PROJECT TITLE :
DATE : LOCATION :
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 2 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
DAFTAR ISI
COVER ……………………………………………………………………………………………………………….... 1
DAFTAR ISI …………………………………………………………………………………………………………… 2
1 . DETAIL ORGANISASI PROJEC …...…………………………………………………………………... 3
2 . STRUKTUR ORGANISASI ……………………………………………………………………………… 4
3 . KINERJA HSE …………………......…………………………………………………………………….... 5
- Report Of Case Work Accident Project Regasification LNG In The Pertamina EP TANJUNG
- Detail Report Of Case Work Accident Project Regasification LNG In Febuary 2018 ( /everyone )
- Rekapitulasi Jam Kerja Aman/Selamat / Safe Working Hours
HEAD OFFICE
Proyek Manajer / Project Manager Jeffry Willem K
Struktur Organisasi /
Organizational Structure
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 5 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
Kom.Griya Indah 1
Perdana Blora, No.3 Blok.B Agus Oran
TJG Hse Laki- 081231- 081348-
Oktavianus 07 Oktober
Laki
Kristen Rt.004/Rw.005 Ab _ 170 68 _ Mulyon g
0765 Officer 1994 Kel.Guntungpaikat 236461 319373
Kurniawan o Tua
Kec.Banjarbaru Selatan
KINERJA HSE
HSE Performance
Detail Report Of Case Work Accident Project Regasification LNG In March 2018 ( / everyone )
Febuary 2018
Jumlah Total Jam Kecelakaan
Jumlah Perawatan Tindak
No Nama Posisi Tenaga Lama Kerja Aman menyebabkan Hari Jumlah Kematian Kerusakan Lanjut
Kerja Hari Medis /
Kerja / Work Safe Hilang / Lost Time Korban / Fatality / kerugian
Hilang MTC
Hours Injury (LTI)
HEAD OFFICE – JAKARTA
Free
1
Jeffry Willem Kappu PMO 1
time
- - - - - - - -
Free
2
Eko Saputra HSE Coordinator 1
time
- - - - - - - -
JOB LOCATION – POWER PLANT PEP TANJUNG (KAL.SEL)
8 jam x
3
M. Prima Jaya Site Coordinator 1 6 hari
- - - - - - -
8 jam x
4
Perdana Oktavianus K HSE Officer 1
6 hari
- - - - - - -
Achmad Rifani
Heriansyah
Didit Saputra
Wahyu Aprilian Fernanda 8 jam x
5 Operator 8 - - - - - - -
Wisnu Alradi 5 hari
Dedy Amrullah Sani
Setia Putra
Patra Sagara Tanjung
DRIVER HELPER TRUCK TRANSPORTATION BONTANG – TANJUNG – BONTANG (KAL.SEL-KAL.TIM)
Arsudin
Iwan M
Sutrisno B 9822 SEH
M Amzah
Hendri B 9823 SEH Driver
Bambang S 9 jam x
6 Sawid B 9824 SEH & 13 - - - - - - -
Goldy N P 4 hari
Romi B 9825 SEH Helper
Alfredsiano
Andi R B 9590 SEH
Bolten S.G
Tri Suci R
JUMLAH 25 - - - - - - -
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 9 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
REKAPITULASI JAM KERJA AMAN / JAM KERJA SELAMAT TAHUN 2018
Maret
No Nama Posisi K J SB M SN SL R K J SB M SN SL R K J SB M SN SL R K J SB M SN SL R K J SB Total
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
HEAD OFFICE – JAKARTA
Project
1 Jeffry Willem Kappu
Manager
HSE
2 Eko Saputra 8 8 8 8 8 8 8 8 8 8 8
Coordinator
JOB LOCATION – POWER PLANT PEP TANJUNG (KAL.SEL)
Site
3 M. Prima Jaya 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Coordinator
HSE
4 Perdana Oktavianus K 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Officer
5 Achmad Rifani (A) Operator 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
6 Heriansyah (G) Operator 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
7 Didit Saputra (C ) Operator 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
8 Wahyu Aprilian Fernanda (B) Operator 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
