Академический Документы
Профессиональный Документы
Культура Документы
INTRODUCTION
1.1 General
Constrution is a very challenging process where each and every activity plays a
crucial part leading to successful termination of project, since the project undergoes
various process and addition to volatile risks maximum projects are either delayed or cost
overrun due to improper management of project. The project from its starting stage to the
termination state i.e the final stage is to be managed in a well organized manner, with the
various mechanization and technological developments the best options are to be made
for the project for optimal usage of resources and to complete the work as per the baseline
provided. Highway projects are very crucial construction process where the frequent
challenges are faced during the construction of a project from technical to non technical
issues, such as change in profile of road to the legal issues such as partial land clearance
hence it is very important to manage the completion and delivery of project in time, hence
project management palys a very important and crucial part in construction process.
Various project management softwares such as Primavera and Microsoft project are
developed to manage the project in a organized manner, which allows tracking of project
1.2 Project
the production of unique product. A project has a definite, start and end date. Two
projects,are not same in nature. Every project has specificcfeatures. The choice of
a set of activities arranged in a hierarchical order with specific start date and end date.
activities of project. Projects management helps to arrange and link tasks, materials and
resources available in the project so as to meet goals and objectives of the project within
work of the project. The project is performed by the group of peoples. A number of
No matter the size of the, project is small or big, it should be completed under 3
constraints. The project constraint in every project gives competition with another project.
The main aim or goal of the project is to deliver a quality project within the constraints.
a) Scope: - It involves work to be done, the uniqueness of results or, the product
c) Cost: - It involves the overall cost or budget of the project required to finish the
d) Quality: - The excellence of the service or product required to satisfy the need of
e) Risk: - It involves the uncertainty situation that takes place during the project
tools. This process determines the work activity timings which identified in the process of
planning and finally it shows in the schedule of project. “Scheduling is a sequencing and
arrangement of each activities with the graphical representation required to complete the
work”.
• Defining interval of time in each activity i.e., when to start and finish
Activity is nothing but tasks or work involved and performed from beginning till
the end of the project. The completion of the project within the planned duration and
on top of the arrow and the duration required for the completion of that task or work
1.6.2 Duration
Duration is the time required to achieve the goals or objectives of the project. It is
the numeral of days or months required to complete project right from start of project to
which require longest time to complete the project. It is a network based method for
1.6.3 Event
Event is nothing the starting or beginning of project. It indicates the start of, a
project and also some of the major tasks involved in the intact project. Each major event
1.6.4 Milestone
It is a chart which is alternative to the bar chart. The activity contains some key
events for completion of activities such key events are called milestones. It is represented
objectives or goals of the project. WBS splits the work implicated in the project so as to
execute the work or task added efficiently and professionally. WBS helps to keep a track
on each activities and identify to overcome the uncertainties that takes during various
stages of the execution. WBS divides the major activities involved in project into sub-
activities so that the project is completed within the anticipated cost and time
(Seetharaman, 2003).
1.6.6 Resource
Resources are labours, equipment’s and materials which are required to complete
the activities of the project. Many activities require one or more resources to complete.
Network represents the link -between the activities and their mutual dependency.
dependent activities. The network logic reflects the timely completion of the project
successor event to that event. In figure 1.4 shows the successor events for 2 are 3, 4 and 5.
Any event which is completed or which occurs sooner than a particular event is
known as a predecessor event to that particular event. In figure 1.4 shows the predecessor
1.6.10 Critical-Path
The highest path in a network map is known as critical path of a project. Critical
path joins the activities of,a project which consume longest duration. The critical path is
also defined as the path which joins activities with longest duration. It represents and
joins the activities or events that are critical so that those events and activities can be
taken care. In PERT, the critical path is the one which joins events with zero slack
whereas in CPM, the critical path is the one which joins the events or activities with zero
1.6.11 Tracking
activities and comparing it with the planned schedule is known as tracking. It is one of the
major tasks that will be performed to know the progress of the work, whether the tasks
circumstances. Tracking also helps to know the delay of time and duration of project and
guides the managing team to take necessary actions to complete the project within the
scheduled time and cost. Planning is done before the execution of the project whereas
sector, the project mainly focuses on optimum resources usage and speedy completion of
the project. It is one of ther most important concept in construction project administration.
