Академический Документы
Профессиональный Документы
Культура Документы
Field and Formation Description Core Analysis (SCA) will be acquired during detailed
The field is located in the tundra (permafrost) of the northern engineering phase.
part of the West Siberian sedimentary basin. It is permafrost
Tundra region with permafrost depth down to approximately Production Data
500 meters. Climate of the region is continental, characterized Production test of three wells from 1997 until 2001 were
by extreme cold winter temperatures down to –60 C and short performed. Long-term production of approximately four years
summer. The reservoir has a vertical depth of approx. 3600 m is only available from two wells. The average rates were
and is located below 2 hydrocarbon horizons, which are both between 300 MCM/d and 400 MCM/d with bottom hole
in production. The reservoir is divided into two layers (layer A flowing pressures between 250 and 400 bars. A third well
and layer B). 14 out of 18 exploration wells proved gas- produced approximately 500 MCM/d at 400 bars for 10
condensate in the Area. month. The total production of these three wells is approx. 1
BCM.
The discovery is a stratigraphic reservoir in the central part of
the gentle, mainly unfaulted north-south striking anticline, Upside potential was identified on one well. A very small
shed from a prograding shelf terrace as turbidity currents and hydraulic fracture improved the productivity by approx. 2.5
deposited at the foot of the shelf slope as fans / channelized fold, most likely indicates cure of drilling induced damage.
fans during regional regressions. The 3455 to 3770 m deep, More upside potential is seen with improved mud systems,
very heterogeneous, strongly over pressured reservoirs are perforation technology, massive hydraulic fracturing and sub-
made of numerous fine-grained sandstone/siltstone layers with horizontal wellbores.
poor reservoir properties (permeabilities mainly <1mD).
Pilot Project
Due to the complexity of the reservoir, Wintershall plan was The Pilot production will come from two clusters with three
to verify the long-term production forecast, the well design wells each (one vertical and two sub-horizontal wells) .The
and drilling costs and the facility and infrastructure design and Pilot Project will minimize risk and identify production upside
costs with a Pilot test that should be performed prior to the potential based on the following:
Full Field Development. This Pilot Test will also provide
more operational experience with the relatively high paraffin • The reservoir section will be cored in the two vertical
content of the condensate and update the production profile wells.
and reserves. • Continuous bottom hole pressure recording will allow
proper definition of well and reservoir properties.
Reservoir Characteristics • Separator samples will be taken from every well under
Key reservoir parameters listed in table 1 are represented on stable flowing conditions at the very beginning of well
the existing reservoir simulation model. These parameters lead testing. In addition, subsurface samples will be collected
to production forecast during the course of the whole project, from the vertical wells to check depth gradient and CGR.
from pilot production to full field production. Validation and • In the new wells Production Logging Tool (PLT)
further investigation is necessary and planned to be carried out measuring the well inflow profiles will be used to validate
during the detailed engineering study and the pilot phase. the calculated permeability profiles.
• Effect of Condensate Banking, with respect to relative gas
PVT / condensate permeability will be investigated for the
Many scattering gas analysis data from the subject reservoir reservoir simulation purposes.
exists. Below the Dew Point (500 bar) fluid drops out of the • Up to 4 wells will be Hydraulically Fractured to identify,
gas. In maximum nearly 10 % of gas saturated pore space can confirm and optimize the field potential.
be occupied by fluid when pressure is depleted to approx. 150
bars. Testing Program
The test program has to be seen as a guideline for the testing
Further confirming PVT sampling analysis need to be
procedure and has to be adjusted according to the actual well
performed during pilot phase to get a more reliable CGR behavior experienced during operations. The purpose of
(Condensate Gas Ratio) value. subject pilot wells is to generate a comprehensive database
through extensive coring, logging, sampling, testing and
Relative Permeability during an extended production phase of approximately two
To produce the subject wells at reasonable rates bottom hole years to serve as a solid basis for the optimization of the full
flowing pressure will be below Dew Point from the very field development concept.
beginning of production history. Well deliverability can
substantially be decreased by fluid (condensate) saturation in
the near wellbore region. Fluid Sampling
One of the major aims is to collect high quality PVT samples
Relative permeability curves used in the existing reservoir during the pilot phase and three methods are deployed:
model do not take into account Condensate Banking and
appear to be unrealistic. To resolve this issue further Special • MDT The MDT tool will be run during the open hole
logging campaign to determine the pressure gradient of
IPTC 10092 3
the formations. This tool will also take PVT samples. Surface Equipment
• Bottom hole sampling during the initial An emergency shut-in valve close to the wellhead serves as
production tests BH samples can provide reliable data safety device in case of any dangerous situation with the test
of the initial reservoir condition, if the bottom hole equipment. The gas flow will be heated via high-pressure heat
flowing pressure is above the dew point pressure (472 exchanger to a level, which prevents Hydrate forms (cooling
bar) at the sampling point and if the flowing rate is at the choke due to the “Joule Thomson Effect”), and Paraffin
above the critical rate to lift all fluid in the wellbore. precipitates (approx. 40°C) at the test separator.
• Surface sampling from the test separator during
the entire pilot production Is the most reliable The flow rate will be adjusted with the choke manifold. The
method, if the test equipment is properly designed these expected initial wellhead pressure is in the range of 300 – 400
samples will be taken on a regular basis during the entire bar and the separator working pressure between 50 – 150 bar.
pilot phase and the laboratory analysis will evaluate the
change of composition with time, which is essential for The test separator has to be insulated and build in a container
compositional reservoir modeling. to be able to deliver high quality PVT samples under well-
defined conditions.
Initial Reservoir Pressure
At the end of the initial clean up the well will be shut-in. The If the gas flow is not heated and the separator not insulated,
shut-in time will be monitored with the permanent bottom hole Hydrates will form and/or Paraffin will precipitate. Hydrate
gauge. blockage can be prevented with Methanol injection, but this
will corrupt the PVT sample. PVT models also relay
Skin Determination especially on accurate measurement of higher C-molecules
The formation Skin is the second important parameter to (C7+), which is in the condensate in low concentration only
describe the inflow capacity of the well and is also essential and Paraffin precipitation will give wrong results. Proper PVT
for the dynamic reservoir modeling. The Skin factor consists modeling is impossible.
of three parameters:
Immediately after clean up separator PVT-sampling is
1. Drilling induced mechanical Skin required at bottom hole pressure above dew point pressure at
In most cases drilling fluid will damage the near sand face with lowest possible rate to carry all liquid
wellbore zone and reduce the well productivity. This continuously to surface.
value will be derived from the pressure build up after
the flow test. Gas and condensate surface samples are taken at constant
separator condensate/gas ratio. Isokinetic sampling of the gas
2. Dynamic Skin samples is required to compensate for liquid “carryover”.
Due to high flow velocities in gas wells, a rate
dependant or dynamic Skin will further reduce the well Due to no sand production experience on the area, Clamp on
productivity and will mask the mechanical Skin. The sand detection system is required for the first test in case of
dynamic Skin will be determined with multiple flow sand produced to surface. This system will allow optimization
rate tests. of the wells during the test and will gain more experience on
the sand strength and mitigate the flare nozzles wash out and
3. Skin from condensate banking uncompleted clean up and production test.
The bottom hole flowing pressure is expected to be far
below the dew point pressure, hence condensate will Completion
drop out, starting in the vicinity of the wellbore and The completion design for the pilot wells was based on the
develop deeper into the reservoir with time. Condensate following key drivers:
banking can reduce the well capacity significantly in
the long term and high effort has to be taken to • Access and drain the reservoir as effectively as possible.
determine this effect. The multi rate tests have to be • Simple, cost effective completion using standard
repeated during the entire pilot phase, but the time approved components where possible.
intervals depend on the individual well behavior. • Wells need to accommodate down hole P/T gauges.
• Wells need to accommodate future fracturing jobs.
Test Methodology • Reservoir damage should be limited by preventing fluid
The initial test sequence for each well consists of initial Clean loss to the reservoir during completion.
Up with pressure build up and a 4-Rate Test with increasing
choke size. The first flow rate of this test is selected above the The key objectives are to:
critical fluid lift rate of the completion (100000m³/d for 89mm • Delivering a well with no environmental or safety
tubing). At stable flowing conditions a bottom hole fluid incidents.
sample will be taken. After the fourth rate the well will be • Delivering a well capable of producing at maximum
shut-in at the surface for pressure build-up. efficiency.
• Delivering a well that allows fracture operation.
4 IPTC 10092
The final production completion string will be 3 ½” tubing for Tubing Test Nipples
all six wells. 3½” tubing has been selected as the optimum size Tubing test/isolation nipple will be installed below the packer.
to cater for the range of flow rates expected as a result of Additionally, the tubing hangers feature standard profiles for
reservoir pressure, well productivity, CGR and accommodate plugs to be set, to allow tubing isolation, Xmas tree/ BOP
fracturing operations. removal, testing, etc.
In the vertical wells layer A and B should be tested separately. Flow Measurements
To achieve this objective additional packer and tail pipe will Mass flow meters will be installed down stream the production
be set between the top and bottom layer. choke on each pilot well. This meter will provide continues
rate measurements. In addition regular testing with three-
Tubing size phase test separator will be conducted at specified time
A number of vertical flow simulations were run with different intervals (3 - 6 month). This will cover calibration to the mass
tubing sizes. 3 ½” 13Cr tubing has been selected as the flow measurements and fluid sampling at different conditions.
optimum size and material due to the high CO2 partial
pressure (+/- 6 bar) to cater for the range of flow rates Completion Risks and Uncertainties
expected as a result of formation permeability, well As currently planned, no new or untested completion
productivity, CGR and reservoir pressure and accommodate technology will be used. The completion will incorporate
fracturing operations. Several sensitivities made at different downhole P, and T gauges. The pilot wells will be cleaned up
wellhead pressure (Figure 4 & 5). and tested rigless. Memory PLTs will be performed on the two
vertical wells to obtain the productivity profile under
The lower pressure loss in the 3 ½” tubing compared to the 2 commingled zone productivity test.
