Академический Документы
Профессиональный Документы
Культура Документы
4
4
4
3
4
3
4
3
3
2
2
3
4
4
4
3
3
4
4
3
4
4
3
4
4
4
3
4
3
1
4
3
3
3
3
4
4
4
4
3
2
2
3
4
4
METHOD STATEMENT
PIPE WELDING INSPECTION FOR SITE PROJECT IMPLEMENTATION
DESIGN CODE ANSI B 31.3 & ASME SECTION IX
cleaning inspection
internal/external
acc reject
line up
preparation for
back shielding gas
repair of welding note: minimum of two passes before leaving the joint to go cold
fit up max welding weave 3x D electrode (filler capping)
finishing of weld surface complete as per the approved welding procedure
repair
note 100% visual welding
VT INSP inspection
grinding
radiographic
test repair
note: repair max two times (2x)
complete welding summary sheet (DIC-WSS-02)
PT inspection repair
stress relief
NDT inspection PWHT note: complete welding summary sheet (DIC-WSS-02)
hardness complete prformance report by RT
test
radiographic
test note: 1. Install end caps after completion of spools
2 .lay down spools on wood protect, machines raised
lay down area for flange faces
pipe spool
Job No
PROJECT NAME
Contract
xxx xxx
Job No
PROJECT NAME
Contract
Legend : NA = Not Applicable. ND = Not Determined. NR = Not Relevant. NP = Not Permitted. CPC-MF-16-A-0200
Welding Procedure Specification (WPS)
Job No
PROJECT NAME
Contract
xxxxxxxxxxx
xxx xxx xxx xxx xxx xxx xxx xxx
xxxxxxx
Remarks / xxx :
Date / xxx
Company / xxx
Title / xxx
Signature / xxx
Stamp / xxx
Legend : NA = Not Applicable. ND = Not Determined. NR = Not Relevant. NP = Not Permitted. CPC-MF-16-A-0200
Procedure Qualification Record (PQR)
Job No
PROJECT NAME
Contract
xxx xxx
Job No
PROJECT NAME
Contract
Legend : NA = Not Applicable. ND = Not Determined. NR = Not Relevant. NP = Not Permitted. CPC-MF-17-A-0200
Procedure Qualification Record (PQR)
Job No
PROJECT NAME
Contract
xxxxxxxxxxx
xxx xxx xxx xxx xxx xxx xxx xxx
xxxxxxx
Remarks / xxx :
Legend : NA = Not Applicable. ND = Not Determined. NR = Not Relevant. NP = Not Permitted. CPC-MF-17-A-0200
Procedure Qualification Record (PQR)
XXXXX
Job No
Project
PROJECT NAME Name
Contract
xxxxxxxxxxxxxxxxxxxxxx
Laboratory Manufacturer Reviewed and Approved
xxx xxx xxx
Name
xxx
Date
xxx
Signature
xxx
Stamp / xxx
Legend : NA = Not Applicable. ND = Not Determined. NR = Not Relevant. NP = Not Permitted. 386929546.xls
Procedure Qualification Record (PQR)
XXXXX
Job No
Project
PROJECT NAME Name
Contract
Stamp / xxx
Legend : NA = Not Applicable. ND = Not Determined. NR = Not Relevant. NP = Not Permitted. 386929546.xls
Initial Welder Evaluatuion
ADDITIONAL JOINT 1
ADDITIONAL JOINT 2 ADDITIONAL JOINT 3 ADDITIONAL JOINT 4
xxxxxx xxxxxx xxxxxx xxxxxx
Line No. Line No. Line No. Line No.
Weld No. Weld No. Weld No. Weld No.
Date : Date : Date : Date :
ACCEPTED / XXXXXXXX
REJECTED / XXXXXXXX
NDE Clearance
Job No.
PROJECT NAME
Contract
RT MPI PWHT
DPI UT Hb
The attached welding inspection recorded is providedf for reference, all original NDE and PWHT reports are
available for inspection.
The welds, piping and fittings associated with the above referenced piping section have been subject to the
required NDE and are acceptable to the requirements of the contract documents. The piping section may be
subject to pressure testing.
Subject :
ISOMETRIC DWG. 1. ISO. DWG COMPANY
Contract No.
LINE NO. 2. MATERIAL CERT. SIGNAT.
REMARKS
WELDING NDT REPORTS
Ref. :
Milestone No.
Rev.
Date
Page
sheet number
Daily Welding Report
XXXXX
Job No
PROJECT NAME
Contract
Fit-up
Line No. Iso Dwg No. Weld No. Pipe Dia. Shop/Field Joint Type Root Pass Fill / Cap Repair Remarks
Inspection
xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
CPC-MF-09-A-0200
xxx xxx xxx
CPC-MF-09-A-0200
Welding Repair Record
XXXXX
Job No
PROJECT NAME
Area Line No. Iso No. Weld No. Dia. Material Date RT Rep No. MT Rep No. PT Rep No. UT Rep No. Date Accept Remarks
Repaired Report no
xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
Job No
PROJECT NAME
Area Line No. Iso No. Weld No. Dia. Material Date RT Rep No. MT Rep No. PT Rep No. UT Rep No. Date Accept Remarks
Repaired Report no
xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx
Welding Notes :
Example : 1 Check Cleanliness of base metal before welding, grind to base metal
2 Check Set up and tacking (qualified tack welder only)
3 Visual Inspection Weld
4 Welder to mark identification number on each fillet weld
5 No arc strikes on pipe (Penetrant Test Inspect)
6 Remove slag and undercut, do not grind into base metal
7 Avoid welding brackets directly on to pipe weld seams
Remarks :
NOTES :
1. Support ring material (lug) made from
mild steel flat bar THK 6mm,
L=20 mm for insulation thickness 25mm,
L=45mm for insulation thickness 50mm. Inspected by: Subcon QC Inspector Inspected by: Prime QC Inspector
Lugs to be equally spaced around the
circumference of the pipe and to be welded to
be pipe before hydrotastic test. Sign: ____________________ Sign: ____________________
2. General notes : support to be put on
- all vertical section, lower case Name: ____________________ Name: ____________________
eg sweep bend above well pad
- all slopes 20 ° Date: _____________________ Date: _____________________
- insulation support ringto be welded
to pipe before hydrotastic test
Rev. 0 2001
Rev. 0 2001
COMPANY NAME
PROJECT ADDRESS
Sheet______ of ______
Welding Parameters Acc. Date Sign Erection Contractor Inspection Remarks Cut Edge Praparation Enclosed N.D.T. Reports
1 Check Cleanliness Remarks: ________________ 1 ______________________
2 Check Set up and Clamping _________________________________________ ________________ 2 ______________________
3 Visual Inspection Weld _________________________________________ ________________ 3 ______________________
4 Radiography Test _________________________________________ ________________ 4 ______________________
5 M. P. I. Test _________________________________________ ________________ 5 ______________________
6 Penetrant Test _________________________________________ ________________ 6 ______________________
7 Ultrasonic Test _________________________________________ ________________ 7 ______________________
Rev 1 20 Nov 98 JP
COMPANY NAME )
WELDERS CONTROL SHEET BY RADIOGRAPHIC EXAMINATION (EVERY WEEK)
PERIOD : TO :
Note : C = Crack, P = Parosity, SL = Slag, LOF = Lack of Fusion, IP = Incomplete Penetration, UC = Undercut Rev. 0, Date
Company Name WELDER QUALIFICATION TEST WQTAR NO. PAGE:
REMARKS :
Rev.0