9 Wisnu Alradi (D) Operator 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
10 Dedy Amrullah Sani (F) Operator 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
11 Setia Putra (E ) Operator 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
12 Patra Sagara Tanjung (H) Operator 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
DRIVER HELPER TRUCK TRANSPORTATION BONTANG – TANJUNG – BONTANG (KAL.SEL-KAL.TIM)
Driver &
18 B 9824 SEH
Arsudin Helper
Iwan M Driver &
19 Sutrisno M Amzah B 9825 SEH
Hendri Helper
Bambang Driver &
20 Sawid B 9823 SEH
Goldy N P Helper
Romi
Alfredsian B 9822 SEH Driver &
21 Andi R
Bolten S. Helper
Tri Suci Driver &
22 B 9590 SEH
Helper
Subtotal JAM
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 10 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
Jadi, Waktu yang di perlukan driver untuk PP Bontang – Tanjung – Bontang adalah 35,6 jam, atau jika dalam
perjalanan dibutuhkan waktu tempuh selama 4 hari dapat diperkirakan waktu yang digunakan driver untuk mengemudi
perharinya yaitu 8,9 / 9 jam perharinya dan sisanya 15,1 / 15 jam dalam satu hari adalah waktu yang digunakan untuk
beristirahat dan sebagainya.
Berdasarkan hasil analisis waktu tempuh tersebut dapat disimpulkan bahwa jam kerja driver sudah hampir
mendekati standar persyaratan mengemudi yang terdapat pada Undang-Undang Pasal 90 Nomor 22 Tahun 2009
Tentang Lalu Lintas dan Angkutan Jalan bahwa waktu kerja bagi pengemudi kendaraan bermotor umum paling lama 8
jam per hari.
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 11 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
Peluang (tinggi, sedang, dan rendah) atau kemungkinan seseorang terkena Terpapar kebisingan, heat stress, tersengat listrik, keracunan bahan
Resiko / Risk
bahaya sehingga terjadi kecelakaan akibat hal tersebut pada periode tertentu. kimia. Tindakan yang diambil berupa upaya pencegahan/warning.
Suatu kejadian tidak diinginkan, diharapkan yang bila keadaannya sedikit saja
Hampir-Nyaris / Near
berbeda dapat mengakibatkan luka pada Manusia, kerusakan Harta benda atau Terpeleset, tersandung, salah dalam pengambilan bahan kimia.
Miss
kerugian
Pertolongan Pertama Kasus kecelakaan kerja yang dalam perawatan lukanya tidak membutuhkan
Pada Kecelakaan / penanganan dari tenaga medis yang professional (perawat/dokter), cukup first Luka terbuka akibat terjatuh / tergores benda tajam
First Aid Case aider ( Petugas P3K ) yang sudah diberikan pelatihan.
Batas Pekerjaan / Kasus kecelakaan kerja yang mana korban tidak dapat bekerja secara normal di
Restricted Work Case bagiannya atau ditugaskan untuk bekerja di jenis pekerjaan lainnya pada
( RWC ) shift/hari berikutnya setelah kecelakaan.
Permanent Partial Kasus kecelakaan kerja yang menyebabkan si pekerja mengalami Seperti kehilangan satu mata/penurunan fungsi penglihatan,
Dissability ( PPD ) ketidakmampuan fisik/fungsi sebagian dan bersifat permanent kehilangan satu tangan dan lainnya.
Fatality Kasus kecelakaan kerja yang menimbulkan kematian pada si pekerja Meninggal dunia
Lost Time Injury ( Jumlah kasus kecelakaan atau cidera yang menyebabkan kehilangan waktu kerja
LTIs ) dari Fatality + PTD + PPD + LWC
Dampak Lingkungan / Kecelakaan kerja yang menyebabkan kerusakan lingkungan secara langsung
Environment Damage seperti tumpahnya minyak ke perairan.
