Академический Документы
Профессиональный Документы
Культура Документы
ISSN No:-2456-2165
Abstract:- An AGC maintains the frequency of the system demand will go as the error input to the controller in the
by balancing the active power generation to the load respective system called as the Area Control Error (ACE).
demand. The frequency of the system is dependent on the Every time the controller takes the corresponding control
active power supply of the system according to the load action and maintains the frequency and the tie-line power in
changes. A conventional PID controller is generally equilibrium such that the ACE will become zero and hence,
employed to achieve AGC. However, proper tuning of the change in the frequencies and the tie-line power becomes
controller parameter is required in order to achieve zero and the system will be stable (2).
satisfactory controller performance. So, the proper choice
II. PROBLEM FORMULATION
of design objectives and the tuning method play very
important part in AGC. In this work, a PID controller
As we know that the effectiveness of the AGC
with derivative term is tuned to control the frequency and
depends not only on the controller, it also depends on the
tie-line power deviations of a two-area non-reheat thermal
objective function chosen in the problem statement because if
system using Ant Lion optimization (ALO) algorithm.
we chose a wrong objective function, even if the optimization
ALO is an efficient optimization algorithm which is based
technique is good it cannot deliver good results. We can
on the behavior of ant lions. For optimization purpose, the
choose the change in the frequencies in the interconnected
fitness function is formulated by considering settling times
of deviations in frequency and tie-line power deviations areas i.e., f1 (change in the frequency in area-1) and
and the integral errors. Four different cases of load f 2 (change in the frequency in area-2) and the Ptie (change
perturbation conditions in both areas are considered. A
comparative assessment of the proposed controller is in the Tie-line Power change), if it is a two area system, as the
carried out with PSO based controller and the obtained objectives to be minimized. These changes (errors) can be
results are tabulated. Time-domain simulations are carried converted into numerical values by converting these error
out to further establish the superior performance of the signals into the Integral of Squared Error (ISE), Integral of
proposed controller. Time multiplied Absolute Error (ITAE), Integral of Absolute
Error (IAE), Integral Square Absolute Error (ISAE) etc., and
Keywords:- Automatic generation control; Ant lion depending on the application and interest we can choose any
optimization; Particle swarm optimization; PID controller; of these error determination techniques, Here in our
multi-area interconnected system. application we have chosen the ITAE as the error criteria
because it gives the clear picture of the variation of the error
output with respect to time and the integral action of ITAE
I. INTRODUCTION
ensures that the integral of the frequency and tie-lines errors
The main objective of electric utilities is to supply of are minimized and time multiplier makes certain that the
reliable power with acceptable quality of power, and the main settling times in these deviations are minimized .
challenge lies in maintaining the equilibrium between the
generation and the supply (1). Because if there is no As the formulation of the objective function should
equilibrium between generation and the supply the whole be selected very carefully, in our work we mainly concentrated
power system may collapse due the mismatch of frequency
on decreasing the settling times of f1 , f 2 , Ptie of line and
between the interconnected system. Automatic Generation
Control (AGC) involves the real and the reactive power also the ITAE of these changes due to changes in the load.
control in it, reactive power control involves the Automatic Here, we should simultaneously achieve two objectives.
Voltage Regulation (AVR) and the real power control involves Hence, we can formulate our problem as the multi-objective
the load-frequency control (LFC) or AGC. Multi-area power problem. This multiple objective problem can be formulated
system is generally an interconnected system and in such into a single objective problem, by giving certain weights to
interconnected systems maintaining the change in frequencies each individual objective to be met. In this work, half of the
in permissible values in the interconnected areas due to the weight is given to the sum of settling times of the frequencies
change in the load demand is done by the AGC system. AGC and tie-line power deviations and other half of the weight is
does this by changing the set-position of the generators for the given to ITAE error of the deviations of the frequencies and
corresponding change in the load and this change in the tie-line power deviations.
J W1 J1 W2 J 2 (3)
Where W1 W2 0.5 Fig 1:- Block diagram for a two-area non-reheat thermal
system.
The constraints to the problem are the minimum and A. Modelling of the Load Frequency Control Block
maximum value of the controller coefficients defined as Diagram
K pmin K p K pmax The complete Block diagram of the load frequency
control of an isolated power station is shown in the Fig 2.
Kimin Ki Kimax
(4) Now the deviation at the output for corresponding
K dmin K d K dmax
change in the load PL is shown in the Fig.2, the open
n min n n max loop transfer function of the figure is given below.
PL ( s)
III. PROPOSED WORK
Pref ( s) Pg 1 PV 1 Pm 1
( s)
A two-equal area interconnected system with two non- 1 g s 1T s 2Hs D
reheat thermal plant with individual area rating of 2000MW Governor Turbine Rotating m ass
with a nominal load of 1000MW in each area is shown in and load
Fig.1 1
R
The two area system shown in the fig.1 consists of a
governor, turbine, and a generator each, and each area has Fig 2:- Block diagram of the load frequency control of an
three Inputs and two outputs, error output from the controller isolated power station.
(denoted by u1 , u2 or Pref 1 , Pref 2 ), change in the load
1 1
(denoted by PD1 , PD 2 ), change in tie-line power (denoted KG(s) H (s) (7)
R (2HS D)(1 g s)(1 T s)
by PTie ) are the inputs and the change in the frequencies in
the two areas (denoted byF1 , F2 ) and the area control The closed loop transfer function relating the change in
the frequency to the change in the load is,
error (denoted by ACE1 and ACE2 ) are the outputs of the
( s) PL ( s)T ( s) (9) The PSO algorithm mainly consists of just three steps
0 Kp 2
0 Ki 2
(17)
0 Kd 2
100 n 500
(5.1)
Following section discusses various case scenarios of the
simulations.
C. Test Cases
The case scenarios taken in this work are step load
changes in both areas. First set of cases consists of load
increase in one area with no load changes in other areas
whereas second set of cases consists of load decrease in one
area with no load changes in other area. The tabulated results
present the simulation results of the studied system. In all Fig 3:- (A) Frequency deviation of Area 1 for Case 1
tabulated results, the minimum value obtained for objective
function and the tuned numerical values of the controller
parameters (i.e. K p , K i , K d and n ) along with settling
times of frequency and tie-line power deviations and minimum
ITAE are presented
Fitness
Function J 1.3349 1.2452
Value Fig 4:- (B) Frequency deviation of Area 2 for Case 2
1.3433 0.6458
Kp
Ki 1.2177 1.4416
Controller
Parameters 1.6443 0.3489
Kd
n 414.4374 282.7629
5.7832 3.0856
f1