If labour management is effective, the project will be complete in time with the quality.
• Labour availability
• Climatic conditions
• Accessibility of site
Primavera is a project management tool founded by Dick Faris, Joel Kopplem and
Les Seskin. It was launched in 1983, the software is handed to the oracle in 2008.
executing, controlling and monitoring in a good way. For enterprise project management,
it is a multiuser tool. It provides information of all the task in the enterprise. Primavera is
a enterprise server/client, web enabled and desktop software which gives satisfaction to
the requirements and needs. It has each feature a management needs to have control of in
a project from begin to finishing of project. The software can analyze what attributes
project needs ,to complete the project in time and saving both time and cost.
Fig 1.6 Primavera P6
management software
ii. To identify the activity definition, sequencing of activity and estimating the
duration for specific activities on the basis of quantitative method, to estimate the
determining plan with risk assessment and then apply the control measures for the
particular risks
iv. To study the planned schedule with the current status of project and to track the
vi. To apply the project management skills with the use of Primavera software and to
Project management concept is very important to lead the project very efficiently
and effectively. Scheduling, tracking and risk management are very complicated in any
executed effectively towards achieving the primary goals. Primavera software is used to
prepare the project schedule which can give the project completion date and information
about the activities and assign the resources required for every activities. Project
schedule can be prepared effectively as this software can provide what are the risks and
problems that occur during each and every activities of the project.
CHAPTER 2
7 Associate EPC Contractor M/s Modern Road Makers Pvt. Ltd., Mumbai
where the section - 1 is located at Karwar where our project wok location of Twin Tunnel
is situated, the twin tunnel was proposed as the existing road contains steep mountain and
dangerous curves, since the mountains are of hard granite and igneous rock since the new
route saves the time and cost of construction with avoiding dangerous curves. The new
route was proposed actually by cutting method, since the mountain top consisted a ancient
DC bungalow which is a heritage building alternate method for road was proposed, that is
The Organization is divided into various function and responsibilities, CGM is the Chief
General Manager of the organization who controls the overall project, under CGM
various level of managers are assigned so as to divide the work load and responsibilities
M1 denotes the manager at a perticular package i.e section 1 ,and M2 denotes the section
2 manager and M3 & M4 are section-3 & section-4 managers respectively, where each
manager is having control on the Design ,the accounts,HR and stores of their respective
section.
Below flow chart shows the organization structure of the project by IRB Infrastructure
Ltd.
level plays a very important role, the organization structure at site level consist of the
Project manager and various level of engineers from senior level to the junior level and
supervisor to guide the work to labours to execute the work and keep going progress.
LITERATURE REVIEW
Planning is a base for each and every work in management field. It serve as base for
executing, monitoring controlling and closing. When quality time is spent on planning, it
will fundamentally minimize the time spent on execution. Planning manages figuring out
a future strategy and choosing ahead of time, the most suitable course of activities for
when to do and how to do. It gives an idea about where we are and where we need to be.
It is a bridge between present and future course of action. Thus planning is nothing but
think before it is executed. Planning is a systematic/orderly thinking about way and needs
helps in avoiding instabilities, confusion, delay of work, unexpected risk, wastages etc.
projects for reducing and controlling delays of project. extensive amount of time, money,
resources are wasted each year in a construction industry due to inappropriate planning
and scheduling. With globalization, the construction project have become gigantic, and
complex. preparation of such require huge amount of paper exertion, which can be
reduced with the aid of project planning software. Providing high-quality planning,
This paper deals with some high probable parameters in Primavera software.
Results of this study show drawbacks of present project management system in station
work project and the efficient planning, as well as the necessitate and usefulness of a
An analysis of the results of survey and comparison of conventional method and using
Primavera, a management tool was undertaken. Primavera software has been selected
because of its comparable and optimum project plans to stimulate the adjustments. The
wide acceptance of this software, especially in industries of developing cities has made
the project managers to easily handle the large projects effectively and also resulted in
results indicate that this management tool has many features and benefits to lead to a
successful project completion. It has been studied that professional project schedulers use
Primavera to plan and analyse multiple projects to ensure the timely completions and
within budget. It must be noted that this study is based on, comparison of relatively small
projects and that results on larger, more intricate projects might be diverse.