MARCH
NO PROGRAM HSE SCHEDULE INFORMATION
I II III IV
I HSE Meeting Program
1 Safety Talk Daily √ √ √ √
2 Safety Briefing Weekly √ √ √ √
3 HSE Monthly Meeting Monthly
4 HSE Management Meeting 3/6 monthly
5 Review Management Meeting Yearly
6 HSE Management Site Visit Refer to List of Project
II HSE Training
1 HSE Orientation/Induction Refer to List of Project
2 Pengajuan Surat Pengantar Partisipasi Progam Pelatihan Safety 6 Monthly
3 HSE Skill Training - APD (PPE) & ERP (Emergency Response Procedure) Yearly
4 Drill ERP Office Yearly
5 Sosialisasi SMK3 and PromKes 3 Monthly
III HSE Reporting
1 HSE Daily Report Daily √ √ √ √
2 HSE Weekly Report Weekly √ √ √ √
3 HSE Monthly Report Monthly √
4 Safe Man Hours Report, Accident Report & APD Report Weekly √
IV HSE Inspection & Audit Program
1 Safety Patrol Monthly
2 Safety Inspection 6 Monthly
3 Audit HSE Internal Yearly
4 Audit HSE External (Audit OHSAS) Yearly
V Healthy & Medical Program
1 Tes Kesehatan (Karyawan) Refer to HRD
2 Medical Check Up (Rutin) Yearly
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 14 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
3 Medical Check Up (Khusus/Requirement Project) Refer to list project
4 Minggu Sehat Jasmani Weekly
VI Continuous Improvement Program
1 HSE on-line Program - Tips & Info HSE by E-mail 2 Weekly
2 Housekepping Daily √ √ √ √
3 Pembuatan Pot bunga dan pembelian bunga / Planting fruit trees √
4 Pembuatan Lantai Kerja pada drainase evap & Standar/tempat Flaxible Hose
5 Rambu-rambu, Poster, Slogan & Mading HSE 3 Monthly
6 Investigasi Report
Safety Talk
2 Reporting
Daily Report
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 20 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
weekly
Report
Report Jam
Kerja Terlampir Terlampir Terlampir
Selamat
Report Data
Case Terlampir Terlampir Terlampir
Accident
Make Job
Safety
Analysis
Pengajuan
Permit Izin
Masuk (
Pembuatan
Memo Safety
Induction
and Surat
Izin Masuk
Lokasi)
Penyediaan
APAR dan
First Aid Box
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 23 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
Gas test
Conection
Pipe line
Maret
No Nama Posisi K J SB M SN SL R K J SB M SN SL R K J SB M SN SL R K J SB M SN SL R K J SB
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 M. Prima Jaya Site Coordinator P S P P S P S P S S P S P S P P S P S P S S P S P S P
2 Perdana Oktavianus K HSE Officer S P S S P S P S P P S P S P S S P S P S P P S P S P S
3 Achmad Rifani (A) Operator S S S S S P P P P P M M M M M S S S S S P P P
4 Heriansyah (G) Operator S S S S S P P P P P M M M M M S S S S S P P P
5 Didit Saputra (C ) Operator S S P P P P P M M M M M S S S S S P P P P P M
6 Wahyu Aprilian Fernanda (B) Operator S S P P P P P M M M M M S S S S S P P P P P M
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 24 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
7 Wisnu Alradi (D) Operator P P P M M M M M S S S S S P P P P P M M M M M
8 Dedy Amrullah Sani (F) Operator P P P M M M M M S S S S S P P P P P M M M M M
9 Setia Putra (E ) Operator M M M M M S S S S S P P P P P M M M M M S S S S
10 Patra Sagara Tanjung (H) Operator M M M M M S S S S S P P P P P M M M M M S S S S
:
Libur / OFF P : Shift jam 07:00 – 15.00
Kebersihan area dalam gedung Rruang Kontrol
OPERATIONAL ACTIVITIES OF PROJECT REGASIFICATION OPRATIONS LNG IN THE POWER PLANT AT PERTAMINA EP TANJUNG
NO ATTACHMENT EXPLANATION & PROCEDURE
1 Mobilisasi Iso Tank (Supply LNG)
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 25 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
Mobilisasi Iso Tank (Supply LNG) dalam hal ini merupakan kegiatan penggantian atau pertukaran antara Iso Tank
Full yang dibawa oleh Headtruck yang sebelumnya telah melakukan loading atau pengisian di PT.Badak LNG
Bontang-Kalimantan Timur dengan Iso Tank Kosong/Habis setelah digunakan atau yang terparkir di Power Plant
Pertamina EP Tanjung. Adapun Prosedur yang digunakan untuk proses Mobilisasi Iso Tank (Supply LNG) adalah
sebagai berikut:
A.Permit/Perizinan Supply LNG
1. Prin/cetak Surat Izin Masuk Sementara yang berisi STNK, SIM beserta KTP Driver yang dipastikan
kedatangannya pada hari tersebut agar dicek/distampel pada bagian Scurity Kantor Industri Pertamina EP
Tanjung.