7/8” (commonly used in that area) due to less friction will
increase the well deliverability and maximize the daily Risk mitigation/registration matrix has been developed to
production rate. Due to lower pressure loss and higher overcome the following:
production rate the difference in flowing wellhead temperature • Wells completed higher.
is negligible (Figure 6). • Liquid zones discovered.
• Poor initial well productivity.
Permanent Downhole Gauges • Not able to retrieve the plug.
Permanent downhole gauges (DHPG) for the 6 pilot wells will • Perforation gun stucked and unable to recover.
be installed as a part of the completion string to provide
• Hydrate and/or paraffin precipitation.
continues bottom hole pressure/temperature measurements.
• DHPG fails.
One gauge carrier with one electronic surface read out
pressure/temperature gauge will be run above the production
packer.
IPTC 10092 5
Additional production rates and pressure build-ups could be During the flow period two accurate electronic
required for full test evaluation and will defined based on well pressure/temperature gauges will be attached to the wellhead.
behavior. If required, a bottom hole shut-in tool could be run During the survey, gas, condensate and water (if any)
with wireline and set in the tubing nipple profile, if wellbore separator rates will be recorded electronically.
storage effects deteriorate the well test evaluation.
Measurements
The well completion is designed to perform hydraulic fracture It is planned to obtain measurements of governing parameters
operation at any time without work-over. Fracture operation and variables during the full clean up and well testing
timing and design depends strongly on the initial well activities. These parameters include and not limited to,
performance and will be decided on when the well production Ambient Pressure & Temperature, Wellhead Thermal
is analyzed. growth/contraction, Annular pressures, Shut-in and flowing
tubing head pressures, Flowline Pressure and Temperature,
Clean-up Choke size, Sand rate if applicable, Separator Pressure &
The wells will be initially opened up at a flow rate above the Temperature, Solids rate and composition Flow rate and
critical flowing rate. Bean-up should take place in steps, each cumulative volumes: condensate, water, gas, H2S and CO2.
lasting approximately 1 hour, or as long as is needed for the
flow to clean up and parameters to stabilize. The wells will be Long Term Production Testing And Production
beaned-up to a clean-up gas rate and if feasible, to the Logging
maximum gas rate that can safely be achieved. Liquid loading The pilot wells production phase is committed for
in the 102mm tubing and slug flow will occur at flow rates approximately two years and long-term tests can be conducted
below approximately 120 Mm3/d. in order to analyze changes of production behavior and of
fluid composition. The focus during this phase is to collect
In the event of sand production in excess of ca. 25 sufficient amount of high quality data to be able to build a
kg/100000m³, the well should be beaned-back to a rate at reliable reservoir model for full field development and not to
which no significant sand production occurs. maximize the production during this phase.
Full clean up of the wells is expected to last approximately 12 Summary and Conclusions
hours. The clean-up period for each well may be curtailed or • The pilot project will be conducted, as an integrated
extended depending on clean-up performance and flow approach in order to develop a sound reservoir model
stability. for the full field development.
The FTHP and FTHT are stable at constant flow rate • Different well completion methods including
The CGR measured at the separator is stable hydraulic fracturing will be applied during the pilot
CO2 measurements are stable phase. This should lead to an optimum and cost
Water rate and composition is stable effective well design for the full field development
under arctic conditions.
Three sets of samples should be taken for each rate. A set
consists of one sample at the wellhead, one condensate sample Acknowledgements
and one gas sample at the separator. One set should be taken at We thank the management of Wintershall for permission to
same flow conditions at the same time. publish this paper and for giving a free hand to the team for
designing the pilot project. Also many thanks go to the team
members and all other persons who directly or indirectly
contributed in this effort.
6 IPTC 10092
M a x im u m F lo w R a t e ( m ³ /d )
1600000
1400000 3 1/2" Frac
1200000 2 7/8" Frac
1000000 4 1/2"
800000 3 1/2"
600000 2 7/8"
400000 2 3/8"
200000
0
0 100 200 300 400 500
Well Head Flow ing Pressure (bar)
200000
C r it ic a l R a t e ( m ³ /d )
150000 4 1/2"
3 1/2"
100000 2 7/8"
2 3/8"
50000
0
Fig 6 Tubing sensitivity flowing wellhead temp.
0 100 200 300 400 500
Well Head Flow ing Pressure (bar)