ID Task Mode Nombre de tarea Duration Start Finish Predecessors

Successors
Fixed CostCost
Accrual

1 Comienzo 0 days Sat 4/21/18 Sat 4/2 2;3 Prorated $0


1/18

2 Proceso constructivo del muro pantalla 71 days Sat 4/21/18 Thu 7/1 1 23 Prorated $ 398772750
9/18

3 Localización trazado y replanteo 1 day Sat 4/21/18 Mon 4 1 4 Prorated $ 3454200


/23/18

4 Descapote y limpieza del terreno 1 day Mon 4/23/18 Tue 4/2 3 5;6 Prorated $ 18818550
4/18

5 Construcción de la viga guía 16 days Tue 4/24/18 Tue 5/1 4 10 Prorated $ 138000000
5/18

6 Sistema de encofrado 6 days Tue 4/24/18 Wed 5 4 7 Prorated $0


/02/18

7 Colocación de acero 4 days Wed 5/02/18 Mon 5 6 8 Prorated $0


/07/18

8 Colocación del concreto 1 day Mon 5/07/18 Tue 5/0 7 9 Prorated $0


8/18

9 Curado del concreto 5 days Tue 5/08/18 Tue 5/1 8 Prorated $0


5/18

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: Ejemplo 1 - Precedencias Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/20/2018 9:29 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Mode Nombre de tarea Duration Start Finish Predecessors
Successors
Fixed CostCost
Accrual

10 Excavación de la zanja 5 days Tue 5/15/18 Mon 5 5 11 Prorated $ 10000000


/21/18

11 Colocación de la armadura 7 days Mon 5/21/18 Tue 5/2 10 12 Prorated $ 4500000


9/18

12 Colocación de las juntas 6 days Tue 5/29/18 Wed 6 11 13;14 Prorated $ 3000000
/06/18

13 Hormigonado 9 days Wed 6/06/18 Mon 6 12 16;17 Prorated $ 100000000


/18/18

14 Colocación del hormigón 2 days Wed 6/06/18 Fri 6/0 12 15 Prorated $0


8/18

15 Curado del hormigón 7 days Fri 6/08/18 Mon 6 14 Prorated $0


/18/18

16 Construcción de la viga de coronación 16 days Mon 6/18/18 Sat 7/0 13 21 Prorated $ 62000000
7/18

17 Sistema de encofrado 6 days Mon 6/18/18 Mon 6 13 18 Prorated $0


/25/18

18 Colocación de acero 4 days Mon 6/25/18 Fri 6/2 17 19 Prorated $0


9/18

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: Ejemplo 1 - Precedencias Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/20/2018 9:29 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Mode Nombre de tarea Duration Start Finish Predecessors
Successors
Fixed CostCost
Accrual

19 Colocación del concreto 1 day Fri 6/29/18 Sat 6/3 18 20 Prorated $0


0/18

20 Curado del concreto 5 days Sat 6/30/18 Sat 7/0 19 Prorated $0


7/18

21 Excavación y fresado 8 days Sat 7/07/18 Tue 7/1 16 23;22 Prorated $ 54000000
7/18

22 Impermeabilización 2 days Tue 7/17/18 Thu 7/1 21 Prorated $ 5000000


9/18

23 Fin 0 days Thu 7/19/18 Thu 7/1 21;2 Prorated $0


9/18

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: Ejemplo 1 - Precedencias Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/20/2018 9:29 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 3
Fixed Cost May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 Dec

2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1

$0

$0

$ 3454200

$ 18818550

$ 138000000

$0

$0

$0

$0

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: Ejemplo 1 - Precedencias Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/20/2018 9:29 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 4
Fixed Cost May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 Dec

2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1

$ 10000000

$ 4500000

$ 3000000

$ 100000000

$0

$0

$ 62000000

$0

$0

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: Ejemplo 1 - Precedencias Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/20/2018 9:29 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 5
Fixed Cost May 2018 June 2018 July 2018 August 2018 September 2018 October 2018 November 2018 Dec

2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1

$0

$0

$ 54000000

$ 5000000

$0 19.07

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: Ejemplo 1 - Precedencias Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/20/2018 9:29 PM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 6