2. Serahkan SIM-S dan Kordinasikan ke bagian Scurity Power Plan akan kedatangan LNG untuk dilakukan
pengamanan jalan saat mobilisasi.
B.Pra-Mobilisasi
3. Lepaskan kabel Grounding pada Iso Tank kosong/habis atau yang akan ditukar/Change
4. Report Head Truck yang pada saat itu telah berada di Power Plan kedalam form mobilisasi yang berisikan Plat
Nomor Polisi Headtruck, Kode Iso Tank (full) beserta jam masuknya, dan Kode Iso Tank (Out) beserta jam
keluarnya.
5. Tanyakan dan simpan Data Sheet yang diserahkan oleh driver yang diterima saat melakukan proses loading di
PT.Badak LNG Bontang.
6. Pastikan seluruh tenaga kerja yang berperan dalam kegiatan ini telah menggunakan APD yang sesuai seperti
Safety Helmet, Coverall, Safety Shoes, Safety Glasses/Face Shield, dan Cotton Gloves serta lakukan
pengawasan oleh supervisor/HSE officer.
7. Pastikan bahwa APAR telah tersedia di Lokasi dan layak untuk digunakan apabila terjadi keadaan darurat
C.Proses
8. Head truk yang datang, melepaskan Iso Tank full LNG di daerah yang telah ditentukan (Parking sementara)
9. Lakukan pengecekkan Iso Tank full LNG untuk memastikan semua valve pada kondisi Close
10. Lakukan uji Gas Test pada Connection BOG, Connection LNG dan Valve-valve yang berada pada Iso Tank
(Full)
11. Head truk lalu mengaitkan / menarik / memindahkan Iso Tank (habis/kosong) dan meletakan nya diluar area
parking regasifikasi LNG
12. Kemudian Head truck memasukan kembali Iso Tank (full) yang sebelumnya di lepas area parking sementara
atau yang telah dilakukan pengecekan dan pengujian Gas Test, ke area parking regasifikasi LNG
D.Finishing
13. Setelah Truck dan Iso Tank kosong/habis meninggalkan lokasi parking dan melanjutkan perjalanan menuju PT
Badak LNG Bontang-KalTim untuk melakukan pengisian ulang (loading), atau telah berakhirnya kegiatan
Mobilisasi Iso Tank (Supply LNG) seluruh tenaga kerja regasifikasi LNG membersihkan area parkir Iso Tank
dari kotoran tanah yang menempel pada ban triler Iso Tank.
14. Pasang kembali kabel Grounding pada Iso Tank full yang telah ditukar/Change atau telah terparkir diarea regas
NO ATTACHMENT EXPLANATION & PROCEDURE
2 Installations Flaxible Hose & Flashing us Nitrogen
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 26 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
Installations Flaxible Hos & Flashing Flaxible Hos dilakukan apabila Flaxible Hose telah atau akan
dipindah dari Iso Tank yang satu ke Iso Tank yang lain untuk memastikan tidak terdapat oksigen dan tidak
terdapat kebocoran pada Flaxible Hose, conektion atau valve pada Iso Tank maupun pipe line regasifikasi
LNG.
