Академический Документы
Профессиональный Документы
Культура Документы
Outline:
At present, NHPC is a Mini Ratna Category-I Enterprise of the Govt. of India with an authorized
share capital of Rs. 1,50,000 Million. With an investment base of over Rs.3,17,000 Million
Approx. , NHPC is among the TOP TEN companies in the country in terms of investment.
Initially, on incorporation, NHPC took over the execution of Salal Stage-I, Bairasiul and Loktak
Hydro-electric Projects from Central Hydroelectric Project Construction and Control Board.
Since then, it has executed 13 projects with an installed capacity of 5175 MW on ownership
basis including projects taken up in joint venture. NHPC has also executed 5 projects with an
installed capacity of 89.35 MW on turnkey basis. Two of these projects have been commissioned
in neighboring countries i.e. Nepal and Bhutan.
SALES Vs PROFIT
Since its inception in 1975, NHPC has grown to become one of the largest organisation in the
field of hydro power development in the country. With its present capabilities, NHPC can
undertake all activities from concept to commissioning of Hydroelectric Projects.
The electricity sector in India is predominantly controlled by Government of India's public sector
undertakings (PSUs). Major PSUs involved in the generation of electricity include National Thermal
Power Corporation (NTPC), National Hydroelectric Power Corporation (NHPC) and Nuclear Power
1
Corporation of India (NPCI). India was one of the pioneering states in establishing hydro-electric power
plants. The installed capacity as of 2008 was approximately 36647.76. The public sector has a
predominant share of 97% in this sector.
However the government must speed up the process of clearing new hydroelectric power
projects and should rope in the private enterprise for the purpose of establishing small hydro
schemes. This will require the government to take suitable policy initiatives. The advantages that
hydroelectric power offer over thermal power plants are immense –
3. Though hydroelectric power projects take a long time to be built, they have a very long
life. The first hydro-project completed in 1897 is still in operation.
4. Cost of generation, operation and maintenance is lower than the other sources of energy.
5. Ability to start and stop quickly and instantaneous load acceptance/rejection makes it
suitable to meet peak demand and for enhancing system reliability and stability.
6. Hydroelectric power plants offer higher efficiency (over 90 per cent) as compared to
thermal power (35 per cent) and gas (50 per cent).
7. Cost of generation is free from inflationary effects after the initial installation.
8. Storage based hydro schemes often provide additional benefits of irrigation, flood control,
drinking water supply, navigation, recreation, tourism, etc.
Though concerns remains over the drawbacks of hydroelectric power plants – dislocation of
population residing in the reservoir area, damage to aquatic life (partly controllable by measures
like building fish ladders for the aquatic species moving upstream and using turbines and power
plants of appropriate design so that fishes pass through it with least damage as they swim
downstream), emission of greenhouse gases due to anaerobic decay of the plant material in the
flooded area and a possibility of dam failure or a terrorist attack on it – the advantages of
hydropower far outweigh the disadvantages.
Hence Indian government must make all efforts to increase the installed hydroelectric power
capacity in the country despite the high initial cost incurred in building them in order to achieve
its targets on power supply.
2
Power station State Operator Units Total capacity
(MW)
Srisailam Andhra Pradesh APGenco 1670
Nagarjunasagar Andhra Pradesh APGenco 1 X 110, 7 X 100.8, 5 X 965
30
SardarSarovar Gujarat SSNNL 6X200, 5X140 1450
Baspa-II Himachal Pradesh JHPL 3 X 100 300
NathpaJhakri Himachal Pradesh SJVNL 6 X 250 1500
Bhakra Himachal Pradesh BBMB 5 X 108, 5 X 157 1325
Dehar Himachal Pradesh BBMB 6 X 165 990
BairaSuil Himachal Pradesh NHPC 3 X 60 180
Chamera-I Himachal Pradesh NHPC 3 X 180 540
Chamera-II Himachal Pradesh NHPC 3 X 100 300
Pong Himachal Pradesh BBMB 6 x 66 396
Uri - I Jammu & NHPC 4 X 120 480
Kashmir
Dulhasti Jammu & NHPC 3 X 130 390
Kashmir
Salal J& K NHPC 6 X 115 690
Sharavathi Karnataka KPCL 1469
Kalinadi Karnataka KPCL 1225
Idukki Kerala KSEB 6 X 130 780
Omkareshwar Madhya Pradesh NHPC 8 X 65 520
IndiraSagar Maharashtra NHPC 8 X 125 1000
Loktak Manipur NHPC 3 X 35 105
Koyna Maharashtra MahaGenco 1960
Rangit Sikkim NHPC 3 X 20 60
Teesta - V Sikkim NHPC 3 X 170 510
Tanakpur Uttarakhand NHPC 3 X 40 120
Dhauliganga-I Uttarakhand NHPC 4 X 70 280
Requirements
According to the Government of India estimates, the power requirement in the country will
increase to 200,000 MW by 2012 and to 400,000 MW by 2020. Hence India needs to exploit all
its available natural resources to the fullest in order to bridge the widening demand-supply gap in
the power sector.
