ID Task Name Duration Start Finish Apr 8, '18 Apr 22, '18 May 6, '18 May 20, '18

T M F T S W S T M F T
1
2 1. Inisiasi 5 days Wed 4/18/18 Mon 4/23/18
3 1.1 Memilih Project Manager 4 days Wed 4/18/18 Sat 4/21/18
4 1.2 Membentuk Project Team 3 days Thu 4/19/18 Sat 4/21/18
5 1.3 Membuat Project Charter 1 day Sat 4/21/18 Sat 4/21/18
6 1.4 Membuat Stakeholder Analysis 2 days Sat 4/21/18 Mon 4/23/18
7 2. Perencanaan 10 days Fri 4/20/18 Tue 5/1/18
8 2.1 Membuat Work Breakdown 3 days Fri 4/20/18 Mon 4/23/18
Structure
9 2.2 Membuat Gantt Chart 6 days Wed 4/25/18 Tue 5/1/18
10 3. Eksekusi 77 days Tue 5/1/18 Sat 7/28/18
11 3.1 Analisa 33 days Tue 5/1/18 Thu 6/7/18
12 3.1.1 Analisa Sistem Lama 18 days Tue 5/1/18 Mon 5/21/18
13 3.1.1.1 Analisa Proses Yang 9 days Tue 5/1/18 Thu 5/10/18
Berjalan
14 3.1.1.2 Analisa Kebutuhan 9 days Fri 5/11/18 Mon 5/21/18
15 3.1.2 Analisa Sistem Baru 15 days Tue 5/22/18 Thu 6/7/18
16 3.1.2.1 Membuat Use Case 8 days Tue 5/22/18 Wed 5/30/18
Diagram
17 3.1.2.2 Membuat Activity 3 days Thu 5/31/18 Sat 6/2/18
Diagram
18 3.1.2.3 Membuat Sequence 3 days Sat 6/2/18 Tue 6/5/18
Diagram
19 3.1.2.4 Membuat Class Diagram 3 days Tue 6/5/18 Thu 6/7/18
20 3.2 Perancangan 18 days Fri 6/8/18 Thu 6/28/18
21 3.2.1 Merancang Arsitektur Sistem 3 days Fri 6/8/18 Sun 6/10/18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: ganchart Milestone Inactive Milestone Start-only


Date: Tue 5/15/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
ID Task Name Duration Start Finish Apr 8, '18 Apr 22, '18 May 6, '18 May 20, '18
T M F T S W S T M F T
22 3.2.2 Merancang Interface Sistem 6 days Sun 6/10/18 Fri 6/15/18
23 3.2.3 Merancang Database 8 days Sat 6/16/18 Mon 6/25/18
24 3.2.4 Merancang Sistem 3 days Tue 6/26/18 Thu 6/28/18
25 3.3. Implementasi 21 days Fri 6/29/18 Sun 7/22/18
26 3.3.1 Membangun Sistem 19 days Fri 6/29/18 Fri 7/20/18
27 3.3.2 Instalasi Sistem 2 days Sat 7/21/18 Sun 7/22/18
28 3.4 Pengujian 6 days Mon 7/23/18 Sat 7/28/18
29 3.4.1 White-Box Testing 3 days Mon 7/23/18 Wed 7/25/18
30 3.4.2 Black-Box Testing 3 days Thu 7/26/18 Sat 7/28/18
31 4. Kontrol 106 days Wed 4/18/18 Sat 8/18/18
32 5. Penutup 16 days Wed 8/1/18 Sat 8/18/18
33 5.1 Serah-Terima Sistem 1 day Wed 8/1/18 Wed 8/1/18
34 5.2 Pemberian Kuisioner Kepuasan 16 days Wed 8/1/18 Sat 8/18/18
Client

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: ganchart Milestone Inactive Milestone Start-only


Date: Tue 5/15/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2
May 20, '18 Jun 3, '18 Jun 17, '18 Jul 1, '18 Jul 15, '18 Jul 29, '18 Aug 12, '18 Aug 2
T S W S T M F T S W S T M F T S W S T M F T S W S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: ganchart Milestone Inactive Milestone Start-only


Date: Tue 5/15/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 3
May 20, '18 Jun 3, '18 Jun 17, '18 Jul 1, '18 Jul 15, '18 Jul 29, '18 Aug 12, '18 Aug 2
T S W S T M F T S W S T M F T S W S T M F T S W S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: ganchart Milestone Inactive Milestone Start-only


Date: Tue 5/15/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress