Академический Документы
Профессиональный Документы
Культура Документы
Institute of technology
Nirma University
Tutorial V
CPM Network
Note: Prepare Table for All network.
1 Prepare table for EST, LST ,EFT, LFT and Float. Find out Critical path for following network.
2 The following activities are given for construction of beam. Arrange all activities in order, assign
time duration to each activity, prepare network and find out critical path.
Activities for a project of casting of R.C.C. Beam over the door opening, are given below in
random order. Arrange them in a proper sequence, using an appropriate logic, assign time
duration to each activity and draw the network, and show all activities in network.
Mix and produce concrete, design the beam, order for wooden forms, bending of reinforcement,
order concrete materials, set concrete mixer at site, curing stage 1, preparation of form, erection
of forms, order for steel reinforcement, strip off side forms, place and compact the concrete,
place the reinforcement, curing stage II, strip off the bottom form work, design concrete mix
proportion.
3 Draw Network for following data and find out critical path.
- A 3 K,C,I,A H 4
- I 5 E L 3
- C 4 L,O B 6
- N 6 B J 7
C E 4 L,O,D, F 3
H
C,I O 6 D,H G 2
C,I, D 7 G M 1
A
N K 8
4 Develop the network for the following data and Show critical path on it.
L A 4 C F 10 F K 6
F,H B 6 H G 6 ---- L 5
L C 7 A H 3 D,E M 4
K D 4 B I 6
I,J E 7 G J 7
5 Develop the network for following data and Show critical path on it.
- A 5
- B 4
- C 5
A D 3
A,B,C E 6
C F 4
D,E G 2
D,E H 3
D,E,F I 4
6 Develop a network on the A_O_A system for a job with following activities and logical
sequence. Prepare table for EST, LST, EFT, LFT, Float, Critical path. Duration of each activity is
given in bracket.
9. Draw a network diagram from the following list of relationships among the activities: