Detailed Estimate for Construction of Fencing of Fisheries Department at Zainapora.

S. Particulars
@ USL @ SL
No No. Length (Ft) Breadth (Ft) Height (Ft) Qty. Unit
1 General Site clearance by the way of engagement of labour for cutting of shrubs, 8
removal of weeds, demolition of damaged fencing. (LS. Subject to Actual).
Earthwork in excavation in foundation trenches or drains not exceeding 10sqm on
plan upto 1.5m, including disposal of the excavated earth lead 50m and lift 1.5m
2
1 170 1.5 2.00 510 Cft.
or 14.44 Cft. 0.88 12.71
Providing and laying of stone soling hand packed tightly.
3 1 170 1.5 0.33 84.15 Cft.
2.38 Cum 0.32 0.76
Providing and laying of Cement concrete in M10 Grade (1:3:6) mix using 40mm N/S
Nallah aggregate.
i) Blocks
1 170 1.5 3.00 1147.5 Cft.
32.50 Cum
4
ii) Coping
1 170 1.5 0.25 95.63 Cft.
2.71 Cum.
a. Cement Concrete =Qty. Vide 4ii & 80% of 4i 28.71 Cum. 2.33 66.89 0.1 2.87
b. Plum = 20% of 4i 6.50 Cum. 0.32 2.08
Providing and fixing of formwork including the removal of the same.
5 2 170 2.50 850 Sft.
Or 79.00 Sqm. 0.20 15.80 0.25 19.75
Providing and fixing of structural steel work in fencing all complete.
Vertical Posts (ISA 40x40x6) @ 6' Spacing
26 7.00 182 Rft.
Or 55.49 m
@ 3.49Kg/m 191.99 Kg.
Top Runner (ISA 40x40x6)
1 170.00 170 Rft.
Or 51.83 Rm.
6
@ 3.49Kg/m 180.88 Kg.
Vertical Flats (40x3)
26 6.00 156.00 Rft
1 170 170.00 Rft
Total = 326.00 Rft
Or 99.39 m
@ 0.94Kg/m 125.23 Kgs
Total Qty. 498.10 Kgs
Providing & Laying of link fencing 50×5 mm mesh using G.I. wire 3mm dia. Complete
7 job.
1 170.00 6.00 640.00 Sft.

Consumption Statement
Cement Aggregate Stone Solling
Item No. Qty
@ Qty. Qtl. @ Qty. Cum. @ Qty. Cum.
3 & 4b 8.88 1.00 8.88
4a 28.71 2.2 63.15 1.35 38.75