Академический Документы
Профессиональный Документы
Культура Документы
4 Piping:
The Contractor shall perform all the piping works required to complete the Works
including, but not limited to:
3.4.1 General:
385294050.doc Page 1 of 10
Updated: 25-Apr-18
10. Block out, cut, or core penetrations through existing floor, wall, or roof structures as
required including close-in, flash or band, paint, and installation of firestop
where indicated. Provide penetrations in concrete tanks not already shown on
the drawings to the satisfaction of the Engineer.
11. Field route, fabricate, paint, assemble, and install all equipment drain piping to the
nearest utility drain unless otherwise indicated on the Drawings.
12. Connect to piping and equipment installed by others in accordance with the Drawings
and Specification.
13. Clean, prepare, apply paint systems on uninsulated carbon steel pipe systems
including valves, piping specialty items, pipe hangers, pipe supports,
miscellaneous steel, nuts, bolts, washers, shims, weldments and other
supporting, fastening or connecting materials. Touch-up paint damage incurred
during handling and installation. The Contractor shall supply the paint system
and the touchup paint system in accordance with the Specification.
14. Complete all destructive and nondestructive testing.
15. Clean and flush all pipe lines and pipe systems in accordance with Drawings and
Specification and including specialized cleaning and flushing procedures such as
pipe-line pickling, acid washing; caustic washing, degreasing, and the like.
16. Cold set pipe supports and piping specialty items.
17. Supply installation materials such as:
(a) Weld rod and fusion rod;
(b) Thread lubricant and gasket compounds;
(c) Joint compounds and joint caulking material;
(d) Grout and shims;
(e) Pipe shop fabrication drawings (spool drawings);
(f) Cleaning fluids and flushing fluids and equipment.
(g) Testing fluids and equipment;
(h) Wrapping and coating materials;
(i) Paint and painting supplies; and
(j) All other items not specifically identified as supplied by the Employer.
18. Supply and install piping identification labels which identify flow direction and content
in accordance with Norma Tecnica Nacional 399.012 and the Refineria de
Cajamarquilla color-coded banding system.
19. Obtain preapproval from the Engineer prior to substitution where documents indicate
"or approved equivalent".
385294050.doc Page 2 of 10
Updated: 25-Apr-18
3.4.2 Area 10 - Concentrate Handling
(k) Fabricate, install and test all piping systems indicated on the process and
instrumentation diagrams and general arrangement Drawings, and
including the following piping classifications:
PIPING
FLUID
SERVICE MATERIAL
MATERIAL
CODES
CLASSIFICATION
385294050.doc Page 3 of 10
Updated: 25-Apr-18
PIPING
FLUID
SERVICE MATERIAL
MATERIAL
CODES
CLASSIFICATION
Non-Corrosive Slurries,
Corrosive Slurries, Erosive
YS, YHS, YSE, HR,
Slurries, Spent Electrolyte,
206 V, D, YF, YHF, YF, Polypropylene
Vents, Drains, Non-Corrosive
RF
Filtrates, Corrosive Filtrates,
Electrolyte, Reagent Feed
Non-Corrosive Slurries,
YS, YHS, YSE, HR, Corrosive Slurries, Erosive
208 Slurries, Spent Electrolyte, Polypropylene
V, D, YF, YHF, YF,
HF Vents, Drains, Non-Corrosive
Filtrates, Corrosive Filtrates,
Electrolyte, Feed Electrolyte
Non-Corrosive Slurries,
YS, YHS, YSE, HR, Corrosive Slurries, Erosive
V, D, YF, YHF, YF, Slurries, Spent Electrolyte,
212 PVC
WP, WR, WCS, Vents, Drain, Non-Corrosive
WCR, WWS Filtrates, Corrosive Filtrates,
Electrolyte, Potable Water,
Emergency Water, Cooling
Water Supply, Cooling Water
Return
(l)
22. Demolition
23. Demolition and removal of existing piping within the plant requires the approval of the
engineer and RdC. Removal of existing piping to install new piping or launders
require coordination between construction and operations so as not to jeopardize the
continuing operation. All piping demolished will be transported to operations
warehouse for storage.
24. Rework
25. Any rework as required by the engineer will be born by the contractor.
26. Additions
385294050.doc Page 4 of 10
Updated: 25-Apr-18
27. Additions as identified by the contractor must be presented to the engineer before work
commences
28. Temporary Piping
29. Any temporary piping identified on the drawings will be removed as per the schedule.
This piping is required to facilitate the installation and modification of some existing
tanks within the leaching area. The installation and removal of this piping must be
done to the schedule. All other temporary piping required by operations to maintain
operability must be presented to the engineer before work commences
30. Tie-ins
31. All tie-ins must be identified and scheduled through the engineer and RdC. In the
event of a unscheduled shut down of the process, all effort should be made to all effort
should be made to take advantage of the situation.
32. Insulation
33. All steam lines will be insulated to U283-4-006
34. Special Cleaning
35. Cleaning of the oxygen piping will be done as per an approved cleaning specification
36. Vendor Piping
37. All vendor piping shall be installed as per vendor instructions or as per U283-4-003
Piping Installation specification whichever is more stringent.
38.
