CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR

HEAD SUBHEAD YEAR TOTAL PROVISION


2016
PROVISION FOR CONSTRUCTION

BRIEF DESCRIPTION OF BUILDINGS


BUILDING Frame Wall Roof Floor Ceiling
a Shop lots
b Tower A
c Tower B

BREAKDOWN OF PRELIMINARY COST ESTIMATE

1 PRELIMINARIES & DESIGN AND BUILD ELEMENTS


2 PILING/SPECIAL FOUNDATION
Type and Size : Precast concrete square pile 300mm x 300mm and 280mm x 280mm
a Concrete Piles (Provisional)

3 BUILDING Drawing No. Floor Area m2 Cost/m2


a Shop lots 5,655.00 RM568.60
b Tower A 5,198.40 RM444.02
c Tower B 5,266.80 RM453.67

4 INTERNAL SERVICES (All in PC Sums inclusive of Profit and Attendance)


a Electrical Services
Electrical Installation
Lift
Communication
Special
b Mechanical Services

Sanitary appliances
Plumbing Installation
Refuse Disposal

Builder's Work in Connection


Builder's Profit

SUBTOTAL carried forward


(PWD 142A - Rev.`91)

DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS


R

RM14,176,027.96

RM11,365,177.37

Window Standard
Normal
Normal
Normal

COST (RM)

RM541,198.92

RM972,108.60
RM972,108.60

RM7,913,008.92
RM3,215,405.25
RM2,308,214.51
RM2,389,389.16

RM782,587.64

RM249,281.07
RM113,338.11
RM44,267.79
RM5,860.51
RM97,849.62
RM218,513.37
RM2,197.69

RM24,488.57
RM26,790.91

RM10,208,904.08
BREAKDOWN OF PRELIMINARY COST ESTIMATE (CONT'D)
SUBTOTAL brought forward
5 EXTERNAL WORKS (6% of item 2-4)
a Site Preparations and Earthworks
b Roads, Carpark and Pavement
c Surface Water Drainage
d Fencing and Gates
e Water Reticulation
f Sewer System and Reticulation
g Open Walkway
h TNB Sub Station
i Laluan Bomba

6 PROVISIONAL SUMS (5% of item 2-5)

s 7 VARIATION OF PRICES (3% of item 2-5)


8 CONTRIBUTION FEE TO LOCAL & UTILITY AUTHORITY
a TNB, TM, IWK,SYABAS, Dewan Bandaraya Kuala Lumpur

###
9 MISCELLANEOUS
a Soil Investigation & Survey Works
b Land Surveyor Fees

10 CONTINGENCIES (2% of item 2-5)


ALL IN UNIT RATES TOTAL (items 1 to 10)

Total Floor Area m2 : 16120.20 Cost/m2 : 751.08 RM12,107,565.67


11
11 SUPERVISION @ 2.00% of construction cost (Item 1 -6)
12 PROFESSIONAL FEES
a Architect
b Quantity Surveyor
c Civil & Structural Engineer 12% of construction cost
d Mechanical & Electrical Engineer
e Government Service Tax @ 5%
f Reimbursables (30% from a-d)

TOTAL COST OF PROJECT


Quantity Surveyor / Estimating Officer Timb. Setiausaha Bhgn. (Teknikal) Setiausaha
Bhgn. Pembangunan & Perolehan Bhgn. Pembangunan & Perolehan

Date: Date: Date:


COST (RM)
RM10,208,904.08
RM580,062.31
-
-
-
-
-
-
-
-
-

RM271,300.00
RM 576,210.98

RM271,300.00
RM307,432.95
RM 150,000.00
RM150,000.00

RM80,000.00
RM50,000.00
RM30,000.00

204,955.35

RM12,107,565.67
RM13,000.00
RM227,303.55
RM1,841,158.73

RM1,363,821.28

RM68,191.06
RM409,146.39

RM14,176,027.96
Bhgn. Pembangunan & Perolehan
NOTES ON FILLING OF PRELIMINARY DETAILED ABSTRACT FORM (PDA)

