PRESUPUESTO BASE
ITEM DESCRIPCION UD. MET. P.U. P.P.
0.00.00 REFORZAMIENTO CERCO PERIMETRIRCO
1.00.00 OBRAS DE CONCCRETO ARMADO 22,351.02
1.01.00 SOBRECIMIENTOS -
1.01.01 CONCRETO EN SOBRECIMIENTO F`C=175 KG/CM2 M3 21.14 325.70 6,885.30
1.01.02 ENCOFRA. - DESENCOF. DE SOBRECIMIENTO M2 241.05 36.54 8,807.97
1.01.03 HABILITACION Y COLOCACION DE ACERO EN SOBRECIMIENTO KG 1,237.50 5.38 6,657.75
1.02.00 COLUMNAS 54,377.16
1.02.01 CONCRETO EN COLUMNAS F`C= 175 KG/CM2 M3 31.08 361.68 11,241.01
1.02.02 ENCOFRA. - DESENCOF. ENN COLUMNAS M2 511.06 45.49 23,248.12
1.02.03 HABILITACION Y COLOCACION DE ACERO EN COLUMNAS KG 3,696.66 5.38 19,888.03
1.03.00 VIGAS 19,611.99
1.03.01 CONCRETO EN VIGAS F`C= 175 KG/CM2 M3 14.78 398.27 5,886.43
1.03.02 ENCOFRA. - DESENCOF. EN VIGAS M2 152.09 44.00 6,691.96
1.03.03 HABILITACION Y COLOCACION DE ACERO PARA VIGAS KG 1,307.36 5.38 7,033.60
-
-
-
-
COSTOS DIRECTO 96,340.17
GASTOS GENERALES (9.2%) 8,863.30
UTILIDAD (8.5%) 8,188.91
SUBTOTAL 113,392.38
IGV (18%) 20410.63
PRESUPUESTO TOTAL 133,803.01
RELA
INDICES
UNIFICADOS
47
47
47
04
05
21
21
02
03
02
02
43
49
48
39
INDICES
UNIFICADOS
02
03
04
05
21
39
43
47
48
49
SUMATORIA TOTAL
INDICES
UNIFICADOS
03
47
39
43
21
05
49
02
04
48
SUMATORIA TOTAL
k=1.00
RELACION DE INSUMOS
MANO DE OBRA
Operario H-H 902.37
Oficial H-H 767.55
Peon H-H 515.94
MATERIALES
ARENA GRUESA M3 36.11
PIEDRA ZARANDEADA DE 1/2" Y 3/4" M3 53.57
CEMENTO PORTLAND TIPO MS (42.5KG) BOLSA 179.69
CEMENTO PORTLAND TIPO I (42.5KG) BOLSA 389.81
CLAVO PROMEDIO CONSTRUCCION KG 145.60
FIERRO CORRUGADO PROMEDIO KG 6553.60
ALAMBRE NEGRO N° 08 KG 14.78
ALAMBRE NEGRO N° 16 KG 134.47
MADERA TORNILLO M2 3518.79
HERRAMIENTAS
VIBRADOR DE CONCRETO 4 HP 2.40" DM
MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 DM
COSTO DIRECTO DE OBRA
GASTOS GENERALES + UTILIDAD
SUB - TOTAL DE OBRA
RESUMEN
PORCENTAJE
ELEMENTO PRECIO
TANTO POR CIENTO
ACERO DE CONSTRUCCION LISO 1,223.63 1.09
ACERO DE CONSTRUCCION CORRUGADO 27,197.44 24.16
AGREGADO FINO 1,263.85 1.12
AGREGADO GRUESO 2,678.50 2.38
CEMENTO PORTLAND TIPO "1" 11,349.74 10.08
INDICE GENERAL DE PRECIOS AL CONSUMIDOR 17,052.21 15.15
MADERA NACIONAL PARA ENCOFRADOS 20,866.42 18.54
MANO DE OBRA ( INCLUYE LEYES SOCIALES) 30,923.08 27.47
MAQUINARIA Y EQUIPO NACIONAL -
MAQUINARIA Y EQUIPO IMPORTADO -
SUMATORIA TOTAL 112,554.87 100.00
INCIDENCIA
ELEMENTO
TANTO POR UNO
ACERO DE CONSTRUCCION CORRUGADO 0.242
MANO DE OBRA ( INCLUYE LEYES SOCIALES) 0.275
INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.152
MADERA NACIONAL PARA ENCOFRADOS 0.185
CEMENTO PORTLAND TIPO "1" 0.125
AGREGADO GRUESO
MAQUINARIA Y EQUIPO IMPORTADO
ACERO DE CONSTRUCCION LISO 0.022
AGREGADO FINO
MAQUINARIA Y EQUIPO NACIONAL
PORCENTAJE INCIDENCIA
SIMBOLO
ANTO POR CIENTO TANTO POR UNO
1.09 0.011 AL
24.16 0.242 AC
1.12 0.011 Af
2.38 0.024 Ag
10.08 0.101 c
15.15 0.152 I
18.54 0.185 Mn
27.47 0.275 Mo
0.000 Mqn
0.000 Mqi
100.00 1.000
PORCENTAJE AGRUPADO
SIMBOLO
(%) (%)
