Академический Документы
Профессиональный Документы
Культура Документы
Date :
PROGRES TARGET
NO ACTIVITY TODAY CUM FINISH CONSTRAINT NOTE
% % Date
C DRAWING
D REPORT ENGINEERING
NO SCOPE SPESIFICATION
SURVEY DESIGN DRAWING CLARIFICATION MTQ/BTQ SHOP DRAWING
DESCRIPTION
SHEET CONTROL
SCOPE OF WORKS ENGINEERING
Project :………………………………………
Owner :………………………………………
Location :………………………………………
NO DESCRIPTION SPECIFICATION
SURVEY
DESIGN
DRAWING
QUANTITY
SURVEYOR
SHOP DRAWING
AS-BUILT DRAWING
DATE VOLUME CONFIRM
Project Name :
Project No. :
Owner :
Study :
Revision :
Project name :
Location : Bontang. Kalimantan Timur
Owner : PT. Indominco Mandiri
Consultant :-
Contractor : PT. Multicom Intermitra
Departement : Engineering
Date :
NO DESCRIPTION
SPESIFICATION UNIT QTY REMARK