1.0 GENERAL INFORMATION

1.1 The information given on this Detailed Abstract is for Government use only.

1.2 No portion of the form is to be left blank. Items not applicable in any particular c
them. If any item is included under 'BUILDING' this shall be stated in the 'COST' c

2.0 TOTAL PROVISION

2.1 Total Provision shall be the amount given by the Client Department as the amoun
shall be given together with the project brief. If this information is not available i

3.0 PROVISION FOR THE CONSTRUCTION

3.1 Provision with Construction shall be the Total Cost of Project as shown. For revise
shall be the Total Cost of project in previously approved PDA.

4.0 BRIEF DESCRIPTION OF BUILDINGS

4.1 The following abbreviations shall be used in completing the 'Brief description of B

Al - Aluminium CCR - Coloured Cement MT - Mosaic Tiles


Rendering

AB - Acoustic Board CHB - Concrete Hollow MFB - Metal Fibre Board


Bricks

AC - Asbestos Ff - Fairface MFW - Metal Framed


Cement Screen Wall

BK - Common Brick FSM - Fairface Screen OGB - Ordinary Gypsum


Wall Board

BRF - Built-up FCB - Fibre Cement PF - Plastered finish


Roofing Felt Board

CBk - Cement Sand GMD - Galvanised Metal PCM - Precast Concrete


Brick Decking Members

CR - Cement GWL - Glass Wool Board Pqt - Parquet


Rendering

CSMT- Casement GWT - Glazed Wall Tiles QT - Quarry Tiles


CT - Ceramic Tiles HP - Hyrib Plaster RC - Reinforced
Concrete

Con - Concrete LV - Louvre RGB - Reinforced Gypsum


Board

Co.T - Concrete Tiles MS - Mosaic Slab St. - Steel

Both the base material and the finish shall be given in the case of floors, walls an

Con./VT RC/WCR

Both the base material or the type of suspension/framing and the finish shall be

T/WCB Al./MFB

4.2 The standard of the building relates to the general standard of finishes rather tha
one the following three categories :

High, normal, low.

(i)

NOTES ON FILLING OF PRELIMINARY DETAILED ABSTRACT FORM (PDA) (CONT'D)

5.0 PILING/SPECIAL FOUNDATION

5.1 Each type and size of Piling/Special Faoundation and its cost shall be stated sepa

6.0 BUILDING

6.1 The cost for the building shall be exclusive of all services.

6.2 The buildings to be listed under item 3 shall refer to the same buildings as listed
6.3 The Floor Area shall mean the Gross Floor Area of all enclosed spaces fulfilling th
measured flat on plan to the internal face of the enclosing walls.

6.4 The Drawing Numbers to be stated shall only be those of the Architectural floors
Structural and other detailed drawing numbers need not be stated.

7.0 INTERNAL SERVICES

7.1 The cost for the internal services shall be inclusive of Profit and Attendance and
where applicable.

8.0 VARIATION OF PRICES

8.1 The amount to be allowed for Variation of Price shall be based on the projected in
index as issued by the Department of Statistics, or 5% of the value of the builder

9.0 CONTIGENCIES

9.1 Contigencies shall not exceed 10 percent of total items 1 to 8.

10.0 PROFESIONAL FEES

10 The amount of Professional fees for each Consultant shall be inserted in the 'Cos
(ii)
ny particular case shall have a dash inserted against
in the 'COST' column.

t as the amount approved for the project and which


not available it shall be left blank.

wn. For revised PDA, Provision for Construction

description of Buildings' :

T - Timber

Tyn - Tyrolean

Tz - Insitu Terrazo

TB - Timber Boarding

TS - Timber Strip

TT - Terazzo Tiles

TSW - Timber Framed


Screen Wall

VT - Vinyl Tiles
WCB - Wood Cement Board

orced Gypsum WCR - Waterproof Cement


Rendering

floors, walls and flat roofs, thus :

finish shall be given in the case of ceiling, thus :

shes rather than to construction and shall be given as

be stated separately

dings as listed under 'Brief Description of buildings'.


ces fulfilling the functional requirements of the building

tectural floors plans, sections and elevations.

endance and all builders work in connection therewith

he projected increase in the relevant building cost


of the builder's work.

ed in the 'Cost' column.


CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR

ELEMENTAL COST PLAN : SHOP LOTS

GROSS FLOOR AREA: 5,655.00 M²


60,869.85 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

1.0 SUB-STRUCTURAL ELEMENTS

1.1 WBLFF 674,792.28 11.09 15.3%

Elemental Total 674,792.28 11.09 15.3%

2.0 SUPERSTRUCTURAL ELEMENTS

2.1 Frame 614,727.55 10.10 13.9%

2.2 Upper Floor 197,311.32 3.24 4.5%

2.3 Roof 230,993.62 3.79 5.2%

2.4 Staircase And Handrailing 29,084.27 0.48 0.7%

Elemental Total 1,072,116.76 17.61 24.3%

3.0 EXTERNAL WALLING AND FINISHES

3.1 External Walls 528,539.50 8.68 12.0%

3.2 Windows 677,305.00 11.13 15.3%

3.3 External Wall, Floor and Ceiling Finishes 130,222.00 2.14 2.9%

B/I/1
CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR

ELEMENTAL COST PLAN : SHOP LOTS

GROSS FLOOR AREA: 5,655.00 M²


60,869.85 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

Elemental Total 1,336,066.50 21.95 30.2%

4.0 INTERNAL WALLING

4.1 Walls 158,201.74 2.60 3.6%

4.2 Doors 174,447.00 2.87 3.9%

Elemental Total 332,648.74 5.46 7.5%

B/I/2
CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR

ELEMENTAL COST PLAN : SHOP LOTS

GROSS FLOOR AREA: 5,655.00 M²


60,869.85 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

5.0 INTERNAL FINISHES

5.1 Wall Finishes 159,501.20 2.62 3.6%

5.2 Floor Finishes 220,669.00 3.63 5.0%

5.3 Ceiling Finishes 94,403.05 1.55 2.1%

Elemental Total 474,573.25 7.80 10.7%

6.0 SERVICES

6.1 Sanitary Fittings and Plumbing Installations 529,010.00 8.69 12.0%

Elemental Total 529,010.00 8.69 12.0%

Total Estimated Building Cost 4,419,207.53 72.60 100.00%

B/I/3
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

RC pile cap, column stump,


ground beam,ground slab,
waterproofing and antitermite

Industrialised Building System


(Frame, Floor and Staircase)

RC suspended floor slab

Metal decking on steel trusses

Staircase Finishes and


Handrailing

115mm thick clay brickwall

Powder coated aluminium


casement windows with
glazing

Generally plaster and painting


for walls, cement screed to
floor, plaster and painting and
UAC suspended panel to
ceiling,