100% 0.00 AC
100% 0.00 Mo
100% 0.00 I
100% 0.00 Mn
100 80.91 c
19.09 Ag
0.00 Mqi
100 49.19 AL
50.81 Af
0.00 Mqn
100%
MANO DE OBRA
22.62 Operario ( 2.00 ) H. H.
22.62 Oficial ( 2.00 ) H. H.
90.27 Peón ( 8.00 ) H. H.
EQUIPO Y HERRAMIENTAS
S/. 51.16 VIBRADOR DE CONCRETO 4 HP 2.40* DM
S/. 213.09 MEZCLADORA CONCRETO TROMPO 8HP DM
COSTO TOTAL DE LA PA
MANO DE OBRA
127.76 Operario ( 1.00 ) H. H.
127.76 Oficial ( 1.00 ) H. H.
COSTO TOTAL DE LA PA
MANO DE OBRA
37.13 Operario ( 1.00 ) H. H.
37.13 Oficial ( 1.00 ) H. H.
COSTO TOTAL DE LA PA
MANO DE OBRA
49.73 Operario ( 2.00 ) H. H.
49.73 Oficial ( 2.00 ) H. H.
198.91 Peón ( 8.00 ) H. H.
EQUIPO Y HERRAMIENTAS
S/. 75.21 VIBRADOR DE CONCRETO 4 HP 2.40* DM
S/. 313.29 MEZCLADORA CONCRETO TROMPO 8HP DM
COSTO TOTAL DE LA PA
MANO DE OBRA
342.41 Operario ( 1.00 ) H. H.
342.41 Oficial ( 1.00 ) H. H.
COSTO TOTAL DE LA PA
MANO DE OBRA
110.90 Operario ( 1.00 ) H. H.
110.90 Oficial ( 1.00 ) H. H.
COSTO TOTAL DE LA PA
MANO DE OBRA
39.46 Operario ( 3.00 ) H. H.
26.31 Oficial ( 2.00 ) H. H.
105.09 Peón ( 8.00 ) H. H.
EQUIPO Y HERRAMIENTAS
S/. 35.77 VIBRADOR DE CONCRETO 4 HP 2.40* DM
S/. 148.98 MEZCLADORA CONCRETO TROMPO 8HP DM
COSTO TOTAL DE LA PA
MANO DE OBRA
121.67 Operario ( 1.00 ) H. H.
121.67 PEON ( 1.00 ) H. H.
COSTO TOTAL DE LA PA
MANO DE OBRA
39.22 Operario ( 1.00 ) H. H.
39.22 Oficial ( 1.00 ) H. H.
COSTO TOTAL DE LA PA
DE FORMULA POLINOMICA
IMINETOS F`C=175KG/CM2
Oficial Peon
2.00 8.00
METRADO: 21.14
230.39
0.5000 35.00 17.50
0.8000 50.00 40.00
8.5000 20.34 172.89
83.16
1.0700 15.89 17.00
1.0700 13.46 14.40
4.2700 12.12 51.75
12.50
0.0300 8.50 2.42
0.0700 144.07 10.08
COSTO TOTAL DE LA PARTIDA = 326.05
OFRADO DE SOBRECIMIENTO
Oficial
2.00
METRADO: 241.05
20.87
0.0400 4.15 0.17
0.1300 4.15 0.54
3.4000 5.93 20.16
15.56
0.5300 15.89 8.42
0.5300 13.46 7.13
Oficial
1.00
METRADO: 1237.50
4.44
0.0200 4.15 0.08
1.0500 4.15 4.36
0.88
0.0300 15.89 0.48
0.0300 13.46 0.40
NAS F`C=175KG/CM2
Oficial Peon
2.00 8.00
METRADO: 31.08
225.29
0.5000 35.00 17.50
0.8000 50.00 40.00
8.5000 19.74 167.79
124.53
1.6000 15.89 25.42
1.6000 13.46 21.54
6.4000 12.12 77.57
12.50
0.0400 8.50 2.42
0.0600 144.07 10.08
COSTO TOTAL DE LA PARTIDA = 362.32
OFRADO EN COLUMNAS
Oficial
1.00
METRADO: 511.06
25.93
0.0200 4.15 0.08
0.1700 4.15 0.71
4.2400 5.93 25.14
19.66
0.6700 15.89 10.65
0.6700 13.46 9.02
Oficial
1.00
METRADO: 3696.66
4.44
0.0200 4.15 0.08
1.0500 4.15 4.36
0.88
0.0300 15.89 0.48
0.0300 13.46 0.40
F`C=175KG/CM2
Oficial Peon
2.00 8.00
METRADO: 14.78
225.29
0.5000 35.00 17.50
0.8000 50.00 40.00
8.5000 19.74 167.79
152.56
2.6700 15.89 42.43
1.7800 13.46 23.96
7.1100 12.12 86.17
12.50
0.0600 8.50 2.42
0.1100 144.07 10.08
COSTO TOTAL DE LA PARTIDA = 390.35
OFRADO EN VIGAS
PEON
1.00
METRADO: 152.09
21.63
0.0300 4.15 0.12
0.1800 4.15 0.75
3.5000 5.93 20.76
22.41
0.8000 15.89 12.71
0.8000 12.12 9.70
Oficial
1.00
METRADO: 1307.36
4.44
0.0200 4.15 0.08
1.0500 4.15 4.36
0.88
0.0300 15.89 0.48
0.0300 13.46 0.40