NO DESCRIPTION
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
A Powerhouse
Inner Wall 8th 9th
Staging Spiral Casing
Filling Conc EL.209.34-210.70
Filling Conc EL.210.70-211.90
Filling Conc EL.211.90-212.85

B Penstock
Wall Left 3rd
Wall Right 2nd 3rd
Inner Wall 1st left 1st right 2nd right 2nd left 3rd

C Tailrace
Foundation 2nd 3rd 4th
Wall Left 1st
Wall Right 1st
Inner Wall 1st left 1st right
SCHEDULE

FEBRUARY, 2018
27 28

4th

2nd
MONTHLY SCHEDULE OF POWER HOUSE
Project : Rajamandala (Hydro Electric Power Plant 1 x 47 MW)
Company : PT. Multi Karya Engineering
Facility : Power House (Civil)

MAY, 2017 JUNE, 2017


NO DESCRIPTION
27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 Pouring Concrete EL 198.025 A
1.1 Install Rebar
1.2 Install Formwork
1.3 Install Waterstop & Cleaning
1.4 Pouring Concrete
2 Pouring Concrete EL 199.400 A
2.1 Install Rebar
2.2 Install Formwork
2.3 Install Waterstop & Cleaning
2.4 Pouring Concrete
3 Pouring Concrete EL 201.000 A
3.1 Install Rebar
3.2 Install Formwork
3.3 Install Waterstop & Cleaning
3.4 Pouring Concrete
4 Pouring Concrete EL 199.400 B
4.1 Install Rebar
4.2 Install Formwork
4.3 Install Waterstop & Cleaning
4.4 Pouring Concrete

5 Pouring Concrete EL 201.500 B


5.1 Install Rebar
5.2 Install Form Wall Pit
5.3 Staging
5.4 Install Form Slab
5.5 Install Rebar Slab
5.6 Install Waterstop & Cleaning
5.7 Pouring Concrete