SE CONSIDERA:
A. REDIMENSIONAMIENTO
SE ASUME h= 0.35 m
ANCHO DE SARDINEL b= 0.25 m Entre 0.20 a 0.25m
H. DE LA VIGA BORDE hb = 0.20 m Entre 0.20 a 0.25m
2% 2%
0.20
0.05
0.35
7.00
B. DISEÑO DE LOSA
METRADO DE CARGAS
P.1/9
TEJCORP
* Camión HL-93
* Tandem
* S/C Equivalente
P.2/9
TEJCORP
0.97 Tn/m
L= 5.45 m
W= 0.10 Tn/m
0.10 Tn/m
L= 5.45 m
P.3/9
TEJCORP
L1 = 5450 mm
W1 = 6500 mm
W= 7000 mm
NL = 2
1. Un Carril Cargado:
E = 250+0.42(L1*W1)^1/2 ≤ W/NL
E= 2749.79 ≤ 3500 mm
E = 2100+0.12(L1*W1)^1/2 ≤ W/NL
E= 2814.23 ≤ 3500 mm
M LL+IM = m(Mmax*1.33+Ms/c)/E
M LL+IM = m(Mmax*1.33+Ms/c)/E
n = nD * nR * n1
n= 1.05
P.4/9
TEJCORP
Mu = 27.00 Tn-m
Mu = 15.68 Tn-m
DISEÑO
Mu = 15675.17 Kg.-m
d asumido = 31 cm.
31
35
P.5/9
TEJCORP
Mu = 27.00 Tn-m
As = 326.54 cm²
As = 24.79 cm²
ACERO DE REPARTICIÓN
ACERO DE TEMPERATURA
DISTRIBUCIÓN DE ACERO
ACERO PRINCIPAL
P.6/9
TEJCORP
ACERO DE REPARTICIÓN
ACERO DE TEMPERATURA
GRAFICA
1/2 20
Ø " @ cm. 5/8 30
Ø " @ cm.
1 20
Ø " @ cm.
P.7/9
TEJCORP
Metrado de cargas
Peso propio = 0.33 Tn/m
D. CALCULO DE ACERO
Area de acero para diseño por servicio 8.53 cm2
VD = 1.31 Tn
VL = 2.20 Tn
V I = 30 % de V L 0.66 Tn
P.8/9
TEJCORP
-259.3447465 6 -0.57
f de 3/8'' 1 @ 0.05 m 6 @ 0.10 m r @ 0.20 m
f de 3/4''
f de 3/4''
P.9/9
COMPROBACION DE MURO DE GRAVEDAD PARA ESTRIBO
Chequeo al Volteo:
4891.45 > 2.00 OK!
Chequeo de deslizamiento:
2198.28 > 1.50 OK!
Verificaciones de esfuerzos de traccion y compresion Esfuerzo a compresión del concreto Fc= 0,4(F´c)
Fc= 700000 Kg/m2
3554.88 < Fc OK!
Chequeo al Volteo:
3826.52 > 2.00 OK!
Chequeo de deslizamiento:
2131.13 > 1.75 OK!
Verificaciones de esfuerzos de traccion y compresion Esfuerzo a compresión del concreto Fc= 0,4(F´c)
Fc= 700000 Kg/m2
30.83 < Fc OK!
Chequeo al Volteo:
70.59 > 2.00 OK!
Chequeo de deslizamiento:
255.01 > 1.50 OK!