CIMIENTO DE MAMPOSTERÍA ESPECIFICACIONES

DATOS
qu = Esfuerzo de Diseño del terreno 20 Ton./m2
DE = Descarga Estructural Ton./ml FORMULAS
Em = Espesor del Muro (tabique rojo,etc) 14 cm.
C = Corona 0.29 M CIM. CENTRAL DE
Wp = Peso Volumétrico del Basalto 2.6 Ton./m3 DOS ESCARPIOS B 
RT
cimiento central
EJE TRAMO DE (Ton/M) Base (M) H (M) Vc (m3/m) Wc (Ton/m) DET (Ton/m) DET/ B(T/m2) RT (Ton/m2) B x H TIPO CORONA
BC
B 1-2 12.544 0.63 0.29 0.13 0.35 12.89 20.55 20 H * 1.73
1 2
0.90 0.53 0.31 0.82 13.36 14.84 0.90 0.60 C-1
2-3 4.25 0.21 -0.07 -0.02 -0.04 12.50 58.82 H BC
1.5 Vc  * H *1
0.60 0.27 0.12 0.31 12.85 21.42 0,60 0.60 C-1 2

W c  V C * 2 . 60
cimiento Lindero
EJE TRAMO DE (Ton/M) Base (M) H (M) Vc (m3/m) Wc (Ton/m) DET (Ton/m) DET/ B(T/m2) RT (Ton/m2) BXH TIPO V V D ET  W C  D E
A 1-2 3.04 0.15 -0.13 -0.03 -0.07 12.47 82.03 20
0.90 0.61 0.36 0.94 13.49 14.99 0.90 0.61 L-1
D ET
2-4 3.96 0.20
0.90
-0.09
0.61
-0.02
0.36
-0.06
0.94
12.49
13.49
63.07
14.99 0.90 0.61 L-1
BASE
RT 
B
CIM. LINDERO
UN ESCARPIO
cimiento central
EJE TRAMO CORONA
DE (Ton/M) Base (M) H (M) Vc (m3/m) Wc (Ton/m) DET (Ton/m) DET/ B(T/m2) RT (Ton/m2) B x H TIPO
2 D-B 3.05 0.15 -0.12 -0.03 -0.07 12.48 81.81 20 1
1.00 0.61 0.40 1.03 13.57 13.57 1.00 0.61 C-1
B-A 3.03 0.15 -0.12 -0.03 -0.07 12.48 82.34

H BC *1
1.00 0.61 0.40 1.03 13.57 13.57 1.00 0.61 C-1 1.5 H

cimiento Lindero
EJE TRAMO DE (Ton/M) Base (M) H (M) Vc (m3/m) Wc (Ton/m) DET (Ton/m) DET/ B(T/m2) RT (Ton/m2) B X H TIPO V
1 D-B 3.05 0.15 -0.13 -0.03 -0.07 12.47 81.77 20
1.00 0.71 0.46 1.19 13.73 13.73 1.00 0.71 L- 1 BASE
A-B 3.03 0.15 -0.13 -0.03 -0.07 12.47 82.31
1.00 0.71 0.46 1.19 13.73 13.73 1.00 0.71 L-1
CIMIENTO DE MAMPOSTERÍA
DATOS. ESPECIFICACIONES
qu = Esfuerzo de Diseño del terreno 3 Ton./m2
DE = Descarga Estructural Ton./m
Em = Espesor del Muro (tabique rojo, etc) 15 cm.
FORMULAS
C = Corona 0.3 M CIM. CENTRAL
DOS ESCARPIOS
Cimiento Central DE
CORONA B 
EJE TRAMO DE (ton/m) Base (M) Vc (m) H (M) B x H TIPO RT
B 1-2 3.64 1.21 0.46 0.69 1.20 0.69 C-1
2-3 4.25 1.42 0.56 0.84 1.20 0.84 C-2 1 BC
V 
2
H
1.5
H 1.5*V
Cimiento Lindero
EJE TRAMO DE (Ton/M) Base (M) Vc (m) H (M) B x H TIPO V
V
A 1-2 3.04 1.01 0.71 1.07 1.01 1.07 L-1
2-4 3.96 1.32 1.02 1.53 1.20 1.53 L-2
BASE

CIM. LINDERO
UN ESCARPIO
Cimiento Central CORONA DE
B 
EJE TRAMO DE (Ton/M) Base (M) Vc (m) H (M) B x H TIPO RT
2 B-A 3.63 1.21 0.46 0.68 1.20 0.68 C-1 1
D-B 4.51 1.50 0.60 0.90 1.20 0.90 C-3
H
V  B C
1.5
H 1.5*V
Cimiento Lindero
EJE TRAMO DE (Ton/M) Base (M) Vc (m) H (M) B x H TIPO V
1 B-A 3.03 1.01 0.71 1.07 1.01 1.07 L-1
BASE
D-B 3.05 1.02 0.72 1.08 1.02 1.08 L-1