B/I/4
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

Generally, 115mm thick clay


brickwall with gypsum board

Solid door, flush door and


acoustic door

B/I/5
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

Plaster and painting and


ceramic wall tile

Cement screed, ceramic tiles


and homogenous tiles

Plaster and paint and UAC


suspended ceiling

Allowance for good quality


sanitary wares and fittings and
plumbing installations

B/I/6
CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR

ELEMENTAL COST PLAN : TOWER A

GROSS FLOOR AREA: 5,198.40 M²


55,955.06 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

1.0 SUB-STRUCTURAL ELEMENTS

1.1 WBLFF 147,686.54 2.64 5.2%

Elemental Total 147,686.54 2.64 5.2%

2.0 SUPERSTRUCTURAL ELEMENTS

2.1 Frame 874,214.93 15.62 30.5%

2.2 Upper Floor 490,624.99 8.77 17.1%

2.3 Roof 135,574.27 2.42 4.7%

2.4 Staircase And Handrailing 24,083.37 0.43 0.8%

Elemental Total 1,524,497.56 27.25 53.3%

3.0 EXTERNAL WALLING AND FINISHES

3.1 External Walls 64,356.19 1.15 2.2%

3.2 Windows 102,304.51 1.83 3.6%

B/I/3
CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR

ELEMENTAL COST PLAN : TOWER A

GROSS FLOOR AREA: 5,198.40 M²


55,955.06 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

3.3 External Wall, Floor and Ceiling Finishes 128,036.59 2.29 4.5%

Elemental Total 294,697.29 5.27 10.3%

4.0 INTERNAL WALLING

4.1 Walls 68,930.78 1.23 2.4%

127,776.67
4.2 Doors - 0.0%

Elemental Total 196,707.45 1.23 2.4%

B/I/4
CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR

ELEMENTAL COST PLAN : TOWER A

GROSS FLOOR AREA: 5,198.40 M²


55,955.06 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

5.0 INTERNAL FINISHES

5.1 Wall Finishes 104,331.89 1.86 3.6%

5.2 Floor Finishes 157,355.57 2.81 5.5%

5.3 Ceiling Finishes 30,624.75 0.55 1.1%

Elemental Total 292,312.21 5.22 10.2%

6.0 SERVICES

6.1 Sanitary Fittings and plumbing installations 406,930.74 7.27 14.2%

Elemental Total 406,930.74 7.27 14.2%

Total Estimated Building Cost 2,862,831.79 48.88 95.54%

B/I/5
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

RC pile cap, column stump,


ground beam,ground slab,
waterproofing and antitermite

Industrialised Building System


(Frame, Floor and Staircase)

RC suspended floor slab

Metal decking on steel trusses

Staircase Finishes and


Handrailing

115mm thick clay brickwall

Powder coated aluminium


casement windows with
glazing

B/I/6
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

Generally plaster and painting


for walls, cement screed to
floor, plaster and painting and
UAC suspended panel to
ceiling,

Generally, 115mm thick clay


brickwall

Solid door and flush door

B/I/7
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

Plaster and painting and


ceramic wall tile

Cement screed, ceramic tiles


and homogenous tiles

Plaster and paint and UAC


suspended ceiling

Allowance for good quality


sanitary wares and fittings and
plumbing installations

B/I/8
CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH SEKOLAH KEBANGSAAN BANDAR BARU SUNGAI L
YANG MENGANDUNGI 24 BILIK DARJAH DAN KEMUDAHAN BERKAITAN DI DAERAH KUALA MUDA, KEDAH

ELEMENTAL COST PLAN : MECHANICAL & ELECTRICAL SERVICES

GROSS FLOOR AREA: 4,676.00 M²


50,332.00 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

1.0 MECHANICAL SERVICES

1.1 Air-conditioning & Ventilation System 330,000.00 6.56 32.0%

1.2 Fire Fighting & Protection System 75,000.00 1.49 7.3%

1.3 Internal Cold Water 65,000.00 1.29 6.3%

1.4 Internal Sanitary 47,500.00 0.94 4.6%

Elemental Total 517,500.00 10.28 50.2%

2.0 ELECTRICAL SERVICES

2.1 External Telephone Services 20,000.00 0.40 1.9%

2.2 Main Switchboard & Earthing 50,000.00 0.99 4.8%

2.3 Sub-Switchboards & Distribution Boards 42,000.00 0.83 4.1%

2.4 Main and Sub-main Cabling 27,000.00 0.54 2.6%

2.5 Final Electrical Wiring 115,000.00 2.28 11.1%

2.6 Electrical Fittings 75,000.00 1.49 7.3%

2.7 Internal Telephone System 30,000.00 0.60 2.9%

2.8 Information Technology Infrastructure System 75,000.00 1.49 7.3%

2.9 Lightning Protection & Earthing System 40,000.00 0.79 3.9%

2.10 MATV System 10,000.00 0.20 1.0%

2.11 Conference/Audio Visual System 30,000.00 0.60 2.9%

Elemental Total 514,000.00 10.21 49.8%

Total Estimated M&E Cost 1,031,500.00 20.49 100.00%

B / II / 1
CADANGAN MEMBINA DAN MENYIAPKAN SEBUAH SEKOLAH KEBANGSAAN BANDAR BARU SUNGAI L
YANG MENGANDUNGI 24 BILIK DARJAH DAN KEMUDAHAN BERKAITAN DI DAERAH KUALA MUDA, KEDAH