Efficient time planning is very vital in determining a success of any project. Thus,
without proper time controlling will cause project delay and consequently budgeted cost
overrun. In this project, VOC port trust of Tuticorin is considered. It had only four lanes
which were not sufficient to bear the traffic. For this purpose an alternate arrangement of
a six lanes is constructed. The work carried out was not done by proper planning,
scheduling and resource allocation. So, that the resources were wasted and the time was
extended. For reducing this wastage in time. It can be done by using the primavera p6
software. In this project, the planning, scheduling, resource allocation, cost and time
management were of done by using primavera P6 software. This software improves the
quality of construction with as per stipulated cost and time. Finally implementation of
Paper concludes that time management structure is considered to perform a keys role in
organization, which is responsible to complete the project in a accurate time, budget cost
within a certain period of time. Poor- time and cost performance are major problemsa
faced by today’s construction industry. The main idea of this project is to prepare the
proper planning and scheduling for the 6 lanes road work construction at VOC PORT
TRUST, Tuticorin. Time management and time control are done by primavera P6
software. The main advantage of project was timely execution and completion of the
project using primavera P6 software. The road construction project has completed prior to
Planning, scheduling and required quantity of resources with regular tracking is very
important any construction projects to reduce delays of the project. Due to improper
of time and resources is wasted with this desired goal is not achieved. In the present work,
study is carried out on residential (G+2) villa. This study covers the process of planning,
scheduling, tracking and controlling of activities. The software used for this study is
primavera p6, this tool is utilized throughout from planning phase to tracking and
regularly, for this, baseline have been managed for similarity between the planned
progress and actual progress by primavera software for proper recognition of problem
which cause deviation. Many uncertainties occur in practical work leads to delay. By
using software techniques, applying resource dependency, rescheduling of the project by
crashing and fast tracking of critical activities overcome the delay duration.
Results showed that Regular monitoring of the work under execution must be done at
least within week in order to take adequate actions against uncertainty, In this project by
applying crashing and fast tracking method duration of selected events is reduced to
proved to be a better tool for scheduling, monitoring and controlling and shows its
efficiency in providing best results with less effort of user by preventing enormous
volume paperwork
CHAPTER 4
METHODOLOGY
As the name indicates, pre data collection means it’s a collection of a data or
Collecting the data from the various studies, previous project after collecting the
data it is maintained in the form of statement and set objectives required for project
in the form of literature review and set objectives required for the project inform of
problem statement. It also deals with what works has to be done with what data collected.
In this stage data of site, estimation of materials required, manpower, equipments’ are
collected.
In this stage data are collected by visiting the site regularly and by identifying
construction sequence. In this stage the data are collected in the form of:
Making comparisons
Daily progress report - The DPR ensures daily progress report that is detailed
description of work done and number of labour and quantity of resource required for the
Work output for labour - This gives a detail of the amount of work done by one labour
(person) in one day. Thus useful in calculation number of days or hours required to
complete the activities and also to ensure how much manpower required on site.
Comparing - the actual duration with planned duration-The data collected from daily
progress report and work output for labour will give an idea of actual duration and it can
This stage is a software part. In this stage the data which are collected from pre
data collection and data collection are analyzed in primavera software. Tracking of
developed by Henry Gantt & Fredric Tailor and can be acknowledged as systematic
technique of project planning. The technique uses, horizontal lines representing time
length of a task achievement for planning and task names are written vertically in break
up columns. each rod is place in front of every task and chart shows starting date,
accomplishment time length and finishing date of tasks (Berch & Grad nitzki,1992)
Benefit of Gantt Chart: Gantt charts have gained wide recognition and attractiveness
theorys or complex calculations are involved. any person can understand them. Gantt
for carrying out a construction project by looking a bar chart than by looking at a
schematic of logic network. The initiation of the critical path method ( CPM ) and the
evolution of commanding computers, Gantt chart did not exceed away or lose importance.
Instead, they evolved to a different supporting role that made them more valuable and
important.
