LSP MATERIAL STATUS UPDATED ON 18-03-2018

Si No ID Title Status THRDNSHB Remarks

1 - Light Supports Approved Delivered

2 107 Light Fixtures Approved Delivered

3 106 Passive Infrared Movement Sensor (PIR) Approved Delivered

4 176 Fire Resistant Approved Partial Qty Delivered work stopped due to non availiblity

5 108 Wiring Devices (including Switches & Sockets) Approved Partially delivered

6 181 Heavy duty socket outlet with plug Approved 3/7/2018/not delivered Awaiting Delivery

7 279 Isolator Approved Partial Qty Delivered

8 280 Cable gland, lugs & accessories Approved 20-Mar-18 Based on cable approval

9 278 Cable tray & accessories Approved 8-Mar-18 Previously committed on 20.02.2018

10 109 LV Distribution Boards for small power & lighting 7-Mar-18


Under Dewa Review, Rev.0
MFC has been received from L &T. FAT
11 179 Distribution board for fire pumps Submitted Dated on , Awaiting 7-Mar-18
Planned 15/03/18 Notification
Approval
12 179 Distribution board for Aspiration System 7-Mar-18

13 87 DC Cables 15-Mar-18 At port.

14 HVAC Power cable Material Submitted

15 Control Cable Material Submitted


LSP MATERIAL STATUS UPDATED ON 18-03-2018

Si No ID Title Status THRDNSHB Remarks

16 111 GI Conduit & Accessories Approved 90% Delivered

17 175 PVC Conduits & Accessories Approved Delivered

18 107 High Bay Lights Approved Delivered

19 277 Flexible Metallic Conduit & accessories Approved Delivered

20 110 Wires & cables for for small power & lighting Approved 90% Delivered

21 110 Brown Wire Approved 5-Mar-18

22 176 Heat Resistant Cable Approved 70% Delivered

23 276 GI trunking & accessories Approved Delivered

24 281 Junction box / enclosure Not Yet Submitted Not Yet Submitted Submission Date