Академический Документы
Профессиональный Документы
Культура Документы
HALDIA REFINERY
CHAPTER - I
1.0. INTRODUCTION
Haldia Refinery was designed to produce various grades of Lube Oil Base Stocks
and Bitumen. Surplus distillates and heavy stocks when pooled together could not
meet FO specification. The feed stock therefore was designed to be visbroken in
a coil type Visbreaker Unit @ 462,000 TPA originally designed by M/s Romanian
State Institute for Oil Refinery Design.
This coil type Visbreaking Unit has been operating at Haldia Refinery since 1976
using a mixture of PDA asphalt, Vacuum Residue, Spindle distillates and Light Oil
as feed stock.
The existing coil type Visbreaker is switched over to a soaker type visbreaker
which result in
a) Reduction in fuel consumption due to low temperature operation
b) Less coke deposition in furnace tubes will at least double the the cycle length
c) Flexibility in operation with respect to processing of different feed stock
particularly that of having higher viscosity
d) Improvement of middle distillate yield by about 5.8% wt
e) Lesser probability of chokage of transfer line PRCV with coke
1.1 Function of Visbreaker Unit
Visbreaking or viscosity breaking is basically a mild thermal cracking process, a
common process wherein long chain hydrocarbon molecules in heavy feed stocks
are broken into small molecules having low viscosity, thereby leading to a viscosity
reduction of feed stock. This results in conserving valuable distillate products which
would otherwise be required to be used as cutter stock to produce fuel oil of required
specification.
There are two alternate processes for visbreaking:
Coil Visbreakinq
In this process, feed stock is cracked at high temperature (480-500 Deg C) in a
furnace with shorter residence time to achieve the required conversion.
Soaker Visbreakina
In this process feed stock is heated to relatively lower temperature (435-445 Deg
C) in a furnace and partly cracked VB charge is hold in a Soaker Drum for longer
residence times (25-30 min) to achieve the required conversion.
1.2 Visbreaking Chemistry
Visbreaking process reduces the viscosity as well pour point of the feed stock.
With the application of heat and temperature higher boiling hydrocarbons are
1
VBU Operating Manual
HALDIA REFINERY
decomposed and form lower boiling hydrocarbon molecules. Some of the reactive
molecules, however, combine with one and other to produce even higher boiling
molecules.
The process produces VB gasoline, gas oil and bottom residue (VB tar), basically
cracked and polymerised stock. The end product is essentially dependent on the
quality of feed stock, the temperature and pressure under which the stock is
cracked.
Cracked products are unstable and form gum. During the cracking some coke is
usually formed. Coke is the end product of polymerisation reaction in which two
large olefinic molecules combine to form an even larger olefinic molecule.
C10 H21 - CH = CH2 + CH2 = CH - C10 H21 ->
C10 H21 - CH =CH - CH2 - CH2-C10H21
When above reaction gets repeated several times, the end product is coke. This
usually found inside the walls of furnace tubes, soaker drum & other spots where
all may remain at high temperature and soak heat for sometimes.
Some of the typical reactions are given below:
C1O H22 ———> C8 H17 + C2 H5
C2 H5 + C6 H14 ———> C2 H6 + C6 H13
C13 H20 ———> C3 H10 + C5 H10
C15 H30, C7 H15 ———> C7 H16 + C14 H28 CH2 + C6 H12 CH2 C2 H6
+ C4 H8 CH2 + C8 H18 + C6 H12 + CH2
CH2 CH CH CH3 + C2 H4
1.3 Feed Stock
The original feed stock to VBU was a mixture of PDA Asphalt, Vacuum Residue,
Spindle Distillates and Light Oil. But considering the feed mix availability scenario,
the soaker is designed to process a feed stock consisting of PDA Asphalt and
Vacuum Residue in a proportion of 60 : 4 0 weight basis.
With mild cracking the feed stock is converted to gas, cracked naphtha, gas oil
and VB tar. The first three streams are separated in a fractionator and sent to
respective tanks while the bottom products i.e VB Tar is sent to FO pool, with or
without cutter stock.
1.4 Design Capacity
1.4.1 Presoaker
No. of stream days/year = 310
Design capacity = 462,000 TPA
2
VBU Operating Manual
HALDIA REFINERY
= 62.1 T/Hr
No of shutdown days/year = 55
- 4 shutdown of 6 days
- 1 shutdown of 11 days
- 1 shutdown of 20 days
1.4.2 Post Soaker
3
VBU Operating Manual
HALDIA REFINERY
4
VBU Operating Manual
HALDIA REFINERY
5
VBU Operating Manual
HALDIA REFINERY
6
VBU Operating Manual
HALDIA REFINERY
7
VBU Operating Manual
HALDIA REFINERY
1.6.2 Products
Case-A : Without Soaker
Product MT/Hr % WT
Gases 0.925 1.49
Stabilised Naphtha 1.428 2.3
Gas Oil 0.926 1.49
VB Tar (350 0C +) 58.82 94.72
Total 62.10 100.00
Case-B With Soaker
Product MT/Hr % WT
Gases 1.28 2.06
Stabilised Naphtha 1.53 2.47
Gas Oil 5.31 8.55
VB Tar (350 0C +) 53.98 86.92
1.7. Utilities & Chemicals
1.7.1 Utility Requirement
Utility Unit Consumption
Pre Soaker Post Soaker
1 Cooling Water MT/Hr 840 620
2. MP Steam MT/Hr 6.3 (*5) 3.06 (*4.5)
3. LP Steam MT/Hr -13 -9.76
4. Power KW 318 570
5. Instrument Air Nm3/Hr 120 180
6. Utility Air Nm3/Hr *500 *624
7. Fuel Gas T/Hr 2 0.973
8. DM Water M3/Hr 15 14
9. Service Water M3/Hr - 0.6 (**12)
(Blow Down)
* Intermitent Operational requirement.
Minus (-) Symbol indicates quantity is generated.
** Hose Station Requirement.
An additional rate of 6 T/Hr steam required by shoot blower for 12 minute, every 8
hours
8
VBU Operating Manual
HALDIA REFINERY
1.7.2 Chemicals
1. Corrosion Inhibitor : Approximately 1200 Kg/Hr
based on Ahuralan @ 5-6 ppm on 37C1 overhead vapour quantity
@ 3-4 ppm on 37C4 overhead vapour quantity
1.8. Battery Limit Conditions
1.8.1 Incoming Streams
Stream Temp (0C) Press (Kg/Cm2g)
