Академический Документы
Профессиональный Документы
Культура Документы
Systems
ProCash 2050xe
ProCash 2050xe USB
Installation Guide
Questions and suggestions
... any questions or suggestions regarding ... any technical questions or problems?
this manual?
Please contact the following address giving If you have any technical questions or problems
the order number of this manual in your please contact your local representative.
message:
Address:
Wincor Nixdorf International GmbH
Handbuchredaktion BD PSD 43
33094 Paderborn
Germany
E-mail: manuals.hardware@wincor-nixdorf.com
Installation Guide
Introduction............................................................................................................................................ 1
Symbols used in this guide...................................................................................................................... 1
Important safety precautions ................................................................................................................... 2
Installation notes ................................................................................................................................ 2
General safety precautions ................................................................................................................ 2
Installation............................................................................................................................................ 73
Removing the packaging....................................................................................................................... 73
Removing the shipping crate................................................................................................................. 74
General............................................................................................................................................. 74
Disassembly ..................................................................................................................................... 74
Mounting sets ........................................................................................................................................ 75
Mounting set 01750051579 for installation frame or installation rack.............................................. 75
Mounting set 01750078516 for UL safe on 25 mm (0.98") installation frame ................................. 76
Mounting set 01750051578 for CEN safe on 25 mm (0.98") installation frame .............................. 76
Mounting set 01750051060 for safe on 82 mm (3.23") and 222 mm (8.74") installation frame or
installation rack................................................................................................................................. 76
Overview of installation types................................................................................................................ 77
Installation with 25 mm (0.98") installation frame.................................................................................. 78
Installing the installation frame......................................................................................................... 78
Mounting the device on the installation frame.................................................................................. 83
Installation with 82 mm (3.23") installation frame.................................................................................. 86
Installing the installation frame......................................................................................................... 86
Mounting the device on the installation frame.................................................................................. 91
Installation with 222 mm (8.74") installation frame................................................................................ 94
Installing the installation frame......................................................................................................... 94
Mounting the device on the installation frame................................................................................ 100
Installation with height-adjustable installation rack ............................................................................. 103
Preparing the installation rack........................................................................................................ 103
Overview ................................................................................................................................... 103
Calculating the rack height........................................................................................................ 104
Calculating the rack setting height ............................................................................................ 104
Mounting the installation rack......................................................................................................... 105
Mounting the device on the installation rack .................................................................................. 114
Installing the tunnel frame ................................................................................................................... 117
Pulling out / pushing in the customer panel ................................................................................... 118
Installing the sealing frame ............................................................................................................ 119
Installing the adjusting plates ......................................................................................................... 121
Securing the tunnel frame .............................................................................................................. 123
Connecting the logo light (only for tunnel frame with light case) ................................................... 124
Connecting the tunnel frame light .................................................................................................. 126
Start-up................................................................................................................................................ 126
T
TN network Power supply network in acc.
with EN 60950
Available accessories:
" " Text in quotation marks contains references to other chapters or sections in this
document.
• Paragraphs following this symbol are actions to be performed in the specified order.
Text following this symbol have to be given special attention in order to avoid
damage or injury.
This symbol identifies paragraphs which contain general notes to facilitate use of
the device and help avoid operating errors.
Installation notes
− When installing the device and/or doing any work on it, make sure that it is
disconnected from power.
− When moving the device from a cold to a warm environment, do not operate it for at
least two hours to prevent possible damage caused by condensation.
− The device is equipped with a safety-tested power cable, which must be connected
only to a suitable grounded outlet.
− Only replace the CCFL light of the tunnel and operating unit when the device is turned
off.
− Always hold the plug when removing the power cable. Never pull the cable itself.
− Install cables in such a way that they will not be stepped on or tripped over or
damaged or squished in any way.
− Make sure that there is always free access to the sockets used or to the electrical
circuit-breakers of the house installation.
Switching off the automatic circuit-breaker or removing the fuse inset from the fuse
holder in the distribution box of the building installation;
Disconnecting the plug connector of the power supply cable from the grounded
socket in the building installation;
Switching off the ON/OFF switch on the power distributor.
Interrupting the power connection between the UPS (uninterruptible power supply)
and the device (see section "General power interrupt" in the operating manual);
− Always keep the device's vents free from obstruction to ensure proper air circulation
and to prevent malfunctions resulting from overheating.
− Only use accessories and extension components that have been approved by us.
Nonobservance can result in damage to the device or violations of regulations
concerning safety, radio interference and ergonomical requirements.
− Note that there are only safety extra-low voltage circuits (SELV circuits) if you want to
feed voltage from an external source into prepared cables to install additional
electronics (e.g. connection for an intruder alarm system).
− To clean the device only use cleaning agents approved by Wincor Nixdorf
International GmbH (see chapter "Appendix", section "Approved cleaning materials" in
the operating manual).
Repairs
Unauthorized opening of the device or repair work carried out improperly could
result in considerable danger to the user.
Lithium batteries
From the time of installation up to the start-up of the device, the climatic
environmental conditions for storage must be met (see chapter "Appendix",
section "Environmental conditions").
Make sure that the values are neither higher nor lower than the specified values
to prevent irreparable damage to the device.
Wincor Nixdorf International GmbH is not liable for any damage to the device
resulting from failure to meet these conditions.