39. Fabricate, install and test all piping systems indicated on the process and
instrumentation diagrams and general arrangement Drawings, and including the
following piping classifications:
PIPING
FLUID
SERVICE MATERIAL
MATERIAL
CODES
CLASSIFICATION
385294050.doc Page 5 of 10
Updated: 25-Apr-18
PIPING
FLUID
SERVICE MATERIAL
MATERIAL
CODES
CLASSIFICATION
Pressure Condensate
Non-Corrosive Slurries,
Corrosive Slurries, Erosive
YS, YHS, YSE, HR,
Slurries, Spent Electrolyte,
206 V, D, YF, YHF, YF, Polypropylene
Vents, Drains, Non-Corrosive
RF
Filtrates, Corrosive Filtrates,
Electrolyte, Reagent Feed
Non-Corrosive Slurries,
YS, YHS, YSE, HR, Corrosive Slurries, Erosive
V, D, YF, YHF, YF, Slurries, Spent Electrolyte,
212 PVC
WP, WR, WCS, Vents, Drain, Non-Corrosive
WCR, WWS Filtrates, Corrosive Filtrates,
Electrolyte, Potable Water,
Emergency Water, Cooling
Water Supply, Cooling Water
Return
(m)
40. Demolition
41. Demolition and removal of existing piping within the plant requires the approval of the
engineer and RdC. Removal of existing piping to install new piping or launders
requires coordination between construction and operations so as not to jeopardize the
continuing operation. All piping demolished will be transported to operations
warehouse for storage.
42. Rework
43. Any rework as required by the engineer will be born by the contractor.
385294050.doc Page 6 of 10
Updated: 25-Apr-18
44. Additions
45. Additions as identified by the contractor must be presented to the engineer before work
commences
46. Tie-ins
47. All tie-ins location must be identified and scheduled through the engineer and RdC
with the tie-in list kept up to date. In the event of a unscheduled shut down of the
process, all effort should be made to take advantage of the situation.
48. Insulation
49. All steam lines will be insulated to U283-4-006
50. Hydrogen
51. Within this area of the plant, special care must be exercised because of the
presence of hydrogen. All mix tanks within this area produce hydrogen at
different rates. Welding and grinding in these areas will require permission
from the engineer
52.
53. Fabricate, install and test all piping systems indicated on the process and
instrumentation diagrams and general arrangement Drawings, and including the
following piping classifications:
PIPING
FLUID
SERVICE MATERIAL
MATERIAL
CODES
CLASSIFICATION
Non-Corrosive Slurries,
YS, YHS, YSE, HR, Corrosive Slurries, Erosive
208 Slurries, Spent Electrolyte, Polypropylene
V, D, YF, YHF, YF,
HF Vents, Drains, Non-Corrosive
Filtrates, Corrosive Filtrates,
Electrolyte, Feed Electrolyte
Non-Corrosive Slurries,
YS, YHS, YSE, HR, Corrosive Slurries, Erosive
V, D, YF, YHF, YF, Slurries, Spent Electrolyte,
212 PVC
Vents, Drain, Non-Corrosive
385294050.doc Page 7 of 10
Updated: 25-Apr-18
PIPING
FLUID
SERVICE MATERIAL
MATERIAL
CODES
CLASSIFICATION
(n)
54. Demolition
55. Demolition and removal of existing piping within the plant requires the approval of the
engineer and RdC. Removal of existing piping to install new piping requires
coordination between construction and operations so as not to jeopardize the
continuing operation. All piping demolished will be transported to operations
warehouse for storage.
56. Rework
57. Any rework as required by the engineer will be born by the contractor.
58. Additions
59. Additions as identified by the contractor must be presented to the engineer before work
commences
60. Tie-ins
61. All tie-ins location must be identified and scheduled through the engineer and RdC
with the tie-in list kept up to date. In the event of a unscheduled shut down of the
process, all effort should be made to take advantage of the situation.
62.
63.
64. Fabricate, install and test all piping systems indicated on the process and
instrumentation diagrams and general arrangement Drawings, and including the
following piping classifications:
385294050.doc Page 8 of 10
Updated: 25-Apr-18
PIPING
FLUID
SERVICE MATERIAL
MATERIAL
CODES
CLASSIFICATION
Non-Corrosive Slurries,
Corrosive Slurries, Erosive
YS, YHS, YSE, HR,
Slurries, Spent Electrolyte,
206 V, D, YF, YHF, YF, Polypropylene
Vents, Drains, Non-Corrosive
RF
Filtrates, Corrosive Filtrates,
Electrolyte, Reagent Feed
(o)
65. Demolition
66. Demolition and removal of existing piping within the plant requires the approval of the
engineer and RdC. Removal of existing piping to install new piping or launders
requires coordination between construction and operations so as not to jeopardize the
continuing operation. All piping demolished will be transported to operations
warehouse for storage.
67. Rework
68. Any rework as required by the engineer will be born by the contractor.
69. Additions
385294050.doc Page 9 of 10
Updated: 25-Apr-18
70. Additions as identified by the contractor must be presented to the engineer before work
commences
71. Tie-ins
72. All tie-ins must be identified and scheduled through the engineer and RdC. The
process in the Cadmium plant is batch allowing for more flexibility within the
construction schedule.
73. Insulation
74. All steam lines will be insulated to U283-4-006
75. Hydrogen
76. Within this area of the plant, special care must be exercised because of the
presence of hydrogen. All mix tanks within this area produce hydrogen at different
rates. Welding and grinding in these areas will require permission from the engineer.
385294050.doc Page 10 of 10
Updated: 25-Apr-18