Вы находитесь на странице: 1из 5

Primavera P6

Exercise Worksheet
P6 Exercise Worksheet

CIVIL ENGINEERING MODULE

Prepare by:

ROBERT NOEL V. PERIA, MAPM, MSOE, PMP


1. PROJECT DETAILS

 EPS Node: CE Services


 Project ID: EC1
 Project Name: My New Home Construction Project
 Project Planned Start: 1-Nov-14
 Data Date: 1-Nov-14
 6 Days Calendar
 10 Hours Per Week
 Friday is Non-Working Day

2. WBS OF MY NEW HOME CONSTRUCTION PROJECT

LAY-OUT WBS

WBS CODE WBS NAME


EC1 MY NEW HOME CONSTRUCTION PROJECT
EC1.1 GRADING
EC1.2 FOUNDATION
EC1.3 STRUCTURE
EC1.3.1 FRAMING
EC1.3.2 ROOF
EC1.3.3 INTERIOR
EC1.3.3.1 MECHANICAL
EC1.3.3.2 ELECTRICAL
EC1.3.3.3 PLUMBING
EC1.3.3.4 DRYWALL
EC1.3.3.5 DÉCOR
EC1.3.4 EXTERIOR
EC1.4 LANDSCAPING
3. CREATE ACTIVITIES
WBS ID ACTIVITY ID ACTIVTY NAME ACT. TYPE DUR SUCCESSOR REL
EC1 MY NEW HOME CONSTRUCTION
A1010 ,
A1000 Project Start S. Milestone 0 SS
A1030
Level of
A1010 Project Management A1020 FF
Effort
A1020 Project Complete F. Milestone 0
EC1.1 GRADING
A1030 Survey and Mark OutSite T. Dependent 2 A1040 FS
A1040 Grade Site T. Dependent 5 A1050 FS
EC1.2 FOUNDATION
A1050 Install Foundation Forms T Dependent 2 A1060 FS
A1060 Install Slab Plumbing T Dependent 1 A1070 FS
FS
A1070 Pour and Float Slab Concrete T Dependent 1 A1080
+7
EC1.3 STRUCTURE
EC1.3.1 FRAMING
A1090 ,
A1110,
A1080 Erect Exterior Walls T Dependent 6 FS
A1160, 1180,
A1100
A1090 Erect Interior Stud Walls T Dependent 4 A1190 FS
A1100 Install Exterior Cladding T Dependent 2 A1240 FS
EC1.3.2 ROOF

A1110 Install Trusses T Dependent 2 A1120 FS

A1120 Install Roof Sheeting T Dependent 1 A1130 FS


A1130 Install Paper and Shingles T Dependent 1 A1140 FS
EC1.3.3 INTERIOR
EC1.3.3.1 MECHANICAL
A1140 Install HVAC Ducting T Dependent 2 A1150 SS
A1150 Install HVAC Unit T Dependent 1 A1020 FF
EC1.3.3.2 ELECTRICAL
Install Breaker Box and Rough
A1160 T Dependent 3 A1170 FS
Wire
A1170 Finish Wiring T Dependent 3 A1020 FF
EC1.3.3.3 PLUMBING
A1180 Install Rough Plumbing Lines T Dependent 4 A1190 FS
EC1.3.3.4 DRYWALL
A1190 Rock Walls and Ceilings T Dependent 3 A1200 SS
A1200 tape and Mud Walls and Ceilings T Dependent 6 A1210, A1230 FS
EC1.3.3.5 DÉCOR
A1210 Install Doors T Dependent 2 A1220 FS
A1220 Door Casings and Baseboards T Dependent 3 A1020 FF
A1230 Install Kitchen Cabinets T Dependent 5 A1020 FF
EC1.3.4 EXTERIOR
A1240 Install Windows T Dependent 2 A1250 FS
A1250 Install Slidings T Dependent 3 A1260 FS
EC1.4 LANDSCAPING
A1260 Lay Turf and Plant Trees T Dependent 1 A1020 FF
4. LABOR RESOURCES
Resource ID Resource Name Max Units/Time Standard Rate Resource Type
Manager Project Manager 8/d AED 95.00/h Labor
Foreman Site Forman 8/d AED 55.00/h Labor
HVACEng HVAC Engineer 8/d AED 80.00/h Labor
Surveyor Land Surveyor 8/d AED 65.00/h Labor
Siding Siding Contractor 8/d AED 47.00/h Labor
Electrician Electrician 8/d AED 47.00/h Labor
Leadman Leadman 8/d AED 47.00/h Labor
Plumber Plumber 8/d AED 47.00/h Labor
RCarp Carpenter 8/d AED 37.00/h Labor
Gen Labor Gen Labor 8/d AED 27.00/h Labor
Operator Operator 8/d AED 50.00/h Labor
Concrete Concrete 0/d AED 115.00 Per CY Material

