the power losses is
solution has been obtained using Newton-Raphson method. calculated as:
The power flow with shunt capacitors is shown in Figure 4.
From Figure 4, it can be observed that the power factor has ΔPloss = Ploss, before cap – Ploss, after cap
been improved to 0.9478.
Ploss= 0.036- 0.024= 0.012 MW= 12kW∆

Figure 4 Power flow solution with adding shunt capacitors


EPSP 078 6

Table 3 Energy Saving


Period Saved energy
One day 12*24=288 kWhr
One month 288*30= 8640 kWhr
One year 8640*12= 103680 kWhr

As shown in Table 3, adding shunt capacitors to the


industrial network will save around 103680 kWhr energy
every year. The cost of the shunt capacitors can be
recovered within few years.

IV CONCLUSIONS

This paper presented a power factor correction for an


existing industrial power distribution network in the AP
Discom. Shunt capacitors is used for power factor
correction. On-site measurements of the network loads and
power factor have been conducted using power quality
analyzer. A time trend of network power factor has also
been measured and recorded over 24 hours. The
measurement results show a power factor for all network
loads. EDSA power system analysis software has been used
to model the network and to determine the network power
losses. The determined location and rating of shunt
capacitors has reduced the energy losses in the network.
The shunt capacitors have been located at the end of each
11 kV feeder. The optimal location of shunt capacitors to
minimize the energy losses is one of the future studies.

REFERENCES

[1]. T.J Miller, Reactive Power Control in electric System,


New York, John Wiley & Sons Inc, 1982.
[2]. M.E. Barn, and F.F WU, “Optimal Capacitor
Placement on Radial Distribution System, IEEE
Transaction on Power Delivery, Vol. 4, pp. 725-734,
1989.
[3]. C.S. Chen, C.T. Shu and Y.H. Yan, “Optimal
Distribution Feeder Capacitor Placement Considering
Mutual Coupling Effect of Conductors, IEEE
Transactions on Power Delivery, Vol.10, pp. 987-
994., 1995,
[4]. T. Gonen, Electric Power Distribution System
Engineering, McGraw-Hill, 1986.
[5]. S. Al-Hinai, K.Ellithy, A. Al-Badi, A. Al-Nofli, and
S. Al-Hatmi, ”Determination of Optimal Rating and
Location of Sunt Var Compensation for SQU
Distribution Network”, Proceeding of GCC Cigré 13th
Annual Seminar, Muscat, Oman, pp. 205-212., Oct
2002.
[6]. EDSA power system analysis software,
www.edsa.com.
[7]. H. Moghbelli, and A. Sadrzadeh, “Application of
State Estimation Technique with Reduced Dimension
Model in a Power System in Presence of Harmonics,”
International Journal of Engineering Science, No. 4,
Vol. 11, 2000, Iran University of Science and
Technology.

Вам также может понравиться