ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


(RP) (RP)

1.00 GENERAL CONDITIONS &


PRELIMINARIES
1.10
1.11 Contractual Requirements LS/ One 2.00 00.000.000 110.000.000
First mobilisation and demobilisation of all Team
construction plant, machinaries, manpower
and equipment necessary to complete the
1.12 whole Works. LS/ One 7.00 0.000.000 30.000.000
Mobilisation and demobilisation from one Team
location to other location exceeding 000m
of all machinaries, manpower and
equipment necessary to complete the
whole Works.
1.20
1.21 Specifed Requirements (Upon Request) LS 1.00 700.000 700.000
Preparation of Progress Report and
1.22 photographs LS 1.00 700.000 700.000
To prepare Shop Drawings and Construction
1.23 Drawings during Construction Period LS 1.00 700.000 700.000
To prepare As Build Drawings after
Construction Period
1.30
Traffic Safety and Control (Traffic
1.31 Management Service) Month 1.00 00.620.000
83.430.000
Traffic safety and control as specifed in
specifcations, drawings and standards,
using Rubber cone.
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
(RP) (RP)

2.0 PAVEMENT WORKS

2.10 Planning and cut down of existing


bituminous pavements using Cold Miling
Machine
2.11 To milling, planning and cut down of Cu.m 2,639.00 000.000 1.319.000.000
existing bituminious pavement using Cold
Milling Machine to 00 mm thickness
including dispose from location of works to
disposal area inside Cikopo-Palimanan Toll
Road, including removal of ''key-in'' joints.
2.12 Rock Excavation including dispose from Cu.m Rate Only 400.000 400.000
location of works to approved dumping area
Amount to be return to EP-NRC JO
2.13 Disposal of Scrap Material to dumping area Cu.m 2,639.00 42.807 -113.100.000

2.20 Bituminous Prime Coat and Tack Coat


Supply and lay Bituminous Prime Coat Sq.m 9,900.00 16.000
2.21 108.480.000
(Grade MC-70 or RC-200)
Supply and lay Bituminous Tack Coat (Grade Sq.m 22,030.00 10.000
2.22 220.300.000
RC-200)

2.30 Asphalt Treated Base Course


Supply, lay and compact Asphalt Treated Cu.m 1,486.00 2.100.000
2.31 3.194.900.000
Base Course (Include Asphalt Cement)

2.40 Asphaltic Concrete Binder Course (AC-BC)


Supply, lay and compact Asphaltic Concrete Cu.m 063.00 2.000.000 1.430.600.000
2.41
Binder Course (Include Asphalt Cement)

2.00 Asphaltic Concrete Wearing Course (AC-WC)


Supply, lay and compact Asphaltic Concrete Cu.m 090.00 2.700.000 1.622.000.000
2.01
Wearing Course include Asphalt Cement

2.60 Road Marking


Supply and apply refective thermoplastic Sq.m 393.00 230.000 90.390.000
2.61
Road Marking (White), Type - A (White)
General Application, t = 3mm
Supply and apply refective thermoplastic Sq.m 101.00 330.000 49.830.000
2.62
Road Marking (White), Type - B1 (White)
General Application, t = 3mm
Temporary Road Marking (White), Type - A Sq.m 393.00 180.000 70.740.000
2.63
(White) General Application
Temporary Road Marking (White), Type - B1 Sq.m 101.00 30.200.000
2.64 200.000
(White) General Application

2.70 Concrete Pavement and Portland Cement


Portland Cement Kg 26,400.00 1.300 34.320.000
2.71
Concrete Pavement, K-300 Cu.m 200.00 300.000.000
2.72 1.700.000
Supply and Lay Plastic Cor Sq.m 3,870.00 9.000 36.908.000
2.73

TOTAL TENDER AMOUNT CARRIED TO


SUMMARY OF TENDER PAGE SOT/1 8.736.748.500