CONSTRUCTION PROGRESS REPORT


(NOTE: This report MUST be prepared at 30%, 60% and 100% of construction)
IP IIRR County Samburu
School St. Paul’s Primary HT’s contact Mr. Lenengatai - 0710477044
Construction of Classroom Contractor Catholic Technical Training Institute
Start Date of Construction 04/09/2015 End Date of Construction 15/10/2015
Construction at 30% Date of the report 25/09/2015

1. Current Project Status;


- Walling is ongoing, currently at a height of 2.1m above the ground floor slab
- Curing of the ground floor slab and masonry wall is ongoing
- Walling materials have been delivered on site
- Sufficient labour has been mobilized on site; 5 skilled and 6 unskilled laborers

2. Progress of the Project as per BoQ;

S/No Description % Remarks


done
Classroom Construction
a. Substructure works 36.7 Done
b. Superstructure walling & 20.9 Ongoing
Concrete works
c. Roofing 20.6 Not yet started
d. Installation of doors & windows 5.7 Not yet started
e. Finishes 16.1 Not yet started

3. Emerging issues/ hindrances;


i. Omission of the provision for louvered vent blocks below windows. The Contractor has however
been notified to adjust the walls to allow for the vents as he proceeds with walling.

4. Conclusion
- The Contractor is cooperative and compliant with all instructions issued on site
- The Project is expected to be completed within the designated time

5. Photos (GPS enabled)


Below are some of the photos taken during site visits. However, most of them are not GPS enabled. A
full photo gallery can be availed upon request

1|Page
ST. PAUL’S PRIMARY SCHOOL; CLASSROOM-SAMBURU COUNTY

Plate 1: Site handover Plate 2: Foundation excavation in progress

Plate 3: Foundation walling in progress Plate 4: Complete foundation wall

Plate 5: Laying of damp-proof polythene Plate 6: Walling in progress


KEEP
CONSTRUCTION PROGRESS REPORT
(NOTE: This report MUST be prepared at 30%, 60% and 100% of construction)
IP IIRR County Samburu
School Nteppes Primary HT’s contact Mr. Lolkirik - 0715103765
Construction of Classroom Contractor Ligwara’s Enterprises Ltd
Start Date of Construction 26/09/2015 End Date of Construction 31/10/2015
Construction at 30% Date of the report 02/10/2015

1. Current Project Status;


- Walling is ongoing, currently at a height of 0.9m above the ground floor slab
- Curing of the ground floor slab and masonry wall is ongoing
- Walling materials have been delivered on site
- Sufficient labour has been mobilized on site; 2 skilled and 6 unskilled laborers

2. Progress of the Project as per BoQ;

S/No Description % Remarks


done
Classroom Construction
a. Substructure works 35.4 Done
b. Superstructure walling & 22.3 Ongoing
Concrete works
c. Roofing 24.1 Not yet started
d. Installation of doors & windows 5.1 Not yet started
e. Finishes 13.1 Not yet started

3. Emerging issues/ hindrances;


ii. Inadequacy of water in the region has slowed down the pace of construction
iii. Expected completion date may be later than the planned date. This depends on how supply of
water stabilizes in Wamba Center

4. Conclusion
- The Contractor is cooperative and compliant with all instructions issued on site
- The Project is expected to be completed later than the designated time

5. Photos (GPS enabled)


Below are some of the photos taken during site visits. However, most of them are not GPS enabled. A
full photo gallery can be availed upon request

3|Page
NTEPPES PRIMARY SCHOOL; CLASSROOM-SAMBURU COUNTY

Plate 7: Excavations for strip foundation Plate 8: Reinforcement fixing for the strip foundations

Plate 9: Backfilling into the foundation walls Plate 10: Hardcore filling and levelling at the
foundations

Plate 11: Sand curing of the GF Slab Plate 12: Walling in progress