Вы находитесь на странице: 1из 1

Status At :

SUB-CONTRACTOR/SUPPLIER COMPARISONS 04:21 29 April 2018


Name Name Name

Site Clearance
B of Q Ref Description Qty. Unit Rate Amount Rate Amount Rate Amount

Aboricultural Gang with chipper and Climbing equipment 3.00 Day 653.20 1,959.60 653.20 1,959.60 -
-

Stock proof fence 1.2m with 75-100mm strainers, 50-75mm


1.50 100 lm 646.00 969.00 646.00 969.00 -
posts at 4m centres with sheep netting and barbed wire
-
Order Amendment -
-
Aboricultural Gang with chipper and Climbing equipment 2.50 Day 653.20 1,633.00 653.20 1,633.00 -
-
-
-
-
-
-
-
-
-
-
-

SUB-TOTAL 4,561.60 4,561.60


Discount - - -
Adjustment to bring to common standard(0% commercial receovery) £0.00
Lowest Tenderer : Adjusted Value 4,561.60 4,561.60
Terms
4,561.60 Qualified Yes/No Yes/No Yes/No
Subcontractor Attendance:
Subcontractor Value 4,561.60 Remarks
Subcotnractor is to
provide all protective
Gain/Loss -
clothing that is required
by the Statutory Health &
Safety regulations

% age 0.00%

Page 1 of 1

Вам также может понравиться