ANALISIS ESTRUCTURAL DE VIGAS CONTINUAS

(METODO DE CROSS)

W1 = 2.500 TON/M W2 = 1.000 TON/M

A B C

L1 = 6.000 M L2 = 1.000 M
I1 = 1.000 I2 = 1.000

(Nota .- Considerar Inercia relativa)

F.D. 0.143 0.857

M.E.P. 0.000 11.250 -0.125 0.000

Equil. -1.589 -9.536

Transp 0.000 0.000

∑M = 0.000 9.661 -9.661 0.000

∑R = 5.890 9.110 10.161 -9.161

RESULTADOS :

MA = 0.000 TON-M RA = 5.890 TON-M

MB = 9.661 TON-M RB = 19.271 TON-M

ING. LUCAS RODOLFO FAVELA OTAÑEZ PAG. 1 DE 5


ANALISIS ESTRUCTURAL DE VIGAS CONTINUAS
(METODO DE CROSS)
MC = 0.000 TON-M RC = -9.161 TON-M

ING. LUCAS RODOLFO FAVELA OTAÑEZ PAG. 2 DE 5


ANALISIS ESTRUCTURAL DE VIGAS CONTINUAS
(METODO DE CROSS)

W1 = 2.500 TON/M W2 = 1.000 TON/M

A B C

L1 = 6.000 M L2 = 1.000 M
I1 = 1.000 I2 = 0.000

(Nota .- Considerar Inercia relativa)

F.D. 1.000 0.000

M.E.P. -7.500 7.500 -0.083 0.083

Equil. -7.417 0.000

Transp -3.708 0.000

∑M = -11.208 0.083 -0.083 0.083

∑R = 5.646 9.354 0.500 0.500

RESULTADOS :

MA = 11.208 TON-M RA = 5.646 TON-M

MB = 0.083 TON-M RB = 9.854 TON-M

ING. LUCAS RODOLFO FAVELA OTAÑEZ PAG. 3 DE 5


ANALISIS ESTRUCTURAL DE VIGAS CONTINUAS
(METODO DE CROSS)
MC = 0.083 TON-M RC = 0.500 TON-M

ING. LUCAS RODOLFO FAVELA OTAÑEZ PAG. 4 DE 5


ANALISIS ESTRUCTURAL DE VIGAS CONTINUAS
(METODO DE CROSS)

W1 = 2.000 TON/M W2 = 2.000 TON/M W3 = 2.000 TON/M

A B C D

L1 = 3.000 M L2 = 3.000 M L3 = 3.000 M


I1 = 1.000 I2 = 1.000 I3 = 1.000

(Nota .- Considerar Inercia relativa)

F.D. 0.500 0.500 0.500 0.500

M.E.P. 0.000 2.250 -1.500 1.500 -2.250 0.000

Equil. -0.375 -0.375 0.375 0.375

Transp 0.000 0.188 -0.188 0.000

Equil. -0.094 -0.094 0.094 0.094

Transp 0.000 0.047 -0.047 0.000

Equil. -0.023 -0.023 0.023 0.023

Transp 0.000 0.012 -0.012 0.000

Equil. -0.006 -0.006 0.006 0.006

Transp 0.000 0.003 -0.003 0.000

Equil. -0.001 -0.001 0.001 0.001

Transp 0.000 0.001 -0.001 0.000

∑M = 0.000 1.750 -1.750 1.750 -1.750 0.000

∑R = 2.417 3.583 3.000 3.000 3.583 2.417

RESULTADOS :

MA = 0.000 TON-M RA = 2.417 TON

MB = 1.750 TON-M RB = 6.583 TON

MC = 1.750 TON-M RC = 6.583 TON

MD = 0.000 TON-M RD = 2.417 TON

ING. LUCAS RODOLFO FAVELA OTAÑEZ PAG. 5 DE 5