Adapun Prosedur yang digunakan untuk proses Installations Flaxible Hose & Flashing us Nitrogen
adalah sebagai berikut:
Monitoring dan pelaporan atau rekapitulasi data dalam hal ini meliputi :
- Data pada Iso Tank : Liquid Level (mmH2O), Pressure (Bar) dan GHV yang terdapat pada Data
Sheet/Sertifikate LNG
- Data pada MRS (Metering Regulating System) : Turbin Meter (m3)
- Data pada EVC (Electronic Volume Corrector) : Tekanan (Bar), Temperatur (C0) dan Kompresibilitas
(K)
Beberapa data tersebut di rekam atau dimasukan kedalam FORM Pemakaian Harian Per-Jam nya untuk
memperoleh nilai matrial yang digunakan untuk mendapatkan nilai satuan gas dalam MMBTU (Million
British Thermal Uni) atau nilai penggunaan stau pemakaian gas oleh Pertamina EP Tanjung melalui
3 beberapa rumus yang telah ditetapkan.
Adapun Procedur yang digunakan untuk proses Installations Flaxible Hose & Flashing us Nitrogen
adalah sebagai berikut:
1. Koordinasikan dengan bagian kompresor & Turbin di powerplant Pertamina untuk melakukan
proses Regasifikasi LNG. Catat dan cek kondisi tekanan yang di minta.
2. Catat awalan Level mmh2o (LL1) dan Tekanan di Isotank serta GHV / Gross heating value nya
( GHV terdapat dalam data sheet bawaan isotank).
3. Catat kondisi Tekanan Isotank, Metering / Volume awal di Turbin Meter, serta catat juga pada
EVC data tekanan, temperature dan Kompresibiltas awalan
4. Pencatatan perubahan Level Volume mmh20 (LL1) dan tekanan ISO Tank,catat juga flowmeter
gas pada Turbin Meter untuk menghitung jumlah gas yang mengalir, dan di EVC catat data
tekakan, temperature serta Kompresibiltas setiap 1 jam.
(Start - Gas In), (Runing - Setting Pressure/Flowrate), (Gas Stop – Delay Regasification LNG) & (Gas Stop – LNG Liquid Drop)
Gas In dalam hal ini merupakan proses awal Start regasifikasi LNG sebelum dinyatakan Runing. Gas In
dilakukan apabila sebelumnya proses regasifikasi LNG dalam posisi Stop yang dikarenakan Drop (seluruh/Ke-4
Iso Tank yang terparkir dalam posisi kosong/habis) atau Delay (ada beberapa Iso Tank yang terparkir dalam
posisi masih berisikan Liquid LNG namun ada permasahan seperti kerusakan/gas lapangan Pertamina EP
dalam setatus tinggi).
Adapun Procedur yang digunakan untuk proses Start - Gas In dan Runing - Setting Pressure/Flowrate adalah
sebagai berikut:
Atur bukaan liquid Fill and Drain Valve ( Apabila tekanan di Iso Tank masih dalam posisi
V1A & V1B ) keposisi 900 untuk (lebih dari) > 2 Bar namun tetap tidak ada
6
mendapatkan kondisi tekanan dan flow rate perubahan tekanan atur bukaan liquid Fill and
operasi yang di butuhkan. Drain Valve ( V1A & V1B ) keposisi
5
1800/2700/3600 hingga 1-2 putaran untuk
Tahan tekanan regasifikasi pada kondisi mendapatkan kondisi tekanan dan flowrate operasi
7 tekanan 1,5 - 2 bar sesuai kebutuhan yang di butuhkan sesuai dengan permintaan tim
Pertamina EP Kompresor / tim Turbin Power Plan PEP Tanjung
Bukaan Ball Valve 6'' – 150# BV-020-01 Jika tetap tidak ada perubahan tekanan maka dapat
8
output MRS berada pada posisi 2 – 4 Strip. disetting dengan mengaktifkan 2-3 unit Vaporizer/
6 Evaporator secara bersamaan. Hal ini berguna
mempercepat laju perubahan wujud liquid menjadi
gas sehingga memperbesar tekanan.