Min Nor Max Min Nor Max
1. Feed Stock - 110 - - 2-9 -
2. MP Steam 230 290 310 13 14 15
3. Cooling Water - 33 - - 3.2 4.0
4. Instrument Air - 40 - 4.0 4.5 6.0
5. Plant air - 40 - 2.0 3.0 7.0.
6. Fuel Oil - 80-90 - - 8.0 10.0
7. Fuel Gas - 30 - - 2.7 4.0
8. LP Steam - 155-160 - 3.5 4 .0 5.0
9. Slop - 60 80 - 1.0 -
10. Spindle Oil - 5.0 70 - 4.0 -
11. Light Oil - 65 80 - 4.0 -
12 . Flushing Oil-I ** - 40 50 - 5.0 -
13. Flushing Oil-II*** - 50 70 - - -
** Gas Oil
*** Spindle Oil
1.8.2 Outgoing Streams
Streams Temp (0 C) Pressure (Kg/Cm2a)
1. VB Gas 45 5.0
2. VB Naphtha 45' 6.5
3. VB Gas Oil 45 7.0
4. VB Tar 80 4.5
5. LP Stream 155 - 160 5.0
9
VBU Operating Manual
HALDIA REFINERY
10
VBU Operating Manual
HALDIA REFINERY
11
VBU Operating Manual
HALDIA REFINERY
12
VBU Operating Manual
HALDIA REFINERY
1.9.6 FILTERS
SNO TAG NUMBER SERVICE DATA SHEET
NUMBER
1 37-GN-101 A/B* FLUSHING OIL 3592-37-2-DS-1401
2 37-GN-102 A/B* FLUSHING OIL 3592-37-2-DS-1402
3 37-GN-103 A/B* VB TAR 3592-37-2-DS-1403
4 37-GN-104 A/B* SOAKER LIQUID 3592-37-2-DS-1404
1) * New Filters
13
VBU Operating Manual
HALDIA REFINERY
CHAPTER - II
2.0 PROCESS DESCRIPTION
The Visbreaking Unit was designed to process a feed stock comprising of a blend
of Short Residue, Asphalt, Light Oil Distillate cut & slops etc to produce a stable
fuel oil component having a lower viscosity and pour point. However, soaker type
VBU is designed to process a feed stock comprising of a blend of Asphalt & SR
(60: 40 wt).
Two number rotary pumps (44-701 P101 A/B) have been installed in the 700 pump
house at the West side of the existing booster pump. The discharge pressure will
be maintained by local spill back controller (44PIC101).
Feed stock is charged into the Pump 37P-1/1R/1B at 80 to 110 Deg C via Feed
Surge Vessel 37B105. Feed surge drum pressure (1.8 kg/cm2.g) will be maintained
with inert gas by a split range pressure controller 37PIC1103. Level will be controlled
by 37LIC1101. For design feed stock, feed temp is to be maintained at 110 Deg
C.
Feed preheating is attained by heat exchange with fractionator bottom residue
(VB Tar) in heat exchanger 37-E-1 A/B/C/D. These four nos. of heat exchanging
units are placed in series. Feed is being preheated to 272 Deg C in this preheat
train and it enters Heater 37-F-1.
The Feed Stock enters the convection section of the heater in two passes. The
feed is split equally between the two heater streams. FRCAL-3702 and FRCAL-
3703 control the individual passflow. From the convection section the stock passes
into the radiation section of the Heater. The two outlet streams from Heater 37-F-1
are brought together in a header and passes into the soaker drum 37C105. From
Soaker drum it is entered into the Fractionator 37-C-1. Heater outlet temperature
is maintained at 430-445 Deg C. In order to prevent coke formation in the furnace
tubes, condensate water (hot well condensate) is injected into the last part of the
convection zone with the help of pump 37-P-8/8A. The effluent from the soaker
flows through a back pressure control valve PICV1301. Upstream of this valve the
stream is quenched with gas oil. The pressure at the outlet of the Soaker drum is
maintained 12-17 Kg/Cm (g) by PICV1301. The Heater is equipped with
combination burners which can operate either on Fuel Gas or Fuel Oil. Provision
has been kept to put quench gas oil to the outlet of furnace as and when it is required
through TRCV3702.
Before passing through PICV-1301, the outlet stream is quenched with gas oil
from P13/13R controlled by PIC1301 which is reset by TIC1307. To overcome
polymerisation and coking, Light Oil quench is given by 37-P-9/9R from VDU into
the Fractionator 37-C-1 between 4th & 5th tray of Distillation column.
To overcome the coke formation in 37C01 bottom, tar quench EX E01D is given
by FIC1401 cascaded with TIC1401 which maintains 37C01 bottom temp.
14
VBU Operating Manual
HALDIA REFINERY
The Column is provided with three sections. The bottom stripping section is
equipped with 4 trays, the middle section comprising of 9 trays and the top section
with 10 trays. One grid plate is existing between 4th & 5th tray. Gasoline vapours
leave column overhead at 13 0 Deg C. Gas oil is removed as a side cut from tray
10 and is fed into the stripping column 37-C-2. The bottom material of 37-C-l is
pumped out by 37-P-2/2R under level control (LIC-3703B) or by 37P119A/B under
level control (LIC-3703A). The temperature gradient of the column is controlled by
a gasoline reflux provided at the column top and a recirculating gas oil reflux
withdrawn from the draw-off tray 10, which is reintroduced into the column of tray
13 after being cooled in E-5, H-1 and a part in E-111A/B and in E-3. Steam is
introduced into the column bottom for stripping the tar from entrained light products.
Water vapours, gases and gasoline from the fractionator column overhead enters
the condenser E-2A/2B from where it is routed to the reflux accumulate or(37-B-
2). The separated gases from Vessel B-2 flows under pressure to the Absorber
37-C-3. The gasoline separated from water is pumped out by Pump P-6 and routed
partially as reflux to the Fractionator Column C-1, with the remainder flowing through
heat exchanger E-4 into the stabiliser column C-4. There is provision to draw off
water via 37B05 from top section (19th tray) of 37C01 to avoid accumulation of
water build up and the water is routed to 37B02 via 37E02.
In the Absorber column (37C03) the heavy hydrocarbons are recovered from rich
gases by gas oil absorption. The lean gases are -routed under pressure control
together with the stabiliser over head gases to the Fuel Oil.
Block as a source of fuel gas. The rich oil from the bottom of the Absorber C-3 is
reintroduced into the Fractionator column by pump P-5/3R for separation after
heating it in 37E111A/B.
Stabilized gasoline from 37-C-4 is routed under level control through 37-E-4
(stabilized gasoline vs. Unstabilized gasoline) and cooler 37-E-7 to storage. Heat
is supplied to the column bottom by reboiler 37-E-5, employing recirculating gas-
oil as the heating medium.. Gasoline flaw is recorded by FR3 713.
Gas-oil is obtained as a side stream fraction from column C-1 and after striping in
the stripper column C-2 it is routed by pump P-3/3R into the VB Tar Circuit at the
S/S inlet of E113 A/B or to the rundown after cooling it in 37E112 A/B. A part of
stripped gas oil after cooling in 37E112 is sent to 37B103 for flushing fluid. A
portion of the gas oil ex H-l is routed through 37-E-111A/B (Lean Vs Rich GO
exchanger) and then through cooler E03 in the Absorber column as absorbent.
Rich Gas oil Ex37C03 is sent to 37C01 via 37E111A/B.
VB Tar from the Fractionator bottom together with gas oil, exchanges heat with
the feed stock in exchanger E-1 A/B/C/D and thereafter passes through steam
generator E113A/B & cooled in cooler E-8 A/B before routing to storage. Provision
has been given to inject light oil or spindle oil as cutter stock at the upstream of
37E08, by 37P120 A/B. Provision exists to quench fractionation bottom by Light
15
VBU Operating Manual
HALDIA REFINERY
Oil (a cut of VDU) since there is possibility of further cracking at the bottom of
Fractionator (the product gets residence time-a certain minimum level is
maintained). Provision has been given for tar quenching at the bottom of 37C01
by FIC1401 which is reset by TIC1401 which maintains the column bottom
temperature within 350-355 Deg C. VB Tar to storage is recorded by FR-3714. A
slip stream of tar is. utilised to heat up slop in 37-E-101 during slop processing.
For obtaining an effective heat recovery in the unit, following Low Pressure Steam
Generation Systems are provided.