ELEMENTAL COST PLAN : MECHANICAL & ELECTRICAL SERVICES

GROSS FLOOR AREA: 4,676.00 M²


50,332.00 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

B / II / 2
SAAN BANDAR BARU SUNGAI LALANG 2
DAERAH KUALA MUDA, KEDAH

Remarks

B / II / 3
SAAN BANDAR BARU SUNGAI LALANG 2
DAERAH KUALA MUDA, KEDAH

Remarks

B / II / 4
CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR
ELEMENTAL COST PLAN : TOWER B

GROSS FLOOR AREA: 5,266.80 M²


56,691.31 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

1.0 SUB-STRUCTURAL ELEMENTS

1.1 WBLFF 149,629.78 2.64 5.1%

Elemental Total 149,629.78 2.64 5.1%

2.0 SUPERSTRUCTURAL ELEMENTS

2.1 Frame 885,717.76 15.62 30.0%

2.2 Upper Floor 497,080.58 8.77 16.8%

2.3 Roof 137,358.14 2.42 4.7%

2.4 Staircase And Handrailing 31,600.80 0.56 1.1%

Elemental Total 1,551,757.28 27.37 52.6%

3.0 EXTERNAL WALLING AND FINISHES

3.1 External Walls 65,202.98 1.15 2.2%

3.2 Windows 103,729.63 1.83 3.5%

3.3 External Wall, Floor and Ceiling Finishes 129,721.28 2.29 4.4%

B/I/5
CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR
ELEMENTAL COST PLAN : TOWER B

GROSS FLOOR AREA: 5,266.80 M²


56,691.31 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

Elemental Total 298,653.89 5.27 10.1%

4.0 INTERNAL WALLING

4.1 Walls 69,837.77 1.23 2.4%

4.2 Doors 173,567.40 3.06 5.9%

Elemental Total 243,405.17 4.29 8.2%

B/I/6
CADANGAN MEMBINA 2 TINGKAT RUANG NIAGA DAN TEMPAT PARKIR KERETA DENGAN 2 BLOCK 7 TING
APARTMENT DI UNIVERSITY MALAYA, KUALA LUMPUR
ELEMENTAL COST PLAN : TOWER B

GROSS FLOOR AREA: 5,266.80 M²


56,691.31 Ft²

Item Constituent Functional Element Elemental Total % Of


Cost Elemental Total
Cost/ft2 Cost
(RM) (RM) (%)

5.0 INTERNAL FINISHES

5.1 Wall Finishes 105,704.68 1.86 3.6%

5.2 Floor Finishes 159,426.04 2.81 5.4%

5.3 Ceiling Finishes 30,442.10 0.54 1.0%

Elemental Total 295,572.82 5.21 10.0%

6.0 SERVICES

6.1 Sanitary Fittings and plumbing installations 412,285.10 7.27 14.0%

Elemental Total 412,285.10 7.27 14.0%

Total Estimated Building Cost 2,951,304.04 52.06 100.00%

B/I/7
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

RC pile cap, ground slab,


waterproofing and antitermite

RC column and beam

RC suspended floor slab

Concrete roof tile on steel


trusses

RC staircase complete with


handrailing

115mm thick clay brickwall

Powder coated aluminium


casement windows with
glazing

Generally plaster and painting


for walls, cement screed to
floor, plaster and painting and
UAC suspended panel to
ceiling,

B/I/8
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

Generally, 115mm thick clay


brickwall

Solid door and flush door

B/I/9
ERETA DENGAN 2 BLOCK 7 TINGKAT SERVIS

Remarks

Plaster and painting and


ceramic wall tile

Cement screed, ceramic tiles


and homogenous tiles

Plaster and paint and UAC


suspended ceiling

Allowance for good quality


sanitary wares and fittings and
plumbing installations

B / I / 10