215 (8.46")
1890 (74.41")
677 (26.65")
667 (26.26")
1405 (55.31")
1500 (59.06")
1500 (59.06")
885 (34.84")
35
668 (26.3")
658 (25.91")
614 (24.17")
(1.38")
13.5
(0.53")
500
(19.69")
634 (24.96")
215 (8.46")
484 50 (1.97")
(19.06")
1890 (74.41")
1616 (63.62")
667 (26.26")
677 (26.65")
1616 (63.62")
1500 (59.06")
885 (34.84")
658 (25.91")
35
614 (24.17")
668 (26.3")
(1.38")
13.5
(0.53")
500
(19.69")
634 (24.96")
215 (8.46")
484 50 (1.97")
(19.06")
1890 (74.41")
1616 (63.62")
1616 (63.62")
677 (26.65")
667 (26.26")
1500 (59.06")
885 (34.84")
35
658 (25.91")
668 (26.3")
(1.38")
(16.89")
429
72/43* 848 (33.39")
600 (23.62") (2.83"/1.69"*) 1208 (47.56")
1243 (48.94")
13.5
(0.53")
500
(19.69")
634 (24.96")
1545 (60.83")
2030 (79.92")
1640 (64.57")
1640 (64.57")
1025 (40.35")
35
798 (31.42")
808 (31.81")
(1.38")
754 (29.69")
72/43*
484 50 (1.97")
(19.06")
2030 (79.92")
1756 (69.13")
1640 (64.57")
1756 (69.13")
1025 (40.35")
35
798 (31.42")
808 (31.81")
(1.38")
754 (29.69")
72/43*
484 50 (1.97")
(19.06")
1756 (69.13")
2030 (79.92")
1756 (69.13")
1640 (64.57")
35
1025 (40.35")
(1.38")
808 (31.81")
798 (31.42")
569 (22.4")
72/43*
2150 (84.65")
1760 (69.29")
1665 (65.55")
1760 (69.29")
1145 (45.08")
35
(1.38")
928 (36.54")
918 (36.14")
484 50 (1.97")
(19.06")
1876 (73.86")
1876 (73.86")
2150 (84.65")
1760 (69.29")
35
1145 (45.08")
(1.38")
918 (36.14")
928 (36.54")
874 (34.41")
72/43*
484 50 (1.97")
(19.06")
1876 (73.86")
2150 (84.65")
1876 (73.86")
1760 (69.29")
35
1145 (45.08")
(1.38")
928 (36.54")
918 (36.14")
689 (27.13")
72/43*
215 (8.46")
677 (26.65")
667 (26.26")
1416 (55.75")
1890 (74.41")
1500 (59.06")
1500 (59.06")
885 (34.84")
60
658 (25.91")
668 (26.3")
614 (24.17")
(2.36")
13.5
(0.53")
500
(19.69")
634 (24.96")
484 75 (2.95")
(19.06")
1890 (74.41")
1630 (64.17")
1630 (64.17")
1500 (59.06")
885 (34.84")
60
658 (25.91")
668 (26.3")
614 (24.17")
(2.36")
72/43*
1183 (46.57")
1243 (48.94")
215 (8.46")
1556 (61.26")
2030 (79.92")
1640 (64.57")
1640 (64.57")
1025 (40.35")
60
798 (31.42")
808 (31.81")
(2.36")
754 (29.69")
72/43*
1183 (46.57)
484 75 (2.95")
(19.06")
1770 (69.69")
2030 (79.92")
1770 (69.69")
1640 (64.57")
1025 (40.35")
60
798 (31.42")
(2.36")
808 (31.81")
754 (29.69")
72/43*
1183 (46.57")
60 (2.36")
2150 (84.65")
1760 (69.29")
1687 (66.42")
1145 (45.08")
918 (36.14")
928 (36.54")
874 (34.41")
43 / 72 *
1183 (46.57")
484 75 (2.95")
(19.06")
2150 (84.65")
1891 (74.45")
1891 (74.45")
1760 (69.29")
60
1145 (45.08")
(2.36")
928 (36.54")
918 (36.14")
874 (34.41")
43 / 72 *
1183 (46.57")
Installation options
The ProCash 2050xe / 2050xe USB can only be installed through a wall cutout.
The following table gives a list of installation options depending on the floor heights on
the customer panel side and on the device side.
The installation options apply to devices with a 35 mm (1.38") tunnel and as well as to
devices with a 60 mm (2.36") tunnel.
Installation options for ProCash 2050xe / Same floor height Different floor
ProCash 2050xe USB with 4–cassette height
dispenser
Installation with 25 mm (0.98") installation frame yes yes
on a concrete base
Installation with 222 mm (8.74") installation frame yes no
Installation with height-adjustable installation rack no* yes
* If you want to use a height-adjustable installation rack and the floor height inside
and outside is the same, the ProCash 2050xe / 2050xe USB can also be installed
on the 190 - 320 mm (7.48" - 12.6") installation rack.
Installation options for ProCash 2050xe / Same floor height Different floor
ProCash 2050xe USB with 5–cassette height
dispenser
Installation with 25 mm (0.98") installation frame yes yes
on a concrete base
Installation with 82 mm (3.23") installation frame yes no
Installation options for ProCash 2050xe / Same floor height Different floor
ProCash 2050xe USB with 6–cassette height
dispenser
Installation with 25 mm (0.98") installation frame yes no
(ProCash 2050xe / 2050xe USB with 6–cassette
dispenser)
Observe the necessary operation and maintenance space for the various types of
installation (see section "Space required for operation and maintenance").
Vents
The device features forced air ventilation on the right side of the top part and in the door
of the operating unit by means of a built-in fan. Additionally, there are vents on the left
and on the rear of the top part. Make sure that the distance between these vents and the
wall is always at least 50 mm (1.97").
1 Vents
Ventilation space
Additional operation and maintenance space, right or left
Operation and maintenance space
Additional space required for the installation (for reaching the fastening screws
in the safe).
1 Wall
35 mm tunnel (1.38")
1155 (45.47")
405 150 (5.91")
(15.94")
980 (38.58")
780 (30.71")
620 (24.41")
848 (33.39")
50 50
(1.97") 13.5 (1.97")
(0.53")
1
850 (33.46")
60 mm tunnel (2.36")
1155 (45.47")
405 150 (5.91")
(15.94")
980 (38.58")
780 (30.71")
620 (24.41")
848 (33.39")
50 50
(1.97") 13.5 (1.97")
(0.53")
875 (34.45")
Installation options
The installation options are described for the ProCash 2050xe / 2050xe USB with 35 mm
(1.38") tunnel by way of example. The specified heights also apply to the
ProCash 2050xe / 2050xe USB version with 60 mm (2.36") tunnel.
Possible versions
The illustration below shows a higher floor level on the outside. The descriptions
also apply if the floor level is higher on the inside and if the floor is on the same
level on the inside and outside.
W**
x3
5
x4
2
1890 (74.41")
6
615 (24.21")
I: 3
710 (27.95")
222 (8.74")
1
648 (25.51")
935* (36.81"*)
870 (34.25")
1 2
7
x1
II: 3
x2
4
1
(.98")
3
25
8
x5 9
III: 3
Not any difference in floor level can be compensated by the installation versions
described. Therefore, the following limit values apply for X1wall:
CEN / UL safe
Option I: min. 778 mm (30.63"), max. 1178 mm (46.38") (UL) /
max. 1128 mm (44.41") (CEN)
Option III: min. 673 mm (26.5")
Possible versions
The illustration below shows a higher floor level on the outside. The descriptions
also apply if the floor level is higher on the inside and if the floor is on the same
level on the inside and outside.
The two different versions, version I (82 mm (3.23") installation frame) and
version II (25 mm (0.98") installation frame with base) are shown on the right side
in the following picture.
82 (3.23")
W** 1
2 5
2030 (79.92")
615 (24.21")
I: 3
710 (27.95")
1
(.98")
25
788 (31.02")
935 (36.81")*
870 (34.25")
1 2 6
7
x5
x1
II: 3
x2
Not any difference in floor level can be compensated by the installation version
described. Therefore, the following limit value applies for X1wall:
CEN safe
Version II: min. 813 mm (32.01")
W**
(24.21")
615
(27.95")
2150 (84.65")
710
933 (36.73")
908 (35.75")
988 (38.9")*
1 2
3 4
− bright ceiling light, light reflections and direct sunlight shining on the screen are
avoided,
− the requirements concerning ambient conditions can be met (see chapter "Appendix",
section "Technical data"),
− existing underfloor heating, energy and/or communication cables, etc., are not
damaged when drilling the mounting holes.
When choosing the installation site, take the noise emission into consideration.
Fans in operation or the noise produced during a transaction could disturb people
in the immediate vicinity of the device and may therefore need to be diminished
with soundproofing (e.g. soundproof cabinets, etc.).
They must comply with the environmental conditions that apply to the specific
device and the maintenance areas (see chapter "Appendix", section "Technical
data").
The device must be screwed to the load-bearing substructure of the installation site or
mounted on a suitable base.
Using the prescribed mounting materials, the following values relating to resistance to
removal of the safe from the installation frame are reached:
The operator must provide a suitable base to protect it from removal by force. We
recommend reinforced concrete B25 (EN206 C20/25) or a higher-quality concrete.
General
The 25 mm (0.98") installation frame has to be used if you want to install the
ProCash 2050xe / 2050xe USB (4– or 5–cassette dispenser on a concrete base
(provided by customer) or if you want to install the ProCash 2050xe / 2050xe USB (6–
cassette dispenser) on the floor.
The installation frame can be either a standard installation frame or a CEN frame
(identified by the 'CEN' sticker).
The installation frame is secured to the base (4– or 5–cassette dispenser) or to the floor
(6–cassette dispenser) at the attachment points (see sections "Drilling diagram for 25 mm
(0.98") installation frame").
Openings which are not used have to be closed by putting in the filling pieces.
For mounting material see section "Mounting sets" in the chapter "Installation".
1
4
2
A B
687 (27.05")
3
842 (33.15")
3
C D
2
569 (22.4")
536 (21.1")
486 (19.13")
429 (16.89")
347 (13.66")
247 (9.72")
202 (7.95")
62 (2.44")
25 (0.98")
130 (5.12")
105 (4.13")
25 (0.98")
4
1
2
391 (15.39")
3
451 (17.76")
2
712 (28.03")
737 (29.02")
817 (32.17")
3
2
3
2
1
5
1 Cable lead-in in the installation frame 4 This side must always point
2 Area for cables to the side with the safe door
3 Cable exit opening underneath 5 Customer panel side
installation frame
General
The 82 mm (3.23") installation frame has to be used if you want to install the
ProCash 2050xe / 2050xe USB (5–cassette dispenser) in the specified wall cutout and
with the same floor height on both sides of the wall.
The installation frame is secured to the floor at the attachment points (see sections
"Drilling diagram for 82 mm (3.23") installation frame").
Openings which are not used have to be closed by putting in the filling pieces.
For mounting material see section "Mounting sets" in the chapter "Installation".
For a safe with resistance level IV (CEN IV), it is mandatory to secure the CEN frame to
the positions marked 2 and 3 with eight threaded rods (see next illustrations).
594 (23.39")
539 (21.22")
179
5
(7.05")
(5.79")
147
1
2 4
A B
687 (27.05")
3
842 (33.15")
3
C D
2
1
568 (22.36")
539 (21.22")
530 (20.87")
515 (20.28")
484 (19.07")
453 (17.83")
265 (10.43")
55 (2.17")
37 (1.46")
151 (5.94")
135(5.31")
55 4
(2.17")
1
159(6.26")
282 (11.1")
309 (12.17")
2
382 (15.04")
462 (18.19")
3
564 (22.2")
2
787 (30.98")
805 (31.69")
5 1
1 Cable lead-in in the installation frame 4 This side must always point
2 Area for cables to the side with the safe door.
3 Cable exit opening underneath 5 Customer panel side
installation frame
General
The 222 mm (8.74") installation frame has to be used if you want to install the
ProCash 2050xe / 2050xe USB (4–cassette dispenser) in the specified wall cutout and
with the same floor height on both sides of the wall.
The installation frame can be either a standard installation frame or a CEN frame
(identified by the 'CEN' sticker).
The installation frame is secured to the floor at the attachment points (see sections
"Drilling diagram for 222 mm (8.74") installation frame").
Then the device is screwed to the installation frame.
Openings which are not used have to be closed by putting in the filling pieces.
For mounting material see section "Mounting sets" in the chapter "Installation".
For a safe with resistance level III (CEN III) and UL, it is mandatory to secure the
installation frame at the positions marked 2 with four threaded rods.
Positions 3 serve as alternative attachment points (see next illustrations).
For a safe with resistance level IV (CEN IV), it is mandatory to secure the CEN frame to
the positions marked 2 and 3 with eight threaded rods (see next illustration).
594 (23.39")
539 (21.22")
179
5
(7.05")
(5.79")
147
1
2 4
A B
687 (27.05")
3
842 (33.15")
3
C D
2
1
568 (22.36")
539 (21.22")
530 (20.87")
515 (20.28")
484 (19.07")
453 (17.83")
265 (10.43")
55 (2.17")
37 (1.46")
151 (5.94")
135(5.31")
55 4
(2.17")
1
159(6.26")
282 (11.1")
309 (12.17")
2
382 (15.04")
462 (18.19")
3
564 (22.2")
2
787 (30.98")
805 (31.69")
5 1
1 Cable lead-in in the installation frame 4 This side must always point
2 Area for cables 5 to the side with the safe door.
3 Cable exit opening underneath 5 Customer panel side
installation frame
General
The installation rack has to be used if you want to install the ProCash 2050xe /
2050xe USB (4–cassette dispenser) in an existing wall cutout and with different floor
heights on the inside and outside. It consists of an upper and a lower part.
The installation rack can be either a standard rack or a CEN rack (identified by the 'CEN'
sticker).
The installation rack is secured to the floor at the attachment points (see section "Drilling
diagram for installation rack").
Then the device is screwed to the installation rack.
Openings which are not used have to be closed by putting in the filling pieces.
For mounting material see section "Mounting sets" in the chapter "Installation".
For a safe with resistance level III (CEN III) and UL, it is mandatory to secure the
installation rack at the positions marked 1 with four threaded rods.
Positions 2 serve as alternative attachment points (see next illustrations).
For a safe with resistance level IV (CEN IV), it is mandatory to secure the CEN rack to
the positions marked 1 and 2 with eight threaded rods (see next illustration).
Lower part
The installation rack must be secured using one threaded rod (for UL / CEN III
safe) or two threaded rods (for CEN IV safe) per group of holes A to D.
The installation rack is secured with a total of four or eight threaded rods.
4
566 (22.28")
3
2
A B
1
814 (32.04")
2 D
C
1
Upper part
594 (23.39")
539 (21.22")
179 (7.05") 3
(5.79")
147
1
2
687 (27.05")
1
842 (33.15")
Lower part
527 (20.75")
453 (17.83")
448 (17.64")
43 (1.69")
433 (17.05")
50 (1.97")
15 (0.59")
398 (15.67")
113 2
(4.45")
(4.29")
109
(6.65")
290 (11.42")
169
1
536 (21.1")
656 (25.83")
754 (29.69")
Upper part
20 (0.79")
82 (3.23")
550 (21.65")
530 (20.87")
484 (19.06")
• Use the following formula to determine the required rack height (see also illustration in
the section "Installation options 4–cassette dispenser"):
• Compare the result with the values in the first column of the following table. The
required rack height X4rack is listed in the right column.
