Вы находитесь на странице: 1из 36

Testing of high-voltage

equipment

Ir. S. Kuivenhoven
KEMA TDT - PDI

Experience you can trust.


Contents

• Introduction to high-power testing


• High-power testing vs pulsed power
• Power sources
• Testing examples
– Reactor testing
– Internal arc
– Synthetic break
– Synthetic make

5-30-2006 Waldur Symposium "Pulsed Power" 2


Why high-power testing….?

… because this is what we want to avoid


5-30-2006 Waldur Symposium "Pulsed Power" 3
What is high-power testing?
• Expose test objects to real life fault conditions and
prove that (for example):

• Circuit breakers are able to interrupt or switch on a


short-circuit current
• Very high currents (up to 80 kArms in a HV grid,
up to 200 kArms for generator CBs)
• High overvoltages after interruption (TRV)

• Transformers, line traps, surge arresters, … are able


to withstand a short-circuit current

5-30-2006 Waldur Symposium "Pulsed Power" 4


Characteristics of High power testing

• Testing according to international standards like IEC


and ANSI or by client instructions
• Test duration: usually 100 ms … 3 s
• Simulate real life conditions: generation of high
current & high voltage
• Cosine phi at testing mostly ~ 0 only apparent
power needed for testing
• Test station must be able to supply huge amounts of
(apparent) power; for example: testing of a 145 kV,
50 kA, Circuit Breaker requires 7250 MVA

5-30-2006 Waldur Symposium "Pulsed Power" 5


High-power testing vs. pulsed power
Power vs. Time

1E+15

1E+12 Sandia Petawatt Program


Power (W)

1E+09
Sandia Z-Beamlet Laser
500 MW Power Plant
1E+06
KEMA HPL
1E+03

1E+00
100E-15 100E-12 100E-9 100E-6 100E-3 100E+0

Time (s)

High-power testing is not really pulsed …


5-30-2006 Waldur Symposium "Pulsed Power" 6
High-power testing vs. pulsed power
Energy vs. Time

1E+12

1E+09 Sandia Petawatt Program


Energy (J)

Sandia Z-Beamlet Laser


1E+06 500 MW Power Plant
KEMA HPL
1E+03

1E+00
100E-15 100E-12 100E-09 100E-06 100E-03 100E+00

Time (s)

… but high energy!


5-30-2006 Waldur Symposium "Pulsed Power" 7
Power sources (test methods)

• Direct Testing (one source)


- On the grid
- Generator fed
- Capacitor bank fed

• Synthetic testing (multiple sources)

5-30-2006 Waldur Symposium "Pulsed Power" 8


Direct Testing
Laboratory supplied by the power grid

• pros
– simple
– cheap
– representative
– high-power available
– low maintenance

• cons
– poor flexibility
– difficult to adjust
5-30-2006 Waldur Symposium "Pulsed Power" 9
EDF
Direct Testing
Generator supplied laboratory

• pros
– adjustable
– flexible
– no influence on
local grid

• cons
– huge investment
– lots of
maintenance KEMA High-Power Laboratory
5-30-2006 Waldur Symposium "Pulsed Power" 10
Generator supplied laboratory (KEMA)
• Using the kinetic energy of rotating machines

• Slowly speeding up a large short-circuit generator


(synchronous machine) by a grid powered motor;
power drawn from grid is relative low and constant.
• When the generator runs at desired speed, the grid
is disconnected and generator keeps on spinning.
• Excitation is switched on
• Machines are synchronised (if using more than one)
• Making switch is closed short-circuit current flows
• Master breaker interrupts current immediately if test
object fails
5-30-2006 Waldur Symposium "Pulsed Power" 11
KEMA’s High-Power laboratory in NL

• KEMA Arnhem since


1937
• World market leader
• 8400 MVA installed
power (largest in
world)
• Testing of circuit
breakers up to 800 kV
- 100 kA
• 50 employees
• 300 test shifts/year

5-30-2006 Waldur Symposium "Pulsed Power" 12


KEMA’s power sources

• Four 2100 MVA short-circuit generators


– Energy per generator @ 50 Hz: 300 MJ
– Maximum 100 kArms, 260 kApk per generator
• Total power @ 50 Hz (all generators in parallel):
– 5000 MVA single phase / 8400 MVA three phase
– If 10% speed reduction allowed: 900 MW

• Double 720 kV 5.3 PF synthetic stage (each 1.4 MJ)


– Needed if breaker power exceeds laboratory’s
direct power

5-30-2006 Waldur Symposium "Pulsed Power" 13


Examples of HP testing

• Reactor
• Internal Arc
• (Synthetic) Break
• (Synthetic) Make

5-30-2006 Waldur Symposium "Pulsed Power" 14


Testing of a reactor (coil)

• Testobject: 2 mH reactor, 50 kA, 50 Hz

• Optimum power transfer if Zsupply = Zload

• Total apparent power: 3142 MVA

• If test object fails total impedance halves fault


current doubles (while supply voltage unchanged)

• Apparent power at fault: 6284 MVA !

5-30-2006 Waldur Symposium "Pulsed Power" 15


Example of a reactor test

KEMA High-Power Laboratory

5-30-2006 Waldur Symposium "Pulsed Power" 16


Internal arc test

• Simulate a short-circuit in a switchgear enclosure.

• Example: 20 kA, 3 sec


– Power: 100 MW
– Energy: 300 MJ (!)