Hydroelectricity thus assumes greater importance than before as India still has a huge untapped
hydroelectric power generation potential. According to the Central Electricity Authority, which
generates important statistics on the power generation and usage in the country, the viable hydro
3
potential in India is 84,000 MW at 60 per cent load factor which is equivalent to 1,48,700 MW
installed capacity.
In addition to this, 6872 MW from 1512 small hydro schemes can also be economically
exploited. Further, the government agencies have identified 56 sites from pumped storage
schemes with an aggregate installed capacity of 94,000 MW.
But despite India being one of the pioneering states in hydroelectric power in Asia, with
Darjeeling power plant established in 1898 and Shimsa (Shivanasamudra) power plant
established in 1902, the total installed capacity of hydroelectric power plants in the country was
only 36647.76 MW in 2008.
Currently, the hydroelectric power plants generate only 21 per cent of the electricity consumed in
the country with 76 per cent of the total electricity being generated by thermal power plants
which are highly polluting and depend on non-renewable fossil fuels.
According to S K Garg, Chairman & Managing Director of NHPC Ltd which is India’s largest
hydroelectric power company and which has been conferred Mini Ratna status by the
government of India, a total of 12 projects with a total installed capacity of 5322 MW will be
established by the company during the Eleventh Plan (2007-2012).
Sites evaluated
1. Bursar,J& K
2. KarmoliLumtiTulli ,Uttarakhand
3. GarbaTawaghat, Uttarakhand
4. ChungarChal, Uttarakhand
5. Lachen,Sikkim
4
Parameters for Assignments of Weights
The following parameters were identified to determine the suitability of the Power Plant at a
particular location
Site Requirements
Each site has been further evaluated based upon the following parameters
1. Geology
2. Water Storage Capability
3. Seasonal Variations in Water Supply
4. Raw Material Availability
5. Water Flow Volume
Community Impacts
1. Relocation expenses
2. Local Resources Affected
3. Employment Potential
Economic Impacts
1. Cost of Alternatives
2. Total Capital Costs & Land Valuation
3. Transmission & Distribution Charges
5
The percent weight estimates of each of the five 1st level parameters and eighteen 2nd level
parameters were calculated based on opinions from NHPC guidelines, consultants working in
this industry and using case-studies.
The sites are rated on a discrete scale of (1-9) with 1 as the worst and 9 the best against each
criterion as follows:-
CRITERION A B C D E
Geology 4 6 8 9 8
Water Storage Capability 5 7 4 5 2
Seasonal Variations in Water Supply 6 4 5 7 2
Raw Material Availability 6 3 7 4 1
Water Flow Volume 7 5 4 3 1
Relocation expenses 2 6 9 9 9
Local Resources Affected 4 7 6 3 6
Employment Potential 5 6 3 5 3
Flora & Fauna Submerged 3 4 5 3 7
Downstream ecology 2 6 6 3 5
Construction Hazards 2 7 8 9 9
Long term effects 6 4 9 7 3
Land lost in Submersion 5 5 3 5 7
Cost & Difficulty 7 3 9 9 8
Terrain Access & Suitability for Construction 7 5 4 9 10
Cost of Alternatives 3 6 2 1 4
Total Capital Costs & Land Valuation 3 3 6 9 9
Transmission and Distribution Charges 5 7 5 7 8
Subsequently, the preference of each parameter in comparison to the other is calculated further
across different parameters using the above ratings and the priority matrix at the 3rd hierarchy is
determined.