1
2
x1
x4 x3
x2
4
3
Tear-off sensor
All safes, installation frames and installation racks have holes for mounting a
tear-off sensor.
To ensure that the tear-off sensor can be mounted after the device has been installed, a
hole for the tear-off sensor has to be drilled at the time the installation frame or the
installation rack is mounted.
To be able to mount the tear-off sensor, the hole has to be cleaned with a vacuum
cleaner and an anchor bolt (e.g. UPAT multicone, Fischer resin cartridge R M) has to be
inserted.
Thus the alarm technician will be able to mount the tear-off sensor in the safe easily after
the device is installed (see also illustration "Mounting structure with CEN III / CEN IV
safe" or "Mounting structure with UL safe" in the corresponding sections of the chapter
"Installation").
Ask your alarm technician about the size of the hole and the cartridge. The mounting
material (threaded rod, cartridge) is to be provided by the alarm technician. The length of
the threaded rod depends on the installation frame or the installation rack you use (see
chapter "Installation").
Drilling diagrams
The following figures specify the distance from the edge of the device (safe) of the drill
holes that are used to secure ProCash 2050xe / 2050xe USB to the installation frame or
installation rack.
482 (18.98")
471.5 (18.56")
107 (4.21")
(5.91")
(7.4")
(10.94")
150
188
278
578 (22.76")
668 (26.3")
Drilling depth:
Holes for installation frame: at least 180 mm (7.09") with 125 mm (4.92") in concrete;
Select the hole diameter according to the mounting
instructions of the caulking cartridge.
Hole for tear-off sensor: at least 40 mm (1.57") in concrete.
Ask your alarm technician about the hole diameter and the
cartridge to be used.
484 (19.06")
472 (18.58")
240 (9.45")
(5.91")
(7.76")
(10.91")
150
197
277
602 (23.7")
682 (26.85")
Drilling depth:
Holes for installation frame: at least 180 mm (7.09") with 125 mm (4.92") in concrete;
Select the hole diameter according to the mounting
instructions of the caulking cartridge.
Hole for tear-off sensor: at least 40 mm (1.57") in concrete.
Ask your alarm technician about the hole diameter and the
cartridge to be used.
484 (19.06")
472 (18.58")
240 (9.45")
(5.91")
(7.76")
(10.91")
150
277
197
599 (23.58")
682 (26.85")
Drilling depth:
Holes for installation frame: at least 180 mm (7.09") with 125 mm (4.92") in concrete;
Select the hole diameter according to the mounting
instructions of the caulking cartridge.
Hole for tear-off sensor: at least 40 mm (1.57") in concrete.
Ask your alarm technician about the hole diameter and the
cartridge to be used.
472 (18.58")
456 (17.95")
406 (15.98")
194 (7.64")
144 (5.67")
(5.91")
(8.84")
(10.81")
224.5
150
274.5
591 (23.27")
641 (25.24")
Drilling depth:
Holes for installation frame: at least 180 mm (7.09") with 125 mm (4.92") in concrete;
Select the hole diameter according to the mounting
instructions of the caulking cartridge.
Hole for tear-off sensor: at least 40 mm (1.57") in concrete.
Ask your alarm technician about the hole diameter and the
cartridge to be used.
General information
When the cables enter the device from below, make sure that the cables cannot
be sheared off when the system is moved.
To connect the device, power and data cables are required. In standard deliveries, the
connections for all the device's power and data cables are situated near the cable feed
opening of the safe. The additional power cable that is provided has a standard length of
2.5 m (8.2 ft). Other ready-to-use lengths of power and data cables can be ordered if
needed via the hardware configurator or must be provided by the customer. Please refer
to the corresponding illustrations in this guide for the positioning of the cables.
To lay the cables inside the installation frame or rack and in the safe, filling pieces may
be removed so that cable sets can be inserted in the cable feed openings (see drawing).
These filling pieces must then be replaced after the cables have been installed. The
cable exit points in the floor must be kept clear to ensure that the cables are not bent or
damaged.
Make sure that the cables provided on-site are long enough to be laid through the
installation frame or through the installation rack into the safe.
You will also find details of the position of cable routing for the device in the
sections "Installation frame 25 mm (0.98")" or "Installation frame 82 mm (3.23"),
"Installation frame 222 mm (8.74")" or "Height-adjustable installation rack".
Power supply
The device must only be connected to a TN system. In addition to the power supply for
the device, grounding outlets must be provided by the customer for supplementary
equipment such as a modem.
L N PE
If the ProCash 2050xe / 2050xe USB was ordered without logos, the logos have
to be provided by the customer. The illustration shows the visible outer surface of
the upper logo case (454 mm x 165 mm (17.87" x 6.5")) and the lower light case
(515 mm x 100 mm (20.28" x 3.94")).
The actual logo dimensions of the logo light case are 465 mm x 171 mm (18.31"
x 6.73").
The actual logo dimensions of the tunnel light case are 523 mm x 107 mm
(20.59" x 0.26").
The entire transportation route, like the installation site, must be checked for load
capacity and, if necessary, strengthened as appropriate before the installation date.
Observe the ambient condition requirements in the chapter "Appendix", section
"Technical data" for transportation and storage.
Due to the shipping crate some dimensions are different (see illustrations below).
1645 (64.76")
1448 (57.01")
796 (31.34")
145 (5.71")
145 (5.71")
1 Shipping crate
1785 (70.28")
1588 (62.52")
936 (36.85")
145 (5.71")
145 (5.71")
1 Shipping crate
1708 (67.24")
1905 (75")
1056 (41.57")
145 (5.71")
145 (5.71")
1 Shipping crate
Check beforehand if there is enough space to move the device through doors
and hallways.
690 (27.17")
520 (20.47")
1350 (53.15")
1580 (62.2")
710 (27.95")
1900 (74.8")
520 (20.47")
690 (27.17")
1350 (53.15")
1580 (62.2")
The climatic environmental conditions for storage must be complied with during
installation and until the device goes into service (see chapter "Appendix",
section "Environmental conditions").
Compliance may not fall short of or exceed the conditions stated, since this could
cause irreparable damage to the device.
In the case of non compliance, Wincor Nixdorf International GmbH does not
accept liability for any damage that occurs to the device.
All dimensions are specified in millimeters (inches). The diagrams are not drawn
to scale.
Contact the person in charge of planning the installation to verify that all
preparations have been performed completely and professionally and that none
of the required power and data cables are missing.
General
For transportation the device is equipped with a shipping crate. This must be removed
before installation.
To move the device only push against the sides of the safe as shown in the
illustration below.
Disassembly
Proceed as follows to remove the shipping crate:
Please return the shipping crate which is no longer needed to Wincor Nixdorf
International GmbH. Please contact your vendor, if necessary.