(a) STEAM GENERATOR H-1 : Employinq recirculated gas oil as che heating
medium, which after cooling is used as quench and recirculating reflux to the
Fractinator and absorbent to 37C03 via 37E111 and 37E3.
(b) STEAM GENERATION IN 37F01 : Steam also qenerates in furnace F-1 to
recover heat from the flue gases in conjunction with H-1. Water circualtion
through the furnace generator is ensured by Pump P-10/10R.
(c) STEAM GENERATOR 37-E-113A/B: Employing tar as the heating medium
ex 37E1D which after cooling in E08A/B goes to rundown.
In order to avoid corrosion of the overheat equipment of the Fractionator and
Stabiliser, facilities are provided for injection of inihibitor (AHURALAN) into
the column overhead lines.
The unit is provided with a blowdown system for emergencies and collection
of drainage/slops in 37-B-1 which can be pumped to slop tank by 37-P-11.
SOOT BLOWING SYSTEM : Heater is provided with soot blowing arrange-
ment at its convection bank.
Following provision is there to process slop continuously ex Tk-601/602. Slop
is received from Tank-601/602 [depending on amount of water < 1%] in 37-
B-101 & separation of water is done by maintaining interphase level (with
continuous water draining facility). Oil is the taken in P-9/9R to 37-C-01 bot-
tom via 37E101 where in slop is heated with a slip stream of VB tar. Amount
of slop processing regulated by controlling 37-C-01 bottom temperature 355
Deg C.
Flushing Oil System consists of the following.
1> Normal Flushing Oil (Gas Oil)
2> Medium Pressure Flushing Oil I (Gas oil)
3> Medium Pressure Flushing Oil - II (SO)
4> Medium Pressure Flushing Oil - III (Extract)
5> High Pressure Flushing Oil (Gas oil)
16
VBU Operating Manual
HALDIA REFINERY
Normal flushing oil is drawn from the Refinery flushing oil header and used for
normal flushing of various equipments like heat exchangers etc.
Medium Pressure Flushing Oil - I (Gas oil from U-37 or U-31) is used for in-
strument purging at the soaker drum instruments i.e. where ever I t is possible to
recover this oil products. Flushing Oil-I from 37B103 is pumped to medium pres-
sure header by 37P115 A/B. MP flushing oil is then filtered in Flushing Oil-I filters (3
7GN101 A/B) before it goes for flushing /purging. Level in 37B103 is maintained
by taking GO in the vessel under level control - Pressure on the discharge of the
Flushing Oil-I pumps is controlled by spill back controller (37PICV 2202). Gas oil
can be sent to 700' pump house for flushing of pumps (44-701 P101 A/B) casing.
Medium pressure flushing oil-II (SO) is used for instrument; purging (where the
stream is going to VB FO rundown), coarse and fine filters. Flushing oil-II (SO)
from flushing oil-II drum B102 is pumped by flushing oil-II pumps (37-P114 A/B) to
the flushing oil-II filters (37GN102 A/B) before using it far flushing/purging. It. is also
been utilised to flush the CBD. lines. Make up flushing oil-II (SO) enters the drum on
level control of the drum. Pressure on the discharge of 37P114 A/B is controlled by
spill back controller (37 PICV2201). Provision has been given to take spindle oil
either from flushing oil header near 37 P9/9R or light oil from 31 E127 outlet.
Flushing oil-III (EXTRACT EX U-33/38) is used exclusively for the seal flushing
of VB tar centrifugual pump 37P119 A/B. Make up flushing fluid-III(Heavy extract)
enters in 37B106 from either U-33 or U-38 on level control of the vessel. It is then
pumped by 37 P121 A/B with spill back control. Stand by pump P121 A or B will
start automatically on low header pressure of flushing fluid. For low low header
pressure of flushing fluid-Ill, 37P119 A/B shall trip. Provision has been given to
take light oil in 37B10S Ex U-31.
High pressure flushing oil connections are provided at the points where there is
possibility of choking because of congealing nature of VB tar/VB fuel oil. Flushing
oil-Ram pump (37P116) has been provided for ramming all such points. Flushing
oil required for ramming is taken from Flushing Oil-I vessel outlet. Pressure at the
outlet of this ram pump is again controlled by spill back control valve (37PICV2204).
During ramming care has to be taken so that the pressure should not be allowed to
increase the permissible limit with respect to that line/circuit (REF ANNEXURE-I
FOR RATING OF THE LINES AND MAXIMUM PRESSURE ALLOWED
DURING RAMMING).
17
VBU Operating Manual
HALDIA REFINERY
CHAPTER - III
3.0 SUGGESTED NORMAL OPERATING CONDITIONS FOR DESIGN FEED
STOCKS
Following operating parameters are maintained during the normal running of the
Unit with design feed stock.
Feed Surge Drum (37-B-105)
Parameter Operating Value Design Value
Pressure, Kg/Cm2g 1.8 3.5
Temperature,0C 110 ISO
Feed Flow, MT/Hr 62
3.0.1 Heater (37-F-1)
Parameter Design Operation Value
Feed Rate, M3/Hr @15 Deg C 59.7
Turbulizing Water, T/Hr 0.621 (0.3105 in each pass)
Inlet Temp, 0C 272 0C
Outlet Temp, 0C 435 0C (445 Deg at 100 MT/hr)
Pressure Drop, Kg/Cm2g 9-15
Coil Outlet pressure Kg/Cm2g 13-19
Tube Skin Temp, 0C(Max) 650
Stack Temp, 0C 300
3.0.2 Soaker Drum (37-C-105)
Parameter Operating Value
Inlet Pressure 13-18 Kg/Cm2g
Outlet Pressure 12-17 Kg/Cm2g
Transfer line pressure (C105 to F01) 7 Kg/Cm2g .
Inlet Temperature 430-440 0C
Middle Temperature 428-430 0C
Outlet Temperature 426-436 0C
Quench Oil Flow 5 M3/Hr
Quench Oil Temperature 204 0C
Transfer Line Temperature (C105 to F01) 415 0c
18
VBU Operating Manual
HALDIA REFINERY
19
VBU Operating Manual
HALDIA REFINERY
20
VBU Operating Manual
HALDIA REFINERY
When feed rate is increased, residence time in furnace coil and soaker drum
reduces causing reduction in severity of cracking reaction resulting in raising the
viscosity and pour point of VB Tar and in turn reduction of coke laydown in furnace
coils and soaker drum. This can partly be compensated by reducing the turbulising
water flow through furnace coils and rest by raising coil outlet temperature. The
normal turbulising water flow through each pass when feed rate is 100% i.e. 62
MT/hr is 310.50 kg/hr/pass and when feed rate is reduced to 90%, the turbulising
water flow is to be increased accordingly.
3.1.2 Furnace outlet transfer line temperature
At constant feed, if transfer temperature is raised the amount of cracking increases.
More gas, naphtha and gas oil are produced and the viscosity of VB Tar goes
down. Simultaneously, coke deposition in the furnace tubes increases resulting in
reduced run length of the unit. In addition, heat input to fractionator increases. This
calls for increase in CR and top reflux flow rates to maintain required product
specifications - When transfer temperature is reduced, the reverse takes place.
At design feed rate i.e. 62 MT/hr transfer temperature is 435 Deg C but transfer
temperatures are changed as per feed quantity or quality and VB FO viscosity/
pour requirements.
Indicative direction of T’put vis-a-vis coil outlet temperature for design feed case
is given below to achieve same conversion.
