Академический Документы
Профессиональный Документы
Культура Документы
Imitative
◦ Allows competitors to explore the market
◦ If their products are successful, the firm quickly launches its imitations
§ Samsung/Apple, Pepsi/Coke, Excel/Lotus 123, Mr. Pibb/Dr. Pepper
First generation touch screen iPhone 2007 First generation touch screen Samsung 2008
Digital
Technology
Light-Lens
Technology
Time
What is a prototype?
- physical model of a product
2. State the objective for each task. Each objective must be:
§ Easily understood
§ Specific in terms of what is to be developed
§ Feasible, given the available personnel, equipment, and time
3. Estimate the personnel, time, and other resources needed to meet the
objectives
D: project difficulty
D = 1: not too difficult (using well-known technologies); D = 2: difficult (some new
technologies); D = 3: extremely difficult (many new technologies)
in visualizing CPM
• Tasks are listed on the vertical axis; time horizontally
• Duration of tasks are indicated by the length of ‘time-spanning’ bars
bar chart.
tically, time tasks
ing Technologies
time
ede H.
University of New Orleans ENME 4733 29
MECHANICAL ENGINEERING
Critical Path Method
AThe
predecessor
critical path relationship implies
is the longest path that
(time) one the
through activity
network.
must come before another in the schedule.
Earliest starting time (ES): the earliest time an activity can begin
Input informa on
Latest starting time (LS): the latest time an activity can begin
Duration
(hours)
Preceded
by Formulate
problem
Planning A Gather information 4
each activity
Concept development C Generate product-level alternatives
D Generate subassembly alternatives
4
5
A,B
A,B Evaluate
Func onality
DFM
Cost
alterna ves
12 C,D,E Reliability
E Evaluate alternatives
Not Robustness
Prototype F Build prototype 10 F acceptable Other DFX
C
A B E F G The durations are only estimates and
D can be specified in units of minutes,
hours, days and weeks….
Notice that “concept development” is not estimated to take 21 hours
(not 4+5+12)
University because you can generate
of New Orleans ENMEalternatives
4733 in parallel. 30
MECHANICAL ENGINEERING
Critical Path Method
Latest finishConstruction
time (LF): LF = LS +Project
D Tasks
• Construction
Total float (TF): TF = LS - ES, the •slack between earliest and
Finance
latest
– start times
Grade & Clear • Sell Space
– Dig footers
– Pour footers • Plan Open House
An activity on the critical path has zero float!!
– Build Fence
– Remove Forms
CPM STEPS
– Lay Blocks
•Create a task list
– Framing •Determine task durations
– Electrical •Determine task dependencies
– Heating and Air Conditioning •Define the critical path/ milestones
– Apply Wallboard •Estimate the project duration
– Painting
§ End nodes
§ project duration (time to complete critical path) minus
duration of end task
§ Middle nodes
§ project duration minus duration of each task
G Install new
tubes
H Leak test
I Check
thermocouples
J Insulate
K Test