Mounting sets
The mounting sets are supplied with the installation frame or the installation rack
of the ProCash 2050xe / 2050xe USB.
The mounting set for the tear-off sensor is not supplied with the device.
* For a CEN IV safe two mounting sets are supplied with the 82 mm (3.23") installation
frame, 222 mm (8.74") installation frame and the installation rack.
When a 25 mm (0.98") installation frame is used only one mounting set is needed.
* If you want to use a height-adjustable installation rack and the floor height inside
and outside is the same, the ProCash 2050xe / 2050xe USB can also be installed
on the 190 - 320 mm (7.48" - 12.6") installation rack.
Make sure that the clearance between the vents and the wall is at least 50 mm
(1.97") (53 mm (2.09") in relation to the installation frame).
• Align the installation frame and mark the holes for mounting the installation frame (see
illustrations below).
The installation frame must be secured using one threaded rod per group of
holes A to D.
The installation frame is secured with a total of four threaded rods.
10 5
1 6
2 4
A B
3
7 6
3
C D
2
1 6
11 5
9
13.5
12 (0.53") 12
8
550 (21.65")
283.5 310.5
(11.16") (12.22")
• Drill the required four or eight holes and the hole for the tear-off sensor, if necessary
(see following figures).
To ensure that the safe does not become detached, the threaded rods of the
installation frame must be fastened in the concrete foundation.
The drilled holes in the concrete foundation must have a depth of at least
125 mm (4.92") for the installation frame (see illustrations below).
For the hole diameter please refer to the instructions for the caulking
cartridge.
The drilled hole in the concrete foundation must have a depth of at least
40 mm (1.57") for the tear-off sensor (see illustrations below). Consult your
alarm technician about the size of the hole and the cartridge.
25 (0.98")
2 3 4 5
180* (7.09" *)
(min. 4.92")
min. 125
min. (1.57")
min. 40
7 6
25 (0.98")
2 3 4 5
180* (7.09" *)
(min. 4.92")
min. 125
min. (1.57")
min. 40
7 6
* This distance depends on the screed height. The threaded rod included in the
mounting set must either be adapted or replaced.
• Clean the drill holes as specified in the mounting instructions of the caulking cartridge.
• Secure the threaded rods in the concrete foundation as specified in the mounting
instructions of the caulking cartridge.
• Remove the filling piece 5b and the filling piece 5b if required from the appropriate
cable feed opening (see position 5a and 5b in the following illustration).
5a
• Screw the installation frame to the pedestal (for material see section "Mounting sets").
If applicable, note the hardening times of the mounting material.
The threaded rods must not protrude beyond the installation frame. If
necessary, level the threaded rods.
• Open the safe door (see chapter "Basic Operation", section "Opening / closing the
safe door (with factory setting)" or "Opening / closing the safe door (with customized
lock)" in the operating manual).
• If it is necessary for the installation remove those parts inside the unit which secure its
components during transportation (see enclosed information sheet).
• Pull out the CMD-V4 (see chapter "Basic Operation", section "Pulling out / pushing in
the cash media dispenser" in the operating manual).
• Lift the CMD-V4 slightly and pull out the locking axle. Carefully lower the CMD-V4.
When lifting or lowering the CMD-V4 make sure that the connecting cables on
the rear side of the CMD-V4 controller are not damaged and that they are not
moved around!
• Remove the two track locks and push the CMD-V4 back in.
• Feed the data cables and the power cable into the safe.
• Replace the filling piece of the installation frame (position 5b) if required and the filling
piece of the safe.
• Attach the VDS label for the CEN installation frame to the inside of the safe door
below the VDS label that is already there. (The VDS label for the mounted installation
frame is included with the installation frame).
• After you have mounted the installation frame and the device, fill out the Confirmation
of Installation form. (The Confirmation of Installation is included with the installation
frame)
• Fax the filled out and signed Confirmation of Installation form to the fax number
provided on the form.
If there is no fax machine available, the form has to be faxed to this number at
a later point in time.
General
The locking axle and the track stops must stay in the safe for future service
operations.
Make sure that the clearance between the vents and the wall is at least 50 mm
(1.97") (53 mm (2.09") in relation to the installation frame).
• Align the installation frame and mark the holes for mounting the installation frame (see
illustrations below).
For a safe with resistance level IV (CEN IV), it is mandatory to secure the CEN frame to
the positions marked 2 and 3 with eight threaded rods (see next illustrations).
The installation frame must be secured using two threaded rods per group of
holes A to D.
The installation frame is secured with a total of eight threaded rods.
5
10 6
1
2 4
A B
3
7
6
7 6
3
C D
2
1 6
5
9
13.5
P*
W*
12 (0.53") 12
11
8
550 (21.65")
283.5 310.5
(11.16") (12.22")
• Drill the required eight holes and the hole for the tear-off sensor, if necessary (see
following figures).
To ensure that the safe does not become detached, the threaded rods of the
installation frame must be fastened in the concrete foundation.
The drilled holes in the concrete foundation must have a depth of at least
125 mm (4.92") for the installation frame (see illustrations below).
For the hole diameter please refer to the instructions for the caulking
cartridge.
The drilled hole in the concrete foundation must have a depth of at least
40 mm (1.57") for the tear-off sensor (see illustrations below). Consult your
alarm technician about the size of the hole and the cartridge.
2 3 4 5
82 (3.23")
8
min. 40 (1.57")
180* (7.09" *)
(min. 4.92")
min. 125
7 6
* This distance depends on the screed height. The threaded rod included in the
mounting set must either be adapted or replaced.
• Clean the drill holes as specified in the mounting instructions of the caulking cartridge.
• Secure the threaded rods in the concrete foundation as specified in the mounting
instructions of the caulking cartridge.
• Remove the filling piece 5b and the filling piece 5b if required from the appropriate
cable feed opening (see position 5a and 5b in the following illustration).
5a
• Screw the installation frame to the floor (for material see section "Mounting sets").
If applicable, note the hardening times of the mounting material.
The threaded rods must not protrude beyond the installation frame. If
necessary, level the threaded rods.
• Open the safe door (see chapter "Basic Operation", section "Opening / closing the
safe door (with factory setting)" or "Opening / closing the safe door (with customized
lock)" in the operating manual).
• If it is necessary for the installation remove those parts inside the unit which secure its
components during transportation (see enclosed information sheet).
• Pull out the CMD-V4 (see chapter "Basic Operation", section "Pulling out / pushing in
the cash media dispenser" in the operating manual).
• Lift the CMD-V4 slightly and pull out the locking axle. Carefully lower the CMD-V4.
When lifting or lowering the CMD-V4 make sure that the connecting cables on
the rear side of the CMD-V4 controller are not damaged and that they are not
moved around!
• Remove the two track locks and push the CMD-V4 back in.
• Feed the data cables and the power cable into the safe.