T’put MT/hr COT Deg C
62.1 435-440
56 (90% of 62.1) 432-438
75 (120% of 62.1). 437-442
100 441-445
3.1.3 VB GO quench to Soaker Outlet
The VB GO quench reduces the temperature at soaker drum outlet and stops
further cracking. This quench helps in reducing the tendency to laydown coke in
the transfer lines to column and column inside. Quench rate should be just sufficient
to avoid coking of transfer line. The quench flows to transfer line should be such
that the transfer line temperature should not exceed 415 Deg C. This flow will be
adjusted according to change in feed conditions and cracking severity. The quench
oil flow is controlled by 37FIC1301 which is reset by 37TIC1301.
3.1.4 Fractionator Pressure
The pressure on the fractionator is maintained by PIC-3703 which releases gas to
FG system. The HV1501 at the upstream of PICV3703 is provided to depressurise
the system to flare. A lower pressure causes more vaporisation resulting in heavier
naphtha and gas oil. Tar viscosity also goes high. Higher pressure makes naphtha
and gas oil lighter. VB tar viscosity also goes down. The normal pressure 5.3 kg/
cm2(g).
21
VBU Operating Manual
HALDIA REFINERY
22
VBU Operating Manual
HALDIA REFINERY
Naphtha. These are removed as gas from the stabiliser overhead. Higher top
temperature makes overhead gas heavier. On the other hand, lower top temperature
gives lighter gas. Design top temperature is 70 Deg C. Lower than design bottom
temperature of stabiliser will result in higher RVP of naphtha. The normal bottom
temperature is 115 Deg C.
Lower column pressure causes Heavier hydrocarbons to be carried into the fuel
gas system. Higher pressure increases RVP of bottom product. Normal top
pressure is 7.2 kg/cm2(g).
3.1.11 Soaker Pressure and Temperature
Normal operating pressure at the top of the soaker drum for design feed stock is
12 kg/cm2 (g). For lighter feeds, a higher operating pressure upto 17 kg/cm2 (g)
at the top of soaker drum can be used to obtain BUBBLE FLOW REGIME in the
soaker drum. To ensure bubble flow regime, the three TE’s - 1303/1304/1305
provided around the soaker drum, at the top should have readings close to each
other. If these readings are not close to each other, then this indicates that some
back mixing is taking place in the drum. Back mixing leads to undesirable cracking
reactions.
23
VBU Operating Manual
HALDIA REFINERY
CHAPTER - IV
4.0 NORMAL START-UP PROCEDURE ;
Some of the checks to be carried out prior to actual commissioning of the unit are
indicated below.
ENSURE THAT :
01) Mechanical work has been completed as per P&ID
02) Hydraulic testing of various equipments/piping has been completed
03) Equipments, piping etc have been flushed and they are ready for use
04) Functional tests of rotary equipments and instruments checking/calibration
have been carried out
05) All safety valves are in position after setting and testing
06) Blinds are installed as per master blind list for start up and they are duly
recorded
07) Blinds from fuel oil lines at the battery limit have been removed
08) Flare, CBD and OWS systems, flushing oil facilities are in working condition
09) Safety and fire fighting equipments are in working condition
10) Unnecessary scaffoldings, wooden planks, cotton waste, nuts and bolts
etc are removed from the operating area
11) Power is available in all pumps and earthing of pump is O.K.
12) Utility headers are commissioned
13) Feed Stock is available and there is sufficient ullage in run down tanks
14) Ensure availability of chemicals and other consumables
15) Before start up of Unit inform the following; agencies :
a) RSM
b) OM & Sà for keeping feed TK ready and line up of rundown product and
slop tanks (i.e. circulation tank) and also to keep TK-715 ready
c) TPSà for power, VM steam & DM water consumption. CHECK THE
STATE GRID POWER SUPPLY STATUS.
d) FOBà for vaporizer pressure as FG will be required during FG back up
START UP OF THE UNIT AFTER M&I COMPRISES OF THE FOLLOWING
OPERATIONS :
1. Pressure testing of columns & Vessels
2. Pressure testing of Furnace Coils
3. Fuel Gas (FG) back up
4. Cold circulation
5. Hot circulation
6. On-stream of Unit
24
VBU Operating Manual
HALDIA REFINERY
25
VBU Operating Manual
HALDIA REFINERY
26
VBU Operating Manual
HALDIA REFINERY
27
VBU Operating Manual
HALDIA REFINERY
28
VBU Operating Manual
HALDIA REFINERY
29
VBU Operating Manual
HALDIA REFINERY
30
VBU Operating Manual
HALDIA REFINERY
31
VBU Operating Manual
HALDIA REFINERY
32
VBU Operating Manual
HALDIA REFINERY
54) Open FRCV-04 and flush Circ. reflux line into 37C-1 Drain Panel Operator/
water through P4/4R/13/13R SUC. & disch. bleeders. When Field Operator
all lines will be water free, hot circulation can be started.
55) Keep level in 37C2 upto 50% and C3 upto 40%. Now stop Panel Operator/
P9/9R Drain water from 37C1, C2 & C3.During cold Field Operator
circulation slop gasoline Tk. to be made free of water and
line content to be drained of water thru’ P9/9R suction drain
points.
56) HOT CIRCULATION
After cold circulation is established and water from all
possible points is removed from the system, the unit
is considered ready for hot circulation, Step wise
operation for hot circulation is given below:
Unit is on cold circulation (30M3/Hr/pass i,e. Tk.703/704 Field Operator
To Tk-703/704 continues. Stop purging of 37-F-1 box. Open
Fuel Gas B/L Audco valve and line up FG upto Furnace.
57) Light up 4 pilot burners at different locations of 37-F-l and Panel Operator/
one FO main burner. Open PRCV-02 and keep close Field Operator
individual FG burner valves. Keep Fuel 0il pressure at 3.3-
3.5 kg/ cm2g by operating TRCAH-3703 C/V. Take DM
water in 37B104.
58) After 1/2 hr light up 2nd F.0. burner at the other end of 37F- Panel Operator/
1 and bring up transfer temp. @30 Deg C/hr. Field Operator
59) Start 37-P115 A/B and start Injecting flushing fluid in all Field Operator
locations.
60) Go on draining water from all low pts. till transfer temp, Field Operator
reaches 110 -12 0 Deg C. Do not raise temp, further till 37-
C-1 bottom materials is water free. Flush out Soaker pump
out line also with LO.
61) CHECK FURNACE INTERLOCK & ESD INTERLOCK. Shift-in-Charge/
in presence of Instrument Maintenance Personnel. Panel Operator
KEY POINTS:
# After Checking of Interlocks again isolate the main
oil burners individually and then reset the S/D Control
valve and then light up the burners.
#SOAKER BPCV to be checked for full opening and
then reset it for normal position
33
VBU Operating Manual
HALDIA REFINERY
34
VBU Operating Manual
HALDIA REFINERY
35
VBU Operating Manual
HALDIA REFINERY
36
VBU Operating Manual
HALDIA REFINERY
37
VBU Operating Manual
HALDIA REFINERY
CHAPTER - V
5.0) SHUTDOWN PROCEDURE
Before shutting down the unit inform the following agencies
- RSM
- OM&S (700 P.H, 900 P.H & ETP)
- TPS - for reduction in consumption of utilities and also afterwards increase in
consumption of VM steam for steaming the columns, vessels etc
- Fire Station - to keep ready diesel pump for watering of columns, vessels etc. if
required
The Shutdown broadly consists of the following operations/steps
A. Reduction of feed rate and then C.O.T
B. Furnace cut off
C. Pumping out bottom products of Columns, Vessels
D. Depressurisation of Vessels, Columns
E. Steaming of Columns, Vessels, Exchangers
F. Watering and handing over the equipments etc to Maintenance
PROCEDURE ACTION TAKEN BY
01) Start reducing T’ put gradually to 28M3/ hr/pass. Before Panel Operator
reducing T’ put reduce stabilizer feed to maintain B2 level
(60-70%)
02) Put off some burners if required. Adjust feed pump Field Operator
discharge pressure by operating bypass valve.