6
Hierarchy
As mentioned earlier, the goal of this problem is to choose the best location for Hydro power
plant. We evaluated the 5 sites based on the criteria by following a 3 level hierarchy as shown
below
Environmental
Site Community Land use Economic
Impacts &Public
Requirements Impacts impacts Impacts
health
Total Capital
Water Storage Local Resources Downstream
Cost & Difficulty Costs & Land
Capability Affected ecology
Valuation
Water Flow
Volume
We used AHP to calculate weights for each criterion. Based on the composite weights, the final
site was chosen.
7
Solution
The problem has 5 main criteria and 18 sub criteria. Hence the total number of comparison
matrices is 24 (18+5+1).
At first, weights are determined for the main criteria as follows.
- Normalize the matrix
- Find out the relative weights
- Check whether the matrix is consistent
o Calculate Eigen value
o Calculate Consistency Index (CI)
o Find out Random consistency Index (RI)
o Calculate Consistency Ratio (CR) as
CR = CI/RI
Comparison matrix
Environmental
Site Community Land use Economic
Criteria Impacts &
Requirements Impacts impacts Impacts
Public health
Environmental Impacts
1/4 3 1 1/3 1/8
&Public health
Economic Impacts 4 7 8 2 1
Normalized matrix
Site Requirements 0.1319 0.1500 0.2449 0.1250 0.1239
Community Impacts 0.0440 0.0500 0.0204 0.0417 0.0708
Environmental Impacts
&Public health 0.0330 0.1500 0.0612 0.0833 0.0619
Land use impacts 0.2637 0.3000 0.1837 0.2500 0.2478
Economic Impacts 0.5275 0.3500 0.4898 0.5000 0.4956
8
The weights are as follows:
The same approach described above is followed to calculate weights of the 18 other
criteria.
Comparison matrix
Seasonal
Water Water
Variations Raw Material
Criteria Geology Storage Flow
in Water Availability
Capability Volume
Supply
Geology 1.0000 3.0000 3.0000 0.5000 4.0000
Water Storage Capability 0.3333 1.0000 1.0000 0.1667 1.0000
Seasonal Variations in Water
0.3333 1.0000 1.0000 0.3333 3.0000
Supply
Normalized matrix
Water Seasonal Water
Storage Variations in Raw Material Flow
NORMALIZED Table Geology Capability Water Supply Availability Volume
Geology 0.2553 0.2500 0.3600 0.2143 0.3333
Water Storage Capability 0.0851 0.0833 0.1200 0.0714 0.0833
Seasonal Variations in Water
Supply 0.0851 0.0833 0.1200 0.1429 0.2500
Raw Material Availability 0.5106 0.5000 0.3600 0.4286 0.2500
Water Flow Volume 0.0638 0.0833 0.0400 0.1429 0.0833
9
The weights are as follows:
Geology 28.26
Water Storage Capability 8.86
Seasonal Variations in Water
13.63
Supply
Raw Material Availability 40.98
Water Flow Volume 8.27
Similarly, the weights of each site, viz. A, B, C, D, E are calculated against each 2nd level
criterion and the matrices are checked for consistency.
In the end, the composite weights for each site are calculated as follows:
10
Flora &
Environmental Fauna Downstream Construction Long term Weight
Submerged ecology Hazards effects
Weights 34.71 17.45 12.40 35.44
A 13.64 9.09 5.56 20.69 0.1434
B 18.18 27.27 19.44 13.79 0.1837
C 22.73 27.27 22.22 31.03 0.2640
D 13.64 13.64 25.00 24.14 0.1877
E 31.82 22.73 27.78 10.34 0.2212
11
The final composite weights for A, B, C, D, E are obtained as:
Land Economic
Site Requirement Community Environment use Impacts
15.51 4.54 7.79 24.90 47.26 100.00
The final composite weights show that maximum value is 23.45126371. Since this weight occurs for
site D, site D is the winner.
12
Conclusion
Final Results
As it is evident from the above scores, based upon the various criteria evaluated in the problem, the best
alternative among the sites is ChungarChal, Uttarkhand.
References
Site evaluation for ranking study of potential hydro-power projects: An Indian perspective using
spatial technologies- A.K. Charaborti, Water Resources Group, NRSA, Hyderabad, India
13