• Replace the filling piece of the installation frame (position 5b) if required and the filling
piece of the safe.
• Attach the VDS label for the CEN installation frame to the inside of the safe door
below the VDS label that is already there. (The VDS label for the mounted installation
frame is included with the installation frame).
• After you have mounted the installation frame and the device, fill out the Confirmation
of Installation form. (The Confirmation of Installation is included with the installation
frame)
• Fax the filled out and signed Confirmation of Installation form to the fax number
provided on the form.
If there is no fax machine available, the form has to be faxed to this number at
a later point in time.
General
The locking axle and the track stops must stay in the safe for future service
operations.
Make sure that the clearance between the vents and the wall is at least 50 mm
(1.97") (53 mm (2.09") in relation to the installation frame).
• Align the installation frame and mark the holes for mounting the installation frame (see
illustrations below).
For a safe with resistance level III (CEN III) and UL, it is mandatory to secure the
installation frame at the positions marked 2 with four threaded rods.
For a safe with resistance level IV (CEN IV), it is mandatory to secure the CEN frame to
the positions marked 2 and 3 with eight threaded rods (see next illustrations).
The installation frame must be secured using one threaded rod (for UL / CEN III
safe) or two threaded rods (for CEN IV safe) per group of holes A to D (see
following illustration).
The installation frame is secured with a total of four or eight threaded rods.
5
10 6
1
2 4
A B
3
6 6
7 7
3
C D
2
1 6
5
P*
13.5
W*
12 (0.53") 12
11
8
550 (21.65")
283.5 310.5
(11.16") (12.22")
• Drill the four or eight required holes and the hole for the tear-off sensor (see the
following illustrations).
To ensure that the safe does not become detached, the threaded rods of the
installation frame must be fastened in the concrete foundation.
The drilled holes in the concrete foundation must have a depth of at least
125 mm (4.92") for the installation frame (see illustrations below).
For the hole diameter please refer to the instructions for the caulking
cartridge.
The drilled hole in the concrete foundation must have a depth of at least
40 mm (1.57") for the tear-off sensor (see illustrations below). Consult your
alarm technician about the size of the hole and the cartridge.
2 3 4
1
7 6 5
180* (7.09" *)
(min. 4.92")
min. (1.57")
min. 40
1 Safe 5 Screed
2 Tear-off sensor 6 Concrete
3 Installation frame 7 Mounting set for installation frame
4 Mounting set for safe 8 Top surface of finished floor
* This distance depends on the screed height. The threaded rod included in the
mounting set must either be adapted or replaced.
2 3 4
5 6 7
8
min. 40 (1.57")
180* (7.09" *)
1 Safe 5 Screed
2 Tear-off sensor 6 Concrete
3 Installation frame 7 Mounting set for installation frame
4 Mounting set for safe 8 Top surface of finished floor
* This distance depends on the screed height. The threaded rod included in the
mounting set must either be adapted or replaced.
• Clean the drill holes as specified in the mounting instructions of the caulking cartridge.
• Secure the threaded rods in the concrete foundation as specified in the mounting
instructions of the caulking cartridge.
• Remove the filling piece 5b and the filling piece 5b if required from the appropriate
cable feed opening (see position 5a and 5b in the following illustration).
5a
• Screw the installation frame to the floor (for material see section "Mounting sets").
If applicable, note the hardening times of the mounting material.
• Open the safe door (refer to the chapter "Basic Operation", section "Opening / closing
the safe door (with factory setting)" or "Opening / closing the safe door (with
customized lock)" in the operating manual of the ProCash 2050xe / 2050xe USB).
• If it is necessary for the installation remove those parts inside the unit which secure its
components during transportation (see enclosed information sheet).
• Pull out the CMD-V4 (see chapter "Basic Operation", section "Pulling out / pushing in
the cash media dispenser" in the operating manual).
• Lift the CMD-V4 slightly and pull out the locking axle. Carefully lower the CMD-V4.
When lifting or lowering the CMD-V4 make sure that the connecting cables on
the rear side of the CMD-V4 controller are not damaged and that they are not
moved around!
• Remove the two track locks and push the CMD-V4 back in.
• Feed the data cables and the power cable into the safe.
• Replace the filling piece of the installation frame if required (position 5b) and the filling
piece of the safe.
• Attach the VDS label for the CEN installation frame to the inside of the safe door
below the VDS label that is already there. (The VDS label for the mounted installation
frame is included with the installation frame).
• After you have mounted the installation frame and the device, fill out the Confirmation
of Installation form. (The Confirmation of Installation is included with the installation
frame)
• Fax the filled out and signed Confirmation of Installation form to the fax number
provided on the form.
If there is no fax machine available, the form has to be faxed to this number at
a later point in time.
General
The locking axle and the track stops must stay in the safe for future service
operations.
Make sure that the distance between the vents and the wall is at least 50 mm
(1.97") (56 mm (2.2") in relation to the lower part of the standard rack and 67 mm
(2.64") in relation to the lower part of the CEN rack).
Overview
(25.51")
648
1 2
x1
x3
x2
x4
• Calculate the height that must be compensated X2height using the following formula
(see also the section "Overview"):
• Compare the result with the figures in the left column of the table below. The required
rack height X4rack is listed in the right column.
• Calculate the setting height for the installation rack using the following formula:
• Place the upper part of the installation rack on the floor as shown in the illustration
below. Screw the hexagon nuts onto the threaded rods as far as the calculated
measurement X3variable (X3).
1 1
2 3 2
X3
1 Threaded rod 3 Installation rack, upper part
2 Hexagon nut X3 Adjustable height of installation rack
(X3variable)
• Insert the lower part of the installation rack as shown in the following figure, and
secure it with the hexagon nuts.
2 2
• Align the installation rack and mark the holes for mounting the installation rack (see
illustrations below).
For a safe with resistance level III (CEN III) and UL, it is mandatory to secure the
installation rack at the positions marked 1 with four threaded rods.
For a safe with resistance level IV (CEN IV), it is mandatory to secure the CEN rack to
the positions marked 1 and 2 with eight threaded rods (see next illustration).
The installation rack must be secured using one threaded rod (for UL / CEN III
safe) or two threaded rods (for CEN IV safe) per group of holes A to D.
The installation rack is secured with a total of four or eight threaded rods.
7
4
3
A 2 B
1
C 2 D
1
4
6
13.5
W*
P*
9 (0.53") 9
8
5
550 (21.65")
269.5 296.5
(10.61") (11.67")
• Drill the four or eight required holes and the hole for the tear-off sensor (see the
following illustrations).
To ensure that the safe does not become detached, the threaded rods of the
installation frame must be fastened in the concrete foundation.
The drilled holes in the concrete foundation must have a depth of at least
125 mm (4.92") for the installation rack (see illustrations below).
For the hole diameter please refer to the instructions for the caulking
cartridge.
The drilled hole in the concrete foundation must have a depth of at least
40 mm (1.57") for the tear-off sensor (see illustrations below). Consult your
alarm technician about the size of the hole and the cartridge.
