Вы находитесь на странице: 1из 4

OUTSTANDING PEKERJAAN TANGKI

T-01 % PROGRESS OBSTACLES


11-Mar 12-Mar

90% 10 ea step grating not yet installed, wait the please allocate worker to fabricate
Stairway Installation action
scaffolding modification the step grating 3 ea

Walkway Modification 100% Finish 100% done per 7 march

Done per 1 March (minus blasting &


Outlet Modification 100% Finish Please allocate the worker to do this
Painting)
item, located in the inside of tank
Roof Nozzle Installation vent 2", 100 % done nozzle 2" 1 ea, 1 1/2" 2
90% Simops with coating activity fabricate vent 2"
level indicator dia 2", 1 1/2" 2 ea ea

Waiting the material from DAVIDI,


Level Indicator Installation 30% Waiting level indicator from DAVIDI they promise to deliver material in
13th march

Water Spray Installation 70% waiting blasting n painting Fabricate the circle waterspray 100% done circle line, install 2" line

There are several Nozzle that still use


Blind-off Nozzle 50% Waiting the worker finish the previous work temporary blind flange, please Allocate worker to do this action item
replace to the permanent.

Please allocate the worker to install


grounding rod and grounding pit.
Grounding Installation 30% Waiting bundwall preparation While the logistic team looking for grounding plate already installed
the clamp. Waiting bundwall
preparation

Support already installed, please


Name Plate Installation 50% Waiting fabrication of name plate from Jakarta speed up the nameplate fabrication
by Jakarta

Please dismantle than keep savely, to


Water Level Installation (for hydro) 100% be used for T-02

Blasting and Painting 80% On Going, finish plan at 13th March 100% done top coat

Labelling 0% On Going, finish plan at 13th March


OUTSTANDING PEKERJAAN TANGKI

PLAN ACTION
13-Mar 14-Mar 15-Mar 16-Mar

action action 100% done

100% done

100% done

Action, parralel with waiting data C


Material Onsite from Metrologi to inline the actual O
capacity
M
100% done 100% done I
S
S
I
O
N
Clamp must be onsite 100% done I
N
G
100% done

Handrail, stairway coating. 100%


done

100% done
OUTSTANDING PEKERJAAN TANGKI

T-02 % PROGRESS OBSTACLES


12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar
Roof Nozzle Installation Ø2", Ø1 0% Not Yet, waiting T-01 Finish
1/2", Ø1 1/2"

Shell Manhole Repair Ø24" 10% On Progress by Davidi

Shell Nozzle Repair, replace Flange 0% Not Yet, waiting T-01 Finish
8"

Level Indicator Installation by 0% Not Yet, waiting T-01 Finish


DAVIDI

Guess Neck Installation 6" 0% Not Yet, waiting T-01 Finish

Waterspray Installation 0% Not Yet, waiting T-01 Finish

Blind-off Nozzle 0% Not Yet, waiting T-01 Finish

Grounding Installation 0% Not Yet, waiting T-01 Finish

Name Plate Installation 50% Waiting Fabrication from Jakarta

Water Level Installation (f/ hydro) 0% Not Yet, waiting T-01 Finish

Blasting and Painting 0% Not Yet, waiting T-01 Finish

Labelling 0% Not Yet, waiting T-01 Finish


KI

PLAN ACTION
20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar

Вам также может понравиться