KEY POINTS :
# Keep watch on PICV-1301 opening. Adjustable
mechanical limit lock is provided to avoid full closing
of PICV-1301.
03) Reduce gas oil circ. reflux in steps to maintain 10th tray Panel Operator
temp & level.
04) Reduce stripping steam flow in steps. Panel Operator
05) Close gas oil to VB Tar & VB Gas Oil R/D valves. Switchover Field Operator
FLO from VBGO to GO ex U-31. Hold level in C02.
06) Stop stripping steam to C2 and isolate both b/v’ s & stop Field Operator
P3/P3R.
38
VBU Operating Manual
HALDIA REFINERY
39
VBU Operating Manual
HALDIA REFINERY
40
VBU Operating Manual
HALDIA REFINERY
41
VBU Operating Manual
HALDIA REFINERY
KEY POINTS :
# Inform RSM before depressurising (Keep Mechanical
Maint. ready for reversing SPB ‘ s on S/O. pts of C-3,
C-4) .
41) Depressurise C-l, C-3 to flare through HV1501 and C04 by Field Operator
opening PSV by pass Block Valve
42) Drain B102/ B103/B105 B106 to 37B1 Field Operator
43) After depressurising, get SPB on F.G. 0/L at B/L blinded Shift-in-Charge
(U/S of b/v)
44) Get vent valve blinds on C-l, C-3, C-4 opened and vent Shift-in-Charge
caps of B-2 & C-2 also opened (Do not open the vent
valves).
45) Steaming of Column, Vessels etc
Start steaming C-1, C-3, C-4, C-105 after draining Field Operator
Condensate. Start steaming in B102/B103/B105/B106
through steam out point. Start steaming flushing fluid circuit.
Drain condensate from all low pts. of pumps, C/V bleeders.
Open HPV’ s.
KEY POINTS :
# Steaming of 37-C-01 to be done by operating FRCV
on Stripping Steam line.
# Open steam to C-2 by opening Stripping Steam block
valve and 37-C-03/ 37-C-04 are steamed by steam out
lines
46) Close C/W to E-2, E-3, E-7, E-112 Field Operator
47) Watering of Columns, Vessels etc
Connection to be made to 37-P6R/3R/7R for Watering of Shift-in-Charge
37-C-01/C-02/C-03/C-04
48) Start P-6/6R and open TRCV-04 (top reflux of 37C-01) and Field Operator
FRCV-09 for flushing 37C-01
49) Start P-3R and open PRCV-3708 for flushing 37C-03/37- Field Operator
C-03
50) Start P-7/7R and open FRCV 10 to flush 37C-04. Field Operator
KEY POINTS :
# DO WOT ALLOW COLUMN LEVELS TO RISE MORE
THAN 70% ON LEVEL INDICATION
42
VBU Operating Manual
HALDIA REFINERY
43
VBU Operating Manual
HALDIA REFINERY
44
VBU Operating Manual
HALDIA REFINERY
residence time in the line, but coke deposition over a long time can not be ruled
out. Hence pressure drop in this line is to be monitored to decide whether cleaning
of this line is required or not. The line is to be cleaned manually by opening the
end blinds at different cross ends.
45
VBU Operating Manual
HALDIA REFINERY
CHAPTER-VI
6.0) FURNACE DECOKING
During the period of operation coke slowly gets deposited on the internal surface
of the furnace tubes. This deposition increases with length of run and severity
of operation. Accumulation of coke deposits on the internal surface of furnace
tubes is detrimental because :
a) It increases the resistance to the Process flow i.e. the Delta P across the
furnace coils builds up and results in gradual T’ put limitation
b) It increases the resistance to heat transfer from the flue gases/flame to the
process fluid and in the process increases the tube metal skin temperature
which reduces the life span of tubes
c) The coke deposits get dislodged from the furnace tubes during some process
upsets end up in the fractionating column flash zone/bottom thus warranting
shutdown for cleaning
Hence it is required to clear the coke deposits from the tubes at regular intervals
and this is achieved by decoking operation. (Post soaker decoking operation
will be required almost once in 12 months in this unit). Decoking is achieved
in 2 stages.
Spalling : Steam is introduced in tubes with furnace on. This causes cooling
action of coke on hot tube surface causing the coke deposits to disintegrate.
The disintegrated coke gets entrained in the steam flow. This removes about
90% of coke deposition.
Burning with air : Introduction of air along with steam into the hot tubes burns
the residual coke deposits and products of combustion are removed by the
steam flow. Air introduction must be gradual and controlled. Otherwise the
resultant burning reaction may result in a run-away temperature of the tube
skin.
The unit is shutdown in the normal manner. It is steamed as per laid down
procedure and the furnace is handed over for necessary preparatory/
blinding/de-blinding jobs to undertake decoking.
6.1 BRIEF ON PAST OPERATIONS WITHOUT SOAKER
Normally the furnace tubes are de-coked when either Delta P across the furnace
or the tube skin temperature become a limitation, which ever may occur earlier.
Typical values for this end of run conditions on various. Occasions just before
going for decoking are listed below to describe the particulars conditions
46
VBU Operating Manual
HALDIA REFINERY
47
VBU Operating Manual
HALDIA REFINERY
48
VBU Operating Manual
HALDIA REFINERY
49
VBU Operating Manual
HALDIA REFINERY
50
VBU Operating Manual
HALDIA REFINERY
CHAPTER-VII
7.0 EMERGENCY HANDLING AND EMERGENCY SHUTDOWN PROCEDURE
There can be situations when the unit is to be shutdown on an emergency basis
consequent upon
→ Failure of feed to the unit
→ Leak in furnace tubes
→ Failure of steam (VM & VB)
→ Power failure
→ Cooling water failure
→ Instrument Air failure
→ Total utility failure
7.1 FAILURE OF FEED TO THE UNIT
There are three number pumps either in offsite or in the unit. In case one goes
under maintenance, two pumps will be available at site. Apparently feed failure
due to non-availability of pump either in offsite or in the unit is. remote.
HOWEVER IT IS TO BE REMEMBERED THAT DURING BOTH ROTARY
PUMPS (44-701-P-101 A/B) FAILURE AT OFFSITE, 37B105 LCV/37B105
NEEDS TO BE BYPASSED IMMEDIATELY TO HAVE SUPPLY FROM
OFFSITE CENTRIFUGAL PUMP.
Try to restart spare feed pump or booster pump as the ease may be. In case all
feed pumps fail or problem is with booster pump, Feed failure with unit will
automatically actuate the “I1” interlocks which will cut off FO & FG, open soaker
BPC, close LV3703B & trip 37P119 A/B. Proceed as follows :
DETAILS OF OPERATION/ACTIVITY OPERATION BY
01) Close stripping steam to 37-C-01 by C/Valve Panel Operator
02) Push emergency shutdown (ESD) switch at auxiliary panel. Panel Operator/
This will close both FO & FG shutdown valves. Open soaker Field Operator
outlet PICV 1301 and open soaker drum pump out C/V
HV1301. Close PIC1401 and LICV3703A in case P119A/B
in line or close LIC3703B in case P2/P2R in line.