2 3 4 5
1
6 7 8
1 Safe 6 Screed
2 Tear-off sensor 7 Concrete
3 Installation rack (upper part) 8 Mounting set for the installation rack
4 Installation rack (lower part) 9 Top surface of finished floor
5 Mounting set for safe
* This distance depends on the screed height. The threaded rod included in the
mounting set must either be adapted or replaced.
2 3 4 5
6 7 8
1 Safe 6 Screed
2 Tear-off sensor 7 Concrete
3 Installation rack (upper part) 8 Mounting set for the installation rack
4 Installation rack (lower part) 9 Top surface of finished floor
5 Mounting set for safe
* This distance depends on the screed height. The threaded rod included in the
mounting set must either be adapted or replaced.
• Clean the drill holes as specified in the mounting instructions of the caulking cartridge.
• Secure the threaded rods in the concrete foundation as specified in the mounting
instructions of the caulking cartridge.
• Remove the relevant filling pieces from the cable lead-ins in the upper part of the
installation rack (see position 1 in the following illustration).
• Screw the installation frame to the floor (for material see section "Mounting sets").
If applicable, note the hardening times of the mounting material.
• Cover the threaded rods used for adjusting the height with U profiles and the nuts with
the sealing plugs (see illustration below).
• Open the safe door (refer to the chapter "Basic Operation", section "Opening / closing
the safe door (with factory setting)" or "Opening / closing the safe door (with
customized lock)" in the operating manual of the ProCash 2050xe / 2050xe USB).
• If it is necessary for the installation remove those parts inside the unit which secure its
components during transportation (see enclosed information sheet).
• Pull out the CMD-V4 (see chapter "Basic Operation", section "Pulling out / pushing in
the cash media dispenser" in the operating manual).
• Lift the CMD-V4 slightly and pull out the locking axle. Carefully lower the CMD-V4.
When lifting or lowering the CMD-V4 make sure that the connecting cables on
the rear side of the CMD-V4 controller are not damaged and that they are not
moved around!
• Remove the two track locks and push the CMD-V4 back in.
• Feed the data cables and the power cable into the safe.
• Replace the filling pieces of the installation rack if required (position 1) and the filling
piece of the safe.
• Attach the VDS label for the CEN installation rack to the inside of the safe door below
the VDS label that is already there. (The VDS label for the mounted installation rack is
included with the installation rack).
• After you have mounted the installation rack and the device, fill out the Confirmation of
Installation form. (The Confirmation of Installation is included with the installation rack)
• Fax the filled out and signed Confirmation of Installation form to the fax number
provided on the form.
If there is no fax machine available, the form has to be faxed to this number at
a later point in time.
General
The locking axle and the track stops must stay in the safe for future service
operations.
For the sake of clarity, the figures on the following pages demonstrating the
individual steps do not show the wall.
• Open the door of the operating unit (see chapter "Basic Operation", section "Opening /
closing the device doors" in the operating manual).
• Push the two release levers of the customer panel down (1). Pull the customer panel
forwards out of the device as far as possible (2).
Pushing it in
Loosen the securing screw until it no longer sits
in the lower groove of the track.
Then push the customer panel into the device
until the release levers click into place.
• Pull out the customer panel and secure it to prevent it from closing accidentally (see
chapter "Basic Operation", section "Pulling out / pushing in the customer panel" in the
operating manual).
• Push the sealing frame over the customer panel (1) into the wall opening until it
touches the outer wall all around.
• Attach the sealing frame to the device at the five attachment points (2) (right, left, top
(2x) and bottom).
• Put the two adjusting plates in place on the right and left side of the customer panel
(1). Attach each adjusting plate with a screw (2).
• Loosen the securing screw of the customer panel until it no longer sits in the lower
groove of the track (see chapter "Basic Operation", section "Pulling out / pushing in
the customer panel" in the operating manual).
• Then push the customer panel into the device until it clicks into place.
• Unlock the operating unit, pull it out as far as possible and secure the customer panel
with a screw so that it cannot accidentally close / bang shut (see chapter "Basic
Operation", section "Pulling out / pushing in the customer panel" in the operating
manual).
Connecting the logo light (only for tunnel frame with light case)
Disconnect the cable from the retaining
aluminum bracket (1).
• Press the two retaining clips down (2) and pull the illumination unit forwards slightly by
the lower edge (3).
• Hold the illumination unit with one hand and push the connector onto the socket (4)
and the ground connector onto the tab (5).
Lay the cables in such a way that they will not be damaged when the customer
panel is pulled out or pushed in.
• Connect the two cables below the tunnel frame (see arrow).
Lay the cables in such a way that they will not be damaged when the customer
panel is pulled out or pushed in.
• Loosen the securing screw until it no longer sits in the lower groove of the track (see
chapter "Basic Operation", section "Pulling out / pushing in the customer panel" in the
operating manual).
• Then push the customer panel into the device until it clicks into place.
Start-up
The service technician will connect the power and data cables.
Delivery package
Installation
• In masonry only:
Drill the necessary bores: drill depth: 20 mm (0.79"), drill diameter: 4 mm (0.16"), and
insert the enclosed fixings in the holes.
• Lay the connecting cable of the standard remote status indicator to the appropriate
device.
• Route the connecting cable through the cable feed openings or the lead-ins into the
device (see the section for the appropriate installation version in the chapter
"Installation").
• Lay the connecting cable in the device to the relay panel for external features so that it
cannot be damaged when components are pulled out.
• Shorten the connecting cable if so required to the appropriate length (see section
"Shortening the cable ends").
Marking on wires
The wires are marked with an adhesive label at the end as follows:
Depending on the device configuration the relay panel for external features can
be either equipped with a USB or a DSUB plug. The wire connection is the same
for both plugs.
• Connect the individual wires to the relay panel for external features as follows:
11 12 13 14
Pin Name
11 Wire 'RED - 11 RED LIGHT'
12 Wire 'WHITE - 12 YELLOW LIGHT'
13 Wire 'GREEN - 13 GREEN LIGHT'
14 Wire 'BLACK - 14 GND'
Delivery package
Installation
• In masonry only:
Drill the necessary bores: drill depth: 40 mm (1.57"), drill diameter: 6 mm (0.02"), and
insert the enclosed fixings in the holes.
• Lay the connecting cable of the audio remote status indicator to the appropriate
device.
• Route the connecting cable through the cable feed openings or the lead-ins into the
device (see the section for the appropriate installation version in the chapter
"Installation").
• Lay the connecting cable in the device so that it cannot be damaged when
components are pulled out.
• Shorten the connecting cable if so required to the appropriate length (see section
"Shortening the cable ends").
Marking on wires
The wires are marked with an adhesive label at the end as follows:
Depending on the device configuration the relay panel for external features can
be either equipped with a USB or a DSUB plug. The wire connection is the same
for both plugs.
