Christine JAUFFRET
EUROCRYOSPACE, FRANCE
CHRISTINE JAUFFRET
Brief bio
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 2
EuroCryospace:
Air Liquide & ArianeGroup company
Business: manufacturing of cryogenic tanks and associated
equipment for the Ariane 5 launcher
Customers:
Satellites
operators
Creation: 1988,
Turnover: ~ 50 M€
Employees: 160 persons
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 3
EuroCryospace – Les Mureaux
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 4
Activity
ESC
Cryotechnic
upper
stage H2 tank
and lines 53m
EPC
Cryotechnic
main stage
tank and
lines
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 5
EPC tank manufacturing process
Welding
Insulation
Equipment integration
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 6
The initial context:
not enough rockets
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 7
Initial context: major changes
in the external and internal context
The answer of Ariane 2015 - A5ME shutdown & launch of the A6 program. New business
towards competition strategy
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 8
Reminder:
5 Focusing steps
Easy to do in production
1. IDENTIFY the system's constraint(s) but not in projects
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 9
Breaking the constraints
one after the other
■ The bottleneck changed many times during the project because of
the improvements made on each successive bottleneck
Bottleneck 3:
X-Ray control of the
Bottleneck 2: lines
Incoming quality
inspection
Bottleneck 1:
Welding machine for
the tank
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 10
Bottleneck 1:
The EPC tank welding machine
■ Welding machine identified as the first bottleneck.
■ Takt time around 38 days vs a requested 27 days Takt to deliver
8 ranks / year Temps d'écoulement des réservoirs EPC par atelier Date de la dernière
mise à jour :
25/01/2018
60
RN (hors C4)
50 48
Timbrage/étanchéité/ressuage
46 46
ISO
43 EQT int
EQT ext
40
37 Takt Time Cad. 8
35
34
Nombre de jours
33 33
32
31
31
30 30
30 29 29
28 28 28 28
27 27 27 27 27 27 27
25 25 25
24 24 24 24
23
23
22
20
20 19
18
37
14
13 28
25 26 25 25 25
23 24 23
10 20 21 20 20 20 20 19 19
17 16 17 16
15 15 15
13 13 12 12
10 10 11 10 10 11 10
9 8 8 8 7 7
31 30 33 71 28 45 43 52 35 33 30 42 32 61 26 24 27 28 30 28 27 28 26
0
R582 R583 R585 R586 R587 R588 R589 R590 R591 R592 R593 R594 R595 R596 R597 R598 R599 R600 R601 R602 R603 R604 R605
Réservoir EPC
Fréquence de mise à jour :
Porteur : MILCENT S. Chemin d'accès : \\jonas\Amélioration_Continue\0-commun AMC\03 - Suivis & indicateurs\032 - Suivi RIE\ 3-suivi global EPC (Goulot) mensuelle
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 11
Applying the Critical Chain principles
on the welding machine
■ Use of a mascot to facilitate the
communication and increase
efficiency between production
and control operations
Critical!
Do not disturb
this operation
Initial process of welding Switching time
Buffer
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 12
Critical Chain + Lean
To improve performances
■ First step: a workshop observation in order to analyse the real
"focused duration" of each task
■ Second step: the planning of operations was reduced
from 38 days to 27 days (22 days + 5 days of buffer)
■ Tanks schedule execution monitored with a Fever Chart
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 13
Results: a huge increase
in speed and productivity
■ Welding machine Takt Time reduced
from 38 days in 3 shifts to 27-28 days in 2 shifts
CCPM - welding
8 EPC welded
during a year
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 14
Bottleneck 2:
Incoming Quality Inspection
■ The work-in-progress in the inspection area went from 1000
packages (Quality Orders) to less than 200 in 6 weeks
■ To absorb the WIP in the incoming quality inspection area
Performance CQR
150
The WIP reduction has reduced the stress level of the team
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 15
Bottleneck 3:
X-Ray control of the lines
■ 130 lines in progress in the workshop
50 waiting for the X-Ray control
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 16
Throughput increased by 25%
Throughput 2016:
6 6 8
6 7,5 8
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 17
Conclusion
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 18
Any Questions ?
www.tocpractice.com 38th International Conference of the TOC Practitioners Alliance - Paris - TOCPA 19