03) Watch and verify security taking action in field at all 5 above Field Operator
mentioned control valves.
04)Close fuel oil, fuel gas main isolation valves. Field Operator
05)Close isolation valve of stripping steam to 37C02 Field Operator
51
VBU Operating Manual
HALDIA REFINERY
52
VBU Operating Manual
HALDIA REFINERY
Any leak from the hydrocarbon tube will catch fire and will be visible from furnace
peepholes. Small leak in the heater tube may eventually coke up and will not
warrant emergency shutdown. Operating personnel and supervisor have to
assess the extent of damage and take recourse to either normal or emergency
shutdown. In case of tube rupture, bridge wall temperature will start shooting
up. Smoke will be appearing at stack top. The smoke will go dense with increase
in leak, Sharp rise in stack temperature may also be observed
DETAILS OF OPERATION/ACTIVITY OPERATION BY
01) Push ESD push button in auxiliary panel Panel Operator
02) Stop feed pump and quench oil (P-13/13R) pump Field Operator
03) Close manually Fuel Gas, Fuel Oil and quench control valve Panel Operator
and open on manual soaker outlet PICV1301 in case if it is
not opened
04) Watch & verify all securities have taken action. Close isolation Field Operator
valve on fuel gas, fuel oil in and Pilot gas headers on the
furnace platform near soot blower panel
05) Watch coil inlet pressure near FRCAL’s and when it comes Field Operator
down to 10 kg/cm , close PICV1301, put steam at furnace
outlet and drain/ pump out C107 & C01 to 37B01/run down.
Quench the blow down with flushing fluid followed by water.
Purge the coils to blow down vessel B-1 with VM steam in
reverse direction. Stop flushing fluid injection.
06) Open fire box purging steam and close individual burner and Field Operator
pilot valves
07) Close stripping steam to 37- C-2 Field Operator
08) Close Stripping Steam to 37-C-1 Panel Operator
09) Open H-1/B104 vent to atmosphere after closing VB header Field Operator
valves
10) Stop P8/8A, P-12. Stop other pumps when they lose suction. Field Operator
Close E-8A/B water
11) Flush Feed and Tar circuits with LO from OM&S. Field Operator
Empty out columns, vessels, pippins etc and steam
purge/water wash the unit till all hydrocarbons are
removed from the system. Isolate the furnace (after
installing blinds etc) and hand it over for repairs once
tubes are free of hydrocarbon.
53
VBU Operating Manual
HALDIA REFINERY
54
VBU Operating Manual
HALDIA REFINERY
55
VBU Operating Manual
HALDIA REFINERY
56
VBU Operating Manual
HALDIA REFINERY
07) Hold levels in C-2, C-3 & C-4 and pressures by closing PRCV’s Panel Operator
08) Close stripping steam to 37-C-1 & 37-C-2 (Both Control Valve
and Block Valve) Panel Operator/
09) Open H-1 & B-104 vent & isolate from VB header Field Operator
Field Operator
10) Put VB steam through economizer coil and vent to
atmosphere Field Operator
Start unit as per normal procedure when power is
resumed. Otherwise flush feed and tar circuits with LO
from offsite.
KEY POINTS :
# Reset all solenoid valves before starting.
#Take clearance before starting the pumps
7.5 COOLING WATER FAILURE
This can happen when all the cooling water pumps fail simultaneously. It is quite
rare and is possible only during total power failure.
The overall effects of cooling water failure will be as follows:
→ There will be no water flow through condensers, coolers. Thus, in the absence
of cooling water, there will be no condensation of overhead vapors resulting
in shooting up of column top pressure. Column and reflux drum safety may
pop. (No water to Condensate E-2 A/B, E-6 and Coolers E-7, E-5, E-8 A/B
& E112 A/B)
→ Products going to storage will be at higher temperature, which is no
permissible.
→ Outlet lines of condenses and coolers will start vibrating.
→ No cooling water to pumps
DETAILS OF OPERATION/ACTIVITY OPERATION BY
01) Drastically rduce the unit throughput and bring down coil
outlet temperature to 200 °C. Panel Operator/
Field Operator
02) In case 37C01 pr. increases, HV1501 provided to reduce
the pressure. Panel Operator
03) Close steam to 37C-01 & 37C-02 (Close both C/V and B/V)
Panel Operator/
04) Isolate Fuel Gas and Fuel Oil burners individually and Control Field Operator
57
VBU Operating Manual
HALDIA REFINERY
58
VBU Operating Manual
HALDIA REFINERY
59
VBU Operating Manual
HALDIA REFINERY
60
VBU Operating Manual
HALDIA REFINERY
61
VBU Operating Manual
HALDIA REFINERY
CHAPTER - VIII
8.0 SAMPLES AND TESTS
The table gives the tentative Schedule of Laboratory tests to be performed
No Test Feed Gases STB VB Gas 37-B-2
Required Gas- Tar Oil
oline
1. Specific
Gravitity
2. Viscosity Once in Once in
Alternate a Shift
Day
3. Sulphur When When
Required Required
4. H2S
5. CCR When,
Required
6. Flash. Pt Daily
Once
7. Octane When
Number Required
8. pH Daily
Once
9. FO stability When
Required
62
VBU Operating Manual
HALDIA REFINERY
CHAPTER - IX
9.0 CONTROL LIMIT
In order to ensure agreed product specification, control limit shall be applied to
individual stream as described in 9.9 of Procedure Manual
VB TAR KV CST AT 50 DEG C 200 - 350 CST
VB TAR FLASH DEG C (MIN) 85 - PREFERABLE
IS 100 Deg C
VB PEED KV CST 800 - 2000 CST(4301
@ 50 Deg C CST @100 Deg C
design)
@ 110 Deg C
9.1 PROCEDURE/ACTIVITIES ACTION/FORM
9.1.1 Operating conditions to be adjusted & maintained within PANEL./
control limit as instructed by DMPN/S.PNE/PNE FIELD OPERATOR
9.1.2 VB gas oil/gasoline colour shall be checked twice in each FIELD OPERATOR
shift
9.1.3 Slop processing in Visbreaker in the flash zone to be
monitored as per the following : a> Flow indication in the
panel PANEL./OPERATOR
b> 37-C-1 bottom temperature PANEL./OPERATOR
c> 37-C-1 10th tray temperature PANEL./OPERATOR
d> 37-C-1 reflux load PANEL./OPERATOR
e> Colour of gas oil FIELD OPERATOR
f>37-B-5 draining FIELD OPERATOR
9.1.4 In case of VB Tar flash point being lower than the control
limit, the following actions shall be taken
a> stripping steam to 37-C-1 to be checked / increased PANEL./OPERATOR
b> Gas oil withdrawal to be increased watching 10th tray PANEL./OPERATOR
temperature
9.1.5 In case of TAR viscosity being higher than the control limit, the following actions
shall be taken:
PROCEDURE/ACTIVITIES ACTION/FORM
a> COT to be increased, within restricted operable limit PNE/SPNE/ DMPN
(435-445 Deg C) if feed viscosity is within the control limit
63
VBU Operating Manual
HALDIA REFINERY
PROCEDURE/ACTIVITIES ACTION/FORM
b> Drop gas oil inside the column taking into account flash PNE/SPNE/
point of VB Tar PANEL OPERATOR
c> Consult with Planning & Coor-dination for reduction of DMPN
feed viscosity within the Control Limit for checking the routing
Of VDU, PDA & BTU
d> Add cutter stock (LO/SO) after consulting with P&C DMPN
64
VBU Operating Manual
HALDIA REFINERY
CHAPTER - X
10.0 SAFETY
Visbreaking Unit (U-37) is an existing one where all safety protection facilities are
prevailing i.e. fire water net work, pill boxes, fire extinguishers etc. However to take
care of additional area (soaker area), Fire Water Network has been modified.