5-30-2006 Waldur Symposium "Pulsed Power" 17


Example 1 of an Internal Arc test

KEMA High-Power Laboratory

5-30-2006 Waldur Symposium "Pulsed Power" 18


Example 2 of an Internal Arc test

Prof. Damstra Laboratory

5-30-2006 Waldur Symposium "Pulsed Power" 19


Circuit breaker testing: break
• Short-circuit current interrupting (breaking) capability
of a Circuit Breaker
• Grid modelled by lumped elements (R, L & C)
Lv
Test Object

• Before breaking: G Ig
– Contacts closed Ug
R

– High current C
TO ITO

Oscillation: TRV
Lv

G
R
• After breaking:
Ug – Contacts open
TO UTRV
C – High Voltage (TRV)
5-30-2006 Waldur Symposium "Pulsed Power" 20
Transient Recovery Voltage
50
UTO [kV]
Contact ITO [kA]
40
Seperation Ugen [kV]

30

20

10

-10

-20

-30
“Current Zero”:
-40
moment of
interruption
-50
0 5 10 15 20 25 30
Time [ms]

5-30-2006 Waldur Symposium "Pulsed Power" 21


“Problem”: increase of capacity per break

KEMA direct
power

electra 2003

5-30-2006 Waldur Symposium "Pulsed Power" 22


example: short-circuit test of a CB (three-phase)
420 kV - 63 kA - 50 Hz
necessary power: 45830 MVA

this exceeds any laboratory's direct power


(KEMA: 8400 MVA)
other methods must be sought:

- single phase test: necessary power 45830/3 = 15277 MVA


this still does not match the power-voltage characteristics of
the most powerful labs.

5-30-2006 Waldur Symposium "Pulsed Power" 23


Solution
before interruption a sufficiently large power must be available to
maintain the full (arc) current at moderate voltage (< 60 kV)
- from generators

contact separation after interruption there is only


the need for a sufficiently high
voltage
- from precharged capacitor

arcing time

short-circuit current transient recovery voltage synthetic testing

5-30-2006 Waldur Symposium "Pulsed Power" 24


Synthetic testing
Triggered spark gap

Generator circuit Synthetic circuit


Lv AB Ls G

G Ig Ii
R
UTRV +
Ug Uh0 Ch
-
TO
C
TO

Ii
Ig

Ug Ui

UTRV

Current circuit Voltage circuit


5-30-2006 Waldur Symposium "Pulsed Power" 25
Synthetic testing
• Synthetic circuit (parallel current injection)

Lv aux Ls G

G Ig Ii
R
+
Ug UTRV Ch
-
TO C

Ig+Ii

Ui
UTRV

5-30-2006 Waldur Symposium "Pulsed Power" 26


Close-up around current zero
40
IAB [kA]
Gap Synthetic Isynth [kA]
35 installation ITO [kA]

fires
30
Current
through test
25
object
20
Equal dI/dt
Generator
15 current

10

Injected
5 current

-5
28.5 29 29.5 30 30.5 31
Time [ms]
5-30-2006 Waldur Symposium "Pulsed Power" 27
Complete synthetic break
300

200

100

-100

-200

UTO [kV]
-300 Isynth [kA]
ITO [kA]

-400
15 20 25 30 35 40 45
Time [ms]

5-30-2006 Waldur Symposium "Pulsed Power" 28


Synthetic test facilities at KEMA

+
-

KEMA High-Power Laboratory


2 x cap. bank
720 kV - 1.4 MJ

5-30-2006 Waldur Symposium "Pulsed Power" 29


Make test
• Goal: show that a switch is capable of making
(switching on) a short-circuit current (faulted circuit).
Lv

• Before making: G

– Contacts open Ug
TO UTO
– High voltage between contacts
Lv

• After making: G Ig

Ug
– Contacts closed TO

– High current
5-30-2006 Waldur Symposium "Pulsed Power" 30
Make test
Fixed contact Moving contact

Contacts
closing

Pre-strike:
full current

Contacts
closed

5-30-2006 Waldur Symposium "Pulsed Power" 31


Synthetic make

• Synthetic make needed if breaker power exceeds


laboratory’s direct power
– Voltage circuit to initiate pre-strike
– Current circuit to supply short-circuit current

• At the moment of pre-strike, the current circuit must


be switched on immediately (the voltage circuit can’t
deliver the short-circuit current)
– Requires a high speed high current making device

5-30-2006 Waldur Symposium "Pulsed Power" 32


Synthetic make circuit
1. TO closes and 2. If contact distance
High Speed synthetic gap fires between contact
Make Device HV AC becomes too small:
between contacts dielectric beakdown
pre-strike
Lv Ls G
R
MD
G Ig Ii 3. MD detects
+
Ug Ch pre-strike and
Lp -
switches on short-
TO
circuit current

Current circuit Voltage circuit, L and C


tuned to generator
frequency

5-30-2006 Waldur Symposium "Pulsed Power" 33


250
UTO [kV]
ITO [kA]
200
Ugen [kV]

150
CB pre-strikes
100

50

-50

-100
Firing of Start of short-
-150
voltage circuit circuit current

-200
Oscillating
Voltage circuit
-250
0 10 20 30 40 50 60
Time [ms]

5-30-2006 Waldur Symposium "Pulsed Power" 34


Make Device

• Trigatron principle, air


gap
Trigger
contact

Main
contacts

• Max 63 kA in 70 Ps
• 80 kA in development
KEMA High-Power Laboratory
5-30-2006 Waldur Symposium "Pulsed Power" 35
The end

Thank you for your attention!

5-30-2006 Waldur Symposium "Pulsed Power" 36

Вам также может понравиться