Solitary of major, network scheduling methods which have been used in construction
industry is CPM ( critical path method ). This method involves the use of a geo metric
depiction of flow chart, which depicts the precedence between activities. The critical path
method ( CPM ) is a duration - driven technique in which the fundamental inputs are
project activities, their durations, and dependence relationships. The CPM formulation
assumes that resources are not constrained in any sense . Use of network techniques and
CPM by construction companies has reached a steady level after the zealous boom of
early 1960‘s. Computer programmers eliminate the need to arrange network, but the
personnel.
When comparing bar charts with networks, Three advantages over bar charts:
Network show logic, the interaction among the activities. Bar charts do not
Networks can estimate, or predict, the completion date of the project, or other
4.3 SCHEDULING
and deliverables, usually with anticipated start and finish dates. A schedule is regularly
used in the project planning and project portfolio management, partss of project
ANALYSIS
Analysis involves the schedule of project prepared by using the Primavera P6 and
it will give the vision for a project and complete in a planned duration within economy
duration, estimating the resource required and schedule development for an activity
To generate an model schedule for any project, first footstep is to accumulate data
available for project. consequently the following steps can be followed in Primavera.
Create a composition of a company with its branches which is executing the project. This
Subsequent to the EPS, OBS is created, which is hierarchy, that reflects the persons
5.2.4. Calendar:
The job is conceded out in 6 days per week. So as standard 6 day workweek calendar is
made with necessary holidays in it. A break of one hour is given in the afternoon.
5.2.5. Create new project:
A project is a set of action and linked in sequence that constitutes a plan for creating a
product or service. The project is produced under respective division in the EPS and
assigned in the person charged form OBS to it. The project can be given intended start
and must finish dates. The project is assigned a calendar which can be global, resource or
project calendar.
WBS is a chain of command of work that must be proficient to complete the project. Each
project has its own hierarchy, with apex level WBS element begin alike to that EPS
nodes. WBS element may enclose more detailed WBS levels, activities, or both.
Activities are essential work elements of a project and form and from lowest level of a
distinctiveness like ,Activity ID, nname, start and finish dates, activity calendar, activity
assigning preceding and succeeding activities with significant relation to the activities.
Finish-to-start, ( FS ) relationship.
Finish-to-finish, ( FF ) relationship.
Start-to-start, ( SS ) relationship.
Start-to-finish, ( SF ) relationship.
Fig 5.0 showing Relationship between activities
When grounding the work, the period is entered in original duration field. The actual
interval can only be entered for the activties, which are completed.
The subsequent are the types of activity dates available in the primavera. actual start,
The activity cost is the addition of all the expenditure incurred to complete activity.
A simple baseline plan is a complete copy of the original schedule which provides a
If the project is not progressing as planned many activities are starting out of
sequence, actual resource use is greater than planned use. and then update should be
Most projects contain some activities that progress as planned and some which do
not. In this case, the best means is to merge the two updating methods.
5.2.14 Tracking
types of layouts such as labour costs, project cost, resource forecasting, resource
5.2.15 Earned-value;
Earned value is a technique for measuring project performance according to both project
cost and schedule. The technique compares budgeted cost of the work to the actual cost.
The claim digger is a schedule scrutiny tool that enables a company to produce a report
that compares chosen data fields in a revised project and a equivalent baseline.
Project threshold consist of parameters assigned to WBS elements, they are used to
Project issues are the problems within schedule that have to be addressed before project
The Figure below provides the Enterprise Structure of my Twin Tunnel Project , Where
responsibilities
carried out one by one. It gives the practical and desirable schedule, and it is very
In order to develop the tools and techniques which are used to activity sequencing
It is a technique used for making of a schedule model using logical relationship, activities
are denoted by nodes and arrow or lines are graphically linked activities with logical
performed. Hence this method is also known as Activity on Node (AON). This technique
3. Start-to-Start (SS) : In this relationship predecessor and successor activity. Both start
at same time.
During preparation of the network diagram using precedence diagram method, an activity
forced by the construction method. During the process of activity sequencing project
preferred result from this method. These dependencies are defined on the basis of past
3. External dependencies: In this type dependencies, the project team have not
controlling, when the non-project activities are forced to starting the project activities.
4. Leads and lags: This method is used to apply the relationship between the activities
From the above processes the results are obtained and implemented in Primavera
software.