Extra pill box (fire alarm) has been installed. The general guidelines for fire fighting
procedures for different equipments and systems are provided in Annexure-1. To
take care of the plant operational safety additional interlocks and alarms etc. have
been provided. These are stated in the following paragraphs.
10.1 The following are the interlocks in U-37, the activities of which will force a unit
shutdown.
TAG NO. LOCATION SERVICE SET VALVE ACTION
FIC3702 F01 PASS #1 FEED 15 M3/HR FUEL SUPPLY
CUTOFF,
SOAKER
BPCV OPEN,
P119 A/B TRIP,
LV3703 B
CLOSE.
FIC3703 F01 PASS #1 FEED 15 M3/HR FUEL SUPPLY
CUTOFF,
SOAKER
BPCV OPEN,
P119 A/B TRIP,
LV3703 B
CLOSE.
ESD AUX CONSOLE MANUAL FUEL SUPPLY
(PUSH ACTIVATION CUT OFF,
BUTTON) SOAKER
BPCV OPEN,
P119 A/B TRIP,
LV3703 B
CLOSE, HV13
01 OPEN.
PIC 3701 FEED PUMP FEED 40.0 KG/ FEED PUMPS
DISCH- CM2G P1/P1R/ P1B
ARGE TRIPPED
10.2 The following are the interlocks in U-37. The activation of the same is accompanied
by a hardware alarm annunciator. Immediate operator intervention on activation of
these interlocks is required which otherwise may cause the unit shutdown.
65
VBU Operating Manual
HALDIA REFINERY
66
VBU Operating Manual
HALDIA REFINERY
67
VBU Operating Manual
HALDIA REFINERY
CHAPTER - XI
U-37 (VBU) INTERLOCK
11.0 IN CASE OF LOW FEED IN EITHER PASS ( F02 & F03 )
• F.O. SUPPLY AND ON OFF VALVES CLOSE.
• SOAKER B.P.C. OPEN.
• 37 P-2/2R STEAM CLOSE (37 C-1 LCV-05)
• F.G. SUPPLY OFF.
• 37P119A AND P119B STOP.
IN CASE OF EMERGENCY SHUT DOWN BUTTON PRESS ( RED COLOUR)
ESD.
• F.O. SUPPLY AND RETURN ON/OFF VALVES CLOSE.
• SOAKER BPC OPEN (SOAKER TOP PC1301)
• 37 P-2/2R STEAM CLOSE (37 C-1 LCV-05)
• F.G. SUPPLY OFF.
• 37P-119A AND P-119B STOP.
• 37HV1301 OPEN (SOAKER BOTTOM)
37 P-13/13R INTERLOCK
37FX1303 FLOW COMES BELOW 8 M3/HR 37P-13/13R TRIP. (PLEASE
OPERATE THE BY-PASS SWITCH AND START THE PUMP THEN WITHDRAW
BY-PASS)
37 P-121A/121B INTERLOCK
37 P-121A OR 121B DISC. PRESSURE COMES BELOW 13 KG/CM2 OTHER
PUMP WILL TAKE AUTO START PROVIDED IT IS IN AUTO.
IF FURTHER DISC. PRESSURE COMES DOWN TO 10 KG/CM2 OR LESS 37
P-119A/119B WILL TRIP.
EMERGENCY DE-PRESSURISATION SYSTEM
SWITCH ON FOR OPENING 32HV1501 LOCATED IN AUXILARY CONSOLE.
FO PRESSURE LESS THAN 2.6 KG/CM FURNACE TRIP.
FEED PUMP P01A/B/R INTERLOCK
FEED PUMP PRESSURE MORE THAN 37 KG/CM2 BYPASS LINE CONTROL
VALVE FULL OPEN.
FEED PUMP PRESSURE MORE THAN 40 KG/CM2 FEED PUMP TRIP.
68
VBU Operating Manual
HALDIA REFINERY
CHAPTER - XII
SECTION - 1
69
VBU Operating Manual
HALDIA REFINERY
HOT PUMPS
• Stop the pump as per procedure
• Before depressurizing. Close warm up b/v
• Close gland sealing, flushing oil.
• Stop steam to mechanical seals
• Allow the pump to cool.
• Flush the pump with FLO, if material is heavy. Drain/depressurize the pump.
• Keep the water house running.
• Incase of high pour point materials like SR, RCO, VR, Wax, etc. open FLO to
suction and run the pump to displace heavy materials into discharge circuit
• If FLO is not available drain preferably through cooler or drain gradually.
12.1.2 HEAT EXCHANGER/CONDENSER/COOLER/ AIR FIN COOLER/
REBOILER:
• ISOLATE AND DECOMMISSION THE EXCHANGER/ CONDENSER/
COOLER/REBOILER AS PER THE PROCEDURE.
• Deenergise the motor of Air Fin Cooler/ Condenser. Ensure that “DO NOT
OPERATE, MEN AT WORK” board is put on the switch
• Flush the equipment handling heavy material with FLO/Steam
• Drain Hydrocarbons to CBD or, OWS. Open the vent valves to ensure the
complete draining
• Provide blinds/W.O towards the exchanger on both the side.
• Give steam connection on top nozzle. Drain water side (it need not be steamed)
• Steam for 4 hours
• Water flush condensers and coolers handling light hydrocarbons.
• Release the equipment for maintenance jobs.
12.1.3 FURNACE:
• Shut down the furnace as per procedure and blind fuel gas lines.
• Open the damper and air registers fully
• Isolate and flush fuel oil circuit and blind fuel oil lines.
• Steam purge the heater coils to displace oil contents to column. (Water washing
can follow for complete coil flushing if permissible, depending upon metallurgy
of coil).
• Passivate the coils wherever required
70
VBU Operating Manual
HALDIA REFINERY
71
VBU Operating Manual
HALDIA REFINERY
• Steam the system for 6 hrs. Steam will wet the entire column such that flange
opening for blinding and W.O. can be done safely.
• Install blinds on all inlet and outlet nozzles except steam and top reflux line.
• Keep the drains and vents of all instrument tapings open.
• Steam the column for 6-8 hrs.
• Ensure that sufficient steam issues from all the wedge openings, keep the vent
open
• Do not exceed working pressure of column while steaming
• Provide water connection to reflux line
• Keep the column drain fully open
• Stop steaming and water wash for above 4 hrs.
• Do not allow water level to build up in the column.
• Repeat steaming and water washing
• Open top manway cover
• Carry out gas test by explosimeter
• If gas test is positive, box up manway and repeat steaming and water washing.
• If gas test is negative, give clearance to open rest of the manholes.
• Get steam and top reflux lines blinded
• Ensure for proper ventilation in the column
• Provide air hose, if required.
• Give clearance for inspection/maintenance jobs.
12.1.6 FLARE HEADER:
• Ensure that all equipment connected with flare system are depressurized after
shut down.
• Close battery limit valve of flare header
• Provide steam connection if not there
• Introduce a small quantity of steam.