• Connect the individual wires to the relay panel for external features as follows:
11 12 13 14
Pin Name
11 Wire 'RED - 11 RED LIGHT'
12 Wire 'WHITE - 12 YELLOW LIGHT'
13 Wire 'GREEN - 13 GREEN LIGHT'
14 Wire 'BLACK - 14 GND'
• Lead the connecting cable through the opening in the lower section and secure it with
the strain relief.
Marking on wires
The wires are marked with an adhesive label at the end as follows:
Pin Name
1 Wire 'RED - RED LIGHT'
2 Wire 'WHITE - YELLOW LIGHT'
3 Wire 'GREEN - GREEN LIGHT'
4 Wire 'BLACK - GND'
• Press the front cover onto the lower section. Ensure that no wires are damaged in the
process.
Marking on wires
The wires are marked with an adhesive label at the end as follows:
Pin Name
1 Wire 'RED - RED LIGHT'
2 Wire 'WHITE - YELLOW LIGHT'
3 Wire 'GREEN - GREEN LIGHT'
4 Wire 'BLACK – GND'
• Press the connecting cable with the spacer into the cable guide (2).
• Mount the board and the back panel as described above under removal.
This check list has been created for all self-service systems. Most questions can be
answered yes or no. Some empty space is provided in the section "Notes concerning
installation preparation" for your convenience if you want to note any questions or drafts.
After checking off all items, copy this list, send it to your head of operations and
make arrangements for an installation date.
Name:
Telephone number:
Fax number:
General information
Installation
Yes No OK
Is the load carrying capacity of the floor sufficient according to
the installation documentation?
Is there floor heating in the installation area?
Are there cavities in the installation area (cable channel,
raised floor)?
Is the operation and maintenance space sufficient?
Is the equipment screened from external light (sunlight)?
Is a video surveillance system to be installed?
Is a door opener system to be installed?
Preparations
Construction work
Yes No OK
Is the securing of cash-dispensers in the raw concrete
ensured (CEN standard)?
Is the frame aligned and fastened in accordance with the
installation instructions?
Has a wall opening that may be required been completed?
Are the ambient conditions met?
Organizational preparations
Yes No OK
Is the generation prepared on the host?
Has the MM module or CIM86 been ordered and is it
available?
Have the encryption/decryption or EPP keys been prepared?
Is the paper and money ready for start-up?
Have you discussed the diameter of the hole that is to be
drilled and the cartridge to be used for the tear-off sensor with
the local alarm provider?
Diameter?
Cartridge to be used?
Technical data
Device conditions
110 - 120 V 220 - 240 V
Idle mode Operation Idle mode Operation
(maximum) (maximum)
without UPS
Rated current consumption: 1.7 A 3.2 A 0.9 A 1.7 A
Apparent power 175 VA 340 VA 190 VA 320 VA
consumption:
Active power: 165 W 295 W 160 W 285 W
Power factor: 0.96 0.91 0.84 0.84
Leakage current (max.): 1.2 mA 1.2 mA 1.2 mA 1.2 mA
with UPS
Rated current consumption: 2.7 A 4.2 A 1.3 A 2.1 A
Apparent power 290 VA 455 VA 280 VA 410 VA
consumption:
Active power: 265 W 395 W 245 W 370 W
Power factor:
Leakage current (max.): 3.5 mA 3.5 mA 3.5 mA 3.5 mA
Installation conditions
Dimensions: 4-cassette 5-cassette 6-cassette
dispenser dispenser dispenser
Height: 1500 mm 1640 mm 1760 mm
(59.1 ") (64.57 ") (69.29 ")
Width: 600 mm 600 mm 600 mm
(23.62 ") (23.62 ") (23.62 ")
Depth: 848 mm 848 mm 848 mm
(33.39 ") (33.39 ") (33.39 ")
Depth with 35 mm (1.38") 1208 mm 1208 mm 1208 mm
tunnel: (47.56 ") (47.56 ") (47.56 ")
Depth with 60 mm (2.36") 1183 mm 1183 mm 1183 mm
tunnel: (46.57 ") (46.57 ") (46.57 ")
Weight of device:
UL safe: 717 kg - 787 kg
(1581 lb) (1735. lb)
3
CEN III safe: 890 kg - -
(1962. lb)
5
CEN IV safe: 890 kg 995 kg -
(1962. lb) (2194 lb)
5
Surface load:
UL safe: 15.6 kN/m2 - 17.2 kN/m2
(2.26 lbf/in2) (2.49 lbf/in2)
CEN III safe: 19.4 kN/m2 - -
(2.81 lbf/in2)
CEN IV safe: 19.4 kN/m2 21.7 kN/m2 -
(2.81 lbf/in2) (3.15 lbf/in2)
Environmental conditions
* The temperature value of + 35 °C deviates from the value of the standard (+ 40 °C).
** Climate control unit required for temperatures < 5 °C.
*** In the limit range the device may only be operated for a short period of time.
Class Remarks
Operation 3M2 Building with minimal external vibration
Transport 2M2 All types of commercial vehicles and trailers as
(in original packing) well as rail and air transport
Storage 1M3 Noticeable vibration and bumps caused for
(in original packing) example by machines or passing vehicles
When selecting the installation site, noise emission should be taken into account.
Fans in operation or the noise produced during a transaction could disturb people
in the immediate vicinity of the device and may therefore need to be diminished
with soundproofing (e.g. soundproof cabinets, etc.).
They must comply with the environmental conditions that apply to the specific
device (see above) and the maintenance areas (see chapter "Planning the
Installation", section "Space required for operation and maintenance").
Standards met
Safety standards:
IEC 60950 EN 60950 C22.2-60950 UL 60950
EMC standards:
EN 55022 / B EN 55024 ICES-003 (CSA 108.8)
FCC CFR 47, part 15, subpart B, class A
Conformity
The CE mark of conformity attached to the product or its package indicates that the
product complies with the requirements of the following EC directives:
− For a free-standing installation the security container of the ATM shall be anchored in
accordance with this instruction, either using the listed anchoring devices or using
similar devices. Each anchoring device shall withstand a 22,000 pound (97,861 N)
vertical or horizontal force applied in an attempt to remove the security container from
its location.
If the free-standing installation is inside a building and the anchoring devices cannot be
secured to the building structure, the unit shall be attached to a steel plate at least 4 feet
by 8 feet by ½ inch thick (1.22 m by 2.44 m by 12.7 mm thick) or an equivalent structure
so as to restrict the removal of the teller machine from the building. The release
mechanism of the attachment devices shall only be accessible when the door of the
security container is open.
Environmental protection
This means that crucial criteria such as long life, choice of material and its labeling,
emissions, packaging, ease of disassembly and recyclability have been taken into
account. This saves resources and relieves the strain on the environment.
Saving energy
Please switch on devices that need not be constantly running only when they are actually
needed. They should also be turned off when they are not needed for longer periods of
time.
Further information
can be obtained from our Environmental Protection section (Referat Umweltschutz):