The fig 5.4 shows activity sequence and 5.5 order of sequence in Twin Tunnel project
properly so that the project is completed successfully.resource required for each activity
The following tools and technique which are used to estimate the resource required to
This involves to find out the best method among the alternative available to perform a
particular task. It is very important to analysis all the alternative methods available to
perform a task so as to choose best one. It also helps to study the nature of the activity
regarding various activities involved in the project and resources required for the
This process is to collect the information on project scope and resources availability for
project.
The following tools and techniques which are used to estimate the duration of project
and also estimate activities start date and end date in Twin Tunnel Highway project.
i. Parametric estimating
In this technique it easier, accurate and estimate the duration of activities based on the
past work of the project historical data. In this process quantity of work and productivity
The following above details obtained using to develop schedule for Twin Tunnel
Highway project by using Primavera P6 and critical path method to develop schedule of
project.
In critical-paths method using activities, duration and dependencies, it will analyze the
greatest path in planned activities to end of project. It is also used to calculate the float of
each activities. Float point means without charging in completion date of project activity
can be allowed delay or lagging in duration. The Fig 5.7 shows the network diagram of
critical path method in which indication of series red arrows the critical path method.
Fig
Fig. 5.7 Network Diagram using CPM
RESULT
The Project was aimed to study the behavior of construction at site and comparing its
actual schedule with the planned schedule, where the construction of tunnel is very
challenging since the risk involved in construction is volatile and hence a very careful
construction of project, the profile of rocks found in tunnel is confirmed by Geologist and
rockbolting of tunnel surface is decided, and there has been no collapsing of rock inside
the tunnel due to robust rockbolting mechanism and removal of excess stones or cracked
The Tunnel construction was started by opening face of the tunnel by excavation and
blasting process, started in 2014 november, RHS Tunnel was started on november 2015
and the LHS tunnel was started on march 2016. The length of RHS tube is 287m and the
length of LHS tube is 267m. The progress of tunnel construction is considered by running
meter length, hence as per study LHS Tunnel is lagging behind the schedule from over
30% due to local issue and lack of resources i.e blasting material supply, which will be
sorted out soon, as the tunnel construction is done parallel, blasting requires staggered
sequence, as the RHS tunnel was first opened ,after 50m of completion of RHS tunnel
LHS tunnel was started. Due to blasting material supply shortage there was few days lag
in schedule,as the risk was calculated one the schedule can be recovered with excess
working hour and excess blasting, as the local community resides nearby the project
location the blasting sound and certain muck flowed along the path towards the houses
nearby even after strict safety precaution there is panic in surrounding location since this
is an uncalculated risk the work keeps getting paused and which lead to lag in schedule of
hours and working in non working days of the company, a good strategy to complete the
project on time
Figure 6.3 and 6.4 showing creation of calender for twin tunnel project at KKBOT
CONCLUSION
The main purpose of this study was to comprehend the part of scheduling and appropriate
work and also to identify precise problems arising during the process. Results of this
study show the drawbacks of present project management system in project and
The conclusion made from the result of this study are as follows
1. Project management software like Primavera helps to plan, schedule, monitor and
control the activities involved in the construction project more effectively and
efficiently.
4. Helps Track the project and keeping update on project which helps in maximum
5. Project Management software help in replanning and mitigate the uncertain events
Earned value analysis and cost management can be done for the present work.
Risk management can be done to identify the risk involved in this project.
REFERENCES
1. Schedule and resources optimization using Primavera in Metro rail project by T.Siva
Nagaraju, Sri Lakshmana Kumar, International Journal of Mechanical And Production
Engineering, Volume- 4, Issue-7, Jul.-2016 , ISSN: 2320-2092
2. Project Monitoring and Control using Primavera, Andrew Fernans Tom1, Sachin
Paul2, International Journal of Innovative Research in Science, Engineering and
Technology Vol. 2, Issue 3, March 2013
5. Planning, Scheduling and Time Management of Six Lanes Road Construction Work at
V.O.C Port Trust using Primavera P6 Software, P. Esakki Thangam, R. Magdalene
Benila, IJSTE - International Journal of Science Technology & Engineering, Volume 2 ,
Issue 11 | May 2016 ISSN (online): 2349-784X