• Give clearance to provide blinds/wedge opening on the system wherever
required with steam on.
• Open the drains and vents of all instrument and of knock-out drum.
• Stop steaming
• Water wash the flare header upto battery limit/knock out drum.
72
VBU Operating Manual
HALDIA REFINERY
73
VBU Operating Manual
HALDIA REFINERY
74
VBU Operating Manual
HALDIA REFINERY
75
VBU Operating Manual
HALDIA REFINERY
• All instrument tappings drain points, distributors, downcomers, inlet and outlet
nozzles are clear
• All internals are fitted properly
• All inside fittings like distributors, thermowells flats of level indicators, etc are in
position.
• Tray manway covers are boxed up
• Manholes are boxed up on 4 bolts while ensuring that nobody is left inside.
• Tray manway and manholes should be boxed up in presence of production staff.
• All manway covers are boxed up as above.
• Blinding/deblinding is complete as per master blind list.
• NRV’s are installed in their proper direction
• Column bottom drains are connected properly.
• Safety valves are installed and lined up
• The instruments are in their respective position
• The column is ready for service
76
VBU Operating Manual
HALDIA REFINERY
CHAPTER - XII
SECTION - 2
77
VBU Operating Manual
HALDIA REFINERY
• Open warm-up (across NRV of discharge line) to heat the pump before starting.
Ensure that while doing so, the dischrge pressure of the running pump does not
fall below operating pressure.
• Open suction valve very slowly for vacuum column pumps.
• Pinch/close the warm-up line valve after the pump is on full load.
• If external seal Oil pumps are provided, the same are to be started and after
adjusting for the rated discharge pressure in the presence of maintenance,
auto change over of the pumps are to be verified before putting one of them in
auto mode and the remaining in manual mode. The one in manual mode is to
be kept running. The casing is to pressurized slowly and after checking for
leaks, etc, main driver is to be started. Before operating the seal oil pumps,
check the seal oil tank level and top up the same , if required.
• If pump is run by a steam turbine, then VB is to be lined up first and then
condensate from VM line is to be drained before charging steam to turbine.
Governer Oil sump level to be checked and made up before starting turbine.
12.1.1.3 SHUT DOWN PROCEDURE:
• Close the discharge b/v fully
• Stop the motor
• Open ward up b/v for hot pump to keep it hot. Ensure that the pump does not
rotate.
• If main driver is a steam turbine, close Vm valve first and then close VB valve .
Close discharge valve of the pump first to stop it from anti-rotating(if control
valve is there at discharge, the same is to be closed prior to closing of steam
valve) and then, close suction valve. Keep seal Oil pumps running. If pump is to
be handed over to maintenance, start depressuring the casing by opening the
vent to compressor suction or, to flare, as is the case.
12.1.14 CHANGE OVER OF THE PUMPS
• Start the standby pump as per standard procedure
• Open the discharge valve gradually. Simultaneously close the discharge valve
of other pump keeping watch on the discharges pressure gauge/flow.
• Switch-off the originally running pump.
• Open warm-up valve of hot pump to keep it warm.
12.1.2 RECIPROCATING PUMPS:
This is a positive displacement pump. Hence an outlet must be available for the
liquid displaced otherwise the system will get over pressurized.
In reciprocating pump liquid is displaced from suction to discharge by the
78
VBU Operating Manual
HALDIA REFINERY
79
VBU Operating Manual
HALDIA REFINERY
80
VBU Operating Manual
HALDIA REFINERY
81
VBU Operating Manual
HALDIA REFINERY
CHAPTER - XIII
13.0 FIRE AND SAFETY
Visbreaking of atmospheric and vacuum residuum is carried out at high temperature
(460 0C) and elevated pressure of 12.0 kg/cm2 g. Thermal cracking produces large
amount of hydrocarbon gases, gasoline, gas oil and fuel oil. The presence of all
these products, high temperature and pressure, fired heaters make Visbreaking
an explosion and fire hazard process.
Thermal sulphur decomposition in the feed results in the formation of hydrogen
sulphide, which is characterised by specific toxicity when present in low
concentration. Due to corrosion and formation of pyrophoric ferrous compounds,
it should always be considered that pyrophoric ferrous compound will catch fire in
air whenever any equipment is opened for repair.
The most dangerous places in the unit are pump house area, sewerage manholes,
pits, hot piping, tube heaters, columns and heat exchangers. In all such places in
case of deviation from process conditions, wear or damage of equipment or piping
gas or oil release may occur which may cause an explosion, fire or injury to people.
Therefore, the operating personal should exercise special care in such dangerous
areas.
Self-ignition temperatures of products present in the units are:
Gasoline - 415-530 0C
Vacuum residues - 280-300 0C
Visbreaker tar - 270 0C
Petroleum coke - 185-200 0C
Gas oil - 300-350 0C
13.1 FIRE FIGHTING FACILITIES
The fire igniting/prevention facilities involve, fire hydrant system, fixed foam system,
fire extinguishers, fire fighting steam and fire alarms.
13.1.1 FIRE HYDRANT SYSTEM
An underground header of 8" size is laid between AVU & VBU with 5 numbers of
hydrant points. One jockey pump, 3 nos. of electrical pumps and 3 nos. of diesel
pumps are installed in water block to maintain ire hydrant pressure and for boosting
the pressure to deal with any emergency situation. Cooling water sprinkling system
on 16P2 is also provided.
13.1.2 FIRE EXTINGUISHERSThe use of fire extinguishers is limited to small fires
when the fire has not yet spread out. The fire extinguishers should always be easily
available in the unit so that small fire does not take the shape of a big fire.
Different types of extinguishers are used for different types of fires.
82
VBU Operating Manual
HALDIA REFINERY
83
VBU Operating Manual
HALDIA REFINERY
84
VBU Operating Manual
HALDIA REFINERY
85
VBU Operating Manual
HALDIA REFINERY
from height. Safety helmet must be worn in day to day plant movement and in
construction/shutdown activities in the unit,
(b) Safety glasses/goggles: -These are to protect eyes from any injury. Different
types of safety glasses are available to be used for chemical handling, furnace
operation welding, grinding etc.
(c) Safety face shield: - To protect eyes and face from any possible hazard due to
chemical/liquid hydrocarbon splash and backfires.
(d) Safety Gloves:
(1) Leather Gloves: -Must be used in day to day operational activities to safeguard
hands against injury due to rough surfaces.
(2) Asbestos Gloves:- To be used while working on hot surfaces.
(3) Rubber Gloves:- To be used in handling of corrosive chemicals.
(e) Safety Belts:- These are to protect against falls from height.
(f) Safety Shoes:- To be used for toe protection/liquid spills on foot.
(g) Safety suits and Aprons: - Asbestos suit to be used in case of a movement in
hot area for a very short time. PVC suit/apron must be used while handling
corrosive chemicals.
(h) Air Purifying Devices:
(1) Filters:- Mouth and nose filters are used in dusty atmosphere.
(2) Canister Masks:- Type CC to be used against toxic gas, petroleum vapours,
Cl2, SO2 etc. Type C.G. to be used against acidic gases.
These canister ,masks can only be used in low vapour concentration (less
than 1 % in atmosphere) and for a period of half an hour maximum.
(3) Breathing Air Apparatus:
(a) Blow Man Breathing Apparatus: These are externally supplied air type masks.
(b) Self contained breathing Apparatus: This type of mask has compressed air
cylinder, which can last for 30 minutes.
Both these masks are to be used against all types of toxic/acidic gases in high
concentrations.
86