CRONOGRAMA DE AVANCE DE OBRA SEMANAL

CORRESPONDIENTE AL MES MAYO

MONTO DE OBRA S/. 312,361.20


MONTO ASIGNADO S/. 263,510.00
FECHA DE INICIO DE OBRA 4/19/2017
PLAZO DE EJECUCIÓN 3 MESES
FECHA DE TERMINO 7/16/2017

CRONOGRAMA VALORIZADO
RESUMEN

Item Descripción UNID METRADO Precio S/.


1.00 OBRAS PROVISIONALES
1.01 CARTEL DE OBRA und 1 S/. 814.92
1.02 ALQUILER DE AMBIENTES PARA ALMACEN Y RESIDENCIA DE OBRA mes 3 S/. 800.00
1.03 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 609.84 S/. 1.27
1.04 CINTA DE SEGURIDAD - MALLAS GLB 1 S/. 400.00
1.05 PUENTE DE MADERA PROVISIONAL und 60 S/. 64.86
4.00 RED DE AGUA POTABLE
4.01 TENDIDO DE TUBERIA TENDIDO DE TUBERIA TENDIDO DE TUBERIA TENDIDO DE TUBERIA
04.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO DE CONSTRUCCION m2 239.76 1.74
04.01.02 EXCAVACION MANUAL DE TERRENO m3 225.68 31.94
04.01.03 REFINE DE ZANJAS m2 239.76 11.72
04.01.04 CAMA DE APOYO P/TUBERIAS (H=0.20 m) m2 239.76 20.29
04.01.05 TUBERIA DE PVC UF C-10 PARA AGUA DE 110 mm (INC. SUMIN. Y COLOC.) m 165 30.13
04.01.06 RELLENO COMPACTADO DE ZANJA CON MATERIAL PROPIO HASTA H=1.00 MTS m 399.6 26.57
04.01.07 TRANSPORTE MANUAL DE MATERIAL EXCEDENTE (D=180 m) m3 31.17 19.17
04.01.08 ELIMINACION MATERIAL EXCEDENTE C/MAQUINARIA m3 31.17 52.83
5.00 RED DE DESAGUE
5.01 DESAGUE
05.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO DE CONSTRUCCION m2 266.08 1.74
05.01.02 EXCAVACION MANUAL DE TERRENO hasta H=1.50 mts m3 339.68 30.19
05.01.03 NIVELADO Y COMPACTADO MANUAL m2 266.08 4.54
05.01.04 CAMA DE APOYO P/TUBERIAS (H=0.20 m) m2 266.08 20.29
05.01.05 TUBERIA PVC DE ALCANTARILLADO SN 4 UF DE 200 mm (INC. SUM. Y COLOC) m 190 47.85
05.01.06 RELLENO DE ZANJAS COMPACTADO CON MATERIAL PROPIO hasta H = 1.50 mts m 332.6 32.44
05.01.07 TRANSPORTE MANUAL DE MATERIAL EXCEDENTE (D=180 m) m3 51.89 19.17
05.01.08 ELIMINACION MATERIAL EXCEDENTE C/MAQUINARIA m3 51.89 52.83
COSTO DIRECTO 193,100
GASTOS GENERALES 37.63% 72,667
COSTO DE INSPECCION DE OBRA 11.64% 22,470
COSTO EXPEDIENTE TECNICO 6.61% 12,762
GASTOS DE LIQUIDACION DE OBRA 5.88% 11,360
TOTAL PRESUPUESTO 312,361

AVANCE EN PORCENTAJE %

SON : VENTI CINCO MIL QUINIENTOS SESENTA Y CINCO CON 41/100 SOLES
ANAL

REGION
DEPARTAMENTO
PROVINCIA
DISTRITO
LOCALIDAD

ORIZADO
MES MES 05
SEMANA semana 05
DIA L M M J V S D
Parcial S/. EJECUTADO 22 23 24 25 26 27 28

S/. 8,281.02

S/. 814.92 S/. 0.00


S/. 2,400.00 S/. 0.00
S/. 774.50 S/. 0.00
S/. 400.00 S/. 0.00
S/. 3,891.60 S/. 389.16 10.00%
S/. 51,340.31 S/. 0.00
S/. 33,133.18 S/. 0.00
S/. 417.18 S/. 208.59 50.00%
S/. 7,208.22 S/. 2,883.29 40.00%
S/. 2,809.99 S/. 843.00 30.00%
S/. 4,864.73 S/. 1,459.42 30.00%
S/. 4,971.45 S/. 3,977.16 80.00%
S/. 10,617.37 S/. 2,123.47 20.00%
S/. 597.53 S/. 0.00
S/. 1,646.71 S/. 0.00
S/. 78,708.90 S/. 0.00
S/. 40,941.81 S/. 0.00
S/. 462.98 S/. 0.00
S/. 10,254.94 S/. 1,025.49 10.00%
S/. 1,208.00 S/. 724.80 60.00%
S/. 5,398.76 S/. 3,239.26 60.00%
S/. 9,091.50 S/. 5,454.90 60.00%
S/. 10,789.54 S/. 3,236.86 30.00%
S/. 994.73 S/. 0.00
S/. 2,741.35 S/. 0.00
193,100.41 25,565.41
72,667.61 9,620.78
22,470.49 2,974.97
12,762.05 1,689.62
11,360.65 1,504.09

312,361.21 41,354.86

13.24%