Apabila terdapat kebocoran pada peralatan
Regasifikasi, segera hentikan pengaliran LNG Apabila terdapat kebocoran pada peralatan
dengan menutup Fill and Drain Valve ( V1A / Regasifikasi, segera hentikan pengaliran LNG
V1B ) dan PBUC Fire Block Valve / Safety dengan menutup Fill and Drain Valve ( V1A / V1B
9
Valve (V4 / V2) pada ISO Tank. Lakukan ) dan PBUC Fire Block Valve / Safety Valve (V4 /
Venting di Fill Line Bleed valve (V11) untuk 7
V2) pada ISO Tank. Lakukan Venting di Fill Line
mengeluarkan gas sisa pada peralatan Bleed valve (V11) untuk mengeluarkan gas sisa
Regasifikasi sebelum melakukan perbaikan. pada peralatan Regasifikasi sebelum melakukan
perbaikan.
MONTHLY REPORT
Job Site – LNG Regasification at Pertamina EP Asset 5 Tanjung Field
Page 30 of 25 Location : Power Plant Date : 1 s/d 31 Maret 2018 HSE
No Gas Stop – Delay Regasification LNG No Gas Stop - LNG Liquid Drop
Gunakan APD yang sesuai seperti Safety Helmet,
Gunakan APD yang sesuai seperti Safety Helmet,
Coverall, Safety Shoes, Safety Glasses/Face
Coverall, Safety Shoes, Safety Glasses/Face Shield,
Shield, Cotton Gloves untuk helper, Cyrogenic
1 1 Cotton Gloves untuk helper, Cyrogenic Gloves /
Gloves / Leather Gloves untuk mekanik/operator
Leather Gloves untuk mekanik/operator serta
serta lakukan pengawasan oleh supervisor/HSE
lakukan pengawasan oleh supervisor/HSE officer.
officer.
Pastikan bahwa APAR telah tersedia di Lokasi Pastikan bahwa APAR telah tersedia di Lokasi dan
2 dan layak untuk digunakan apabila terjadi 2 layak untuk digunakan apabila terjadi keadaan
keadaan darurat darurat
Untuk menghentikan aliran Liquid LNG, ada Untuk menghentikan aliran Liquid LNG, ada
beberapa valve yang harus ditutup yang pertama: beberapa valve yang harus ditutup yang pertama:
tutup Fill and Drain Valve (V1A & V1B); setelah tutup Fill and Drain Valve (V1A & V1B); setelah
3 itu tutup Fill and Drain Fireblock valve/Safety 3 itu tutup Fill and Drain Fireblock valve/Safety
Valve (V2 / V4) pada Iso Tank; dan yang terlhir Valve (V2 / V4) pada Iso Tank; dan yang terlhir
tutup Gate Valve A/B/C/D pada Pipe Line yang tutup Gate Valve A/B/C/D pada Pipe Line yang
telah digunakan. telah digunakan.
Melakukan pengecekan tekanan pada keluaran di Melakukan pengecekan tekanan pada keluaran di
MRS dan apabila sudah tidak bisa pengaliran lagi MRS dan apabila sudah tidak bisa pengaliran lagi
maka tutup full Ball Valve 6'' – 150# BV-020-01 maka tutup full Ball Valve 6'' – 150# BV-020-01
5 6
output MRS dan Venting Gas yang output MRS dan Venting Gas yang tersisa/tertinggal
tersisa/tertinggal pada pipe line dengan membuka pada pipe line dengan membuka Vent Valve / drain
Vent Valve / drain yang berada di Inlet MRS. yang berada di Inlet MRS.