Budgeted
Activity ID Activity Name Resource ID Units / Time Quantity
A1010 Project Management Foreman 8/d 1
A1010 Project Management Manager 8/d 1
A1030 Survey and Mark Out Site Surveyor 8/d 1
A1040 Grade Site Operator 8/d 1
A1050 Install Foundation Forms RCarp 8/d 1
A1050 Install Foundation Forms GenLabor 8/d 1
A1060 Install Slab Plumbing Plumber 8/d 1
A1070 Pour and Float Slab Concrete GenLabor 8/d 4
A1080 Erect Exterior Wall Frames RCarp 8/d 3
A1090 Erect Interior Stud Walls RCarp 8/d 2
A1100 Install OSB Exterior Cladding RCarp 8/d 3
A1110 Install Trusses RCarp 8/d 3
A1120 Install Roof Sheeting RCarp 8/d 3
A1130 Install Paper and Shingles GenLabor 8/d 3
A1140 Install HVAC Ducting HVACEng 8/d 1
A1150 Install HVAC Unit HVACEng 8/d 1
A1160 Install Breaker Box and Rough Wiring Electrician 8/d 1
A1170 Finish Wiring Electrician 8/d 1
A1180 Install Rough Plumbing Lines Plumber 8/d 1
A1190 Install Drywall Sheeting Leadman 8/d 2
A1200 Tape and Mud Leadman 8/d 2
A1210 Install Doors RCarp 8/d 1
A1220 Door Casings and Baseboards RCarp 8/d 1
A1230 Install Kitchen RCarp 8/d 2
A1240 Install Windows RCarp 8/d 1
A1250 Install Siding Siding 8/d 1
A1260 Lay Turf and Plant Trees GenLabor 8/d 3
5. MATERIAL RESOURCES
Budgeted
Activity ID Activity Name Resource ID Units / Time Quantity Standard Rate, AED/Unit
A1040 Grade Site Grading 8/d 120 sq.m Aed 15/ sq.m
A1050 Install Foundation Forms Concrete 8/d 50 cu.m Aed 1600/ cu.m
A1050 Install Foundation Forms Concrete 8/d 50 cu.m Aed 1600/ cu.m
A1060 Install Slab Plumbing Concrete 8/d 20 cu. m Aed 1600/ cu.m
A1070 Pour and Float Slab Concrete Concrete 8/d 20 cu. m Aed 1600/ cu.m
A1080 Erect Exterior Wall Frames Steel 8/d 400 kg Aed 17.00 /kg
A1090 Erect Interior Stud Walls Steel 8/d 400 kg Aed 17.00 /kg
A1100 Install OSB Exterior Cladding Cladding 8/d 120 sq. m Aed 770/ m
A1110 Install Trusses Steel 8/d 1400 kg Aed 17.00 /kg
A1120 Install Roof Sheeting Roof 8/d 80 sq. m Aed 125/ sq.m
A1170 Finish Wiring Cables 8/d 2500 m Aed 45/ sq.m
A1180 Install Rough Plumbing Lines Pies 8/d 120 m Aed 110/m
A1190 Install Drywall Sheeting Sheets 8/d 80 sq. m Aed 8.00/m
A1210 Install Doors Doors 8/d 3 nrs Aed 3500/nr
A1220 Door Casings and Baseboards Doors 8/d 3 nrs Aed 2700/nr
A1240 Install Windows Windows 8/d 6 nrs Aed 1200/nr
A1250 Install Siding Siding 8/d 4 nrs Aed 1800/nr
A1260 Lay Turf and Plant Trees Plants 8/d 40 sq. m Aed 65/ sq.m