Equipment Productivity in Infrastructure Projects in GCC Countries

Conference Paper (PDF Available)  · May 2016 with 438 Reads

Conference: Conference: CIB World Building Congress 2016, At Tampere, Finland

Cite this publication

Mohamed Abdelaal
University of Bolton

Hassan Emam
4.37 · University of Bolton

Peter Farrell
6.07 · University of Bolton

Abstract
Good site management in construction must continually pursue the ef cient utilization and allocation of labour, material and equipment. These
elements are all essential in the pursuit of the Gulf Cooperation Council's (GCC's) vision for the future. Improvement of equipment productivity should be
a considerable concern for control of infrastructure projects. In GCC countries, whilst the direct unit cost of equipment per hour in terms of cost rates
paid may not be signi cantly high, ndings indicate indirect costs are signi cant include hiring, transporting, storage, technical support, supervision and
insurances. Productivity in construction in analytical methods is de ned as unit output per hour. It is important to note that equipment productivity is a
measure of the overall effectiveness of organisation systems in utilizing labour, equipment and capital to convert labour efforts into useful output, and is
not a measure of the capabilities of labour alone. Ef ciency and effectiveness of organisation systems in utilizing resources will lead to minimizing
construction waste. The selection of the appropriate type and size of construction equipment often affects the required amount of time and effort and
thus productivity. Research ndings indicate that construction equipment is used to perform essentially repetitive operations, and can be classi ed
according to its functions into: (a) that requiring operators such as cranes and graders which stay within the con nes of construction sites, and (b)
haulers such as dump trucks and ready mixed vehicles which transport materials to and from sites. The aim of this paper is to identify and analyse
major and common factors affecting equipment productivity on construction projects. A comprehensive literature review and factors recommended by
authors from previous studies will be the foundation of the paper. The method for the study was a quantitative questionnaire supported by exploratory
qualitative interviews with industry practitioners in GCC countries, and the survey ndings indicates the major factor impacting equipment productivity is
rework due to external factors like design changes or/and scope change.

Discover the world's research


15+ million members
100+ million publications
700k+ research projects

Join for free

Full-text (PDF)

Available from: Hassan Emam, Sep 01, 2016


Download full-text PDF

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 1/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

Equipment Productivity in Infrastructure Projects in


GCC Countries

Mohamed Abdelaal, University of Bolton,


maa4mpo@bolton.ac.uk
Hassan Emam, University of Bolton,
he2mpo@bolton.ac.uk
Peter Farrell, University of Bolton,
P.Farrell@bolton.ac.uk

Abstract

Good site management in construction must continually pursue the efficient utilization and
allocation of labour, material and equipment. These elements are all essential in the pursuit of
the Gulf Cooperation Council’s (GCC’s) vision for the future. Improvement of equipment
productivity should be a considerable concern for control of infrastructure projects. In GCC
countries, whilst the direct unit cost of equipment per hour in terms of cost rates paid may not
be significantly high, findings indicate indirect costs are significant include hiring, transporting,
storage, technical support, supervision and insurances.

Productivity in construction in analytical methods is defined as unit output per hour. It is


important to note that equipment productivity is a measure of the overall effectiveness of
organisation systems in utilizing labour, equipment and capital to convert labour efforts into
useful output, and is not a measure of the capabilities of labour alone. Efficiency and
effectiveness of organisation systems in utilizing resources will lead to minimizing construction
waste. The selection of the appropriate type and size of construction equipment often affects the
required amount of time and effort and thus productivity.

Research findings indicate that construction equipment is used to perform essentially repetitive
operations, and can be classified according to its functions into: (a) that requiring operators such
as cranes and graders which stay within the confines of construction sites, and (b) haulers such
as dump trucks and ready mixed vehicles which transport materials to and from sites.

The aim of this paper is to identify and analyse major and common factors affecting equipment
productivity on construction projects. A comprehensive literature review and factors
recommended by authors from previous studies will be the foundation of the paper. The method
for the study was a quantitative questionnaire supported by exploratory qualitative interviews
with industry practitioners in GCC countries, and the survey findings indicates the major factor
impacting equipment productivity is rework due to external factors like design changes or/and
scope change.

Keywords: Construction, Productivity, Equipment, Factors

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 2/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 523 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 3/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 4/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

1. Introduction
Productivity in construction is often broadly defined as output per labour/equipment hour. Since
labour/equipment constitutes a large part of construction cost and the quantity of
labour/equipment hours in performing tasks in construction is more susceptible to the influence
of management than are materials or capital, this productivity measure is often referred to as
‘labour/equipment productivity’. However, it is important to note that labour/equipment
productivity is a measure of the overall effectiveness of organization systems in utilizing its
resource and capital to convert into useful output, and is not a measure of the capabilities of
labour alone. For example, by investing in new equipment to perform certain tasks in
construction, output may be increased for the same number of labour hours, thus resulting in
higher labour productivity. An increase in productivity was noted prior to the mid-1960s in the
construction industry (Stall, 1983). Later, a decline in productivity became an issue of great
concern in the construction all over the world. In 1968, the Construction Roundtable was
established due to concern about the increased cost of construction resulting from an increase in
inflation and a significant decline in construction productivity (Thomas and Kramer, 1988). It
was necessary to implement, as far as possible, industry-wide principles of production
throughout the construction process. It was argued that careful adaptation would be required, to
implement knowledge and experience gained in manufacturing to construction (Alarcon and
Borcherding, 1991).

Past studies and research show that a number of factors affect productivity, but there are still
unidentified factors that need to be further studied even in developed countries
(Makulsawatudom and Emsley, 2002). A study by Polta and Arditi (2005) stated that policies to
raise productivity are not always similar in each country. Their study identified different factors
affecting labour productivity and grouped them according to their characteristics such as design,
execution plan, material, equipment, labour, health and safety, supervision, working time,
project factors, quality, leadership and coordination, organization, owner/consultants, and
external factors. Adrian (1987) classified the factors causing low productivity as industry-
related factors, labour-related factors, and management-related factors. Industry-related factors,
essentially, are the characteristics of the construction industry, such as the uniqueness of
construction projects, varied locations, adverse and unpredictable weather, and seasonality.
Labour-related factors included lack of training and learning for labour, and lack of motivation.
Management-related factors usually refer to a lack of management, and inappropriate use of
tools and techniques. Olomolaiye et al. (1998) classified productivity factors into two
categories: external factors are outside the control of organization management and internal
factors relate to productivity issues originating within the organization. Thomas and Sakarcan
(1994) developed ideas to describe factors affecting labour productivity. One study suggested
that scheduled overtime always leads to efficiency losses because of the inability to deliver
materials, tools, equipment, and information at an accelerated rate (Ginther, 1993). Productivity
in the construction industry is not only influenced by labour, materials and equipment.
However, most researchers and construction practice to date has primarily concentrated on
labour productivity, as though labourers’ performance is the sole contributor to increased
construction productivity (Alwi, 1995). Investigation conducted by (Alwi, 2002) concluded that
there was now concern over the high level of non-value adding activities within the construction
industry. The activities, known as construction waste (disposals), have been identified as major
factors affecting construction productivity. The foundation for this paper is built upon the work
of Abdelaal et al, (2014) which examined labour productivity in GCC countries.

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 5/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 524 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 6/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 7/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

2. Literature Review
Productivity is the outcome of several interrelated factors. Discussed below are various factors
affecting construction productivity and are reviewed from past studies.

2.1. Site working time:

During construction projects, working overtime initially results in increased production


rates, but continuing overtime may lead to increased costs and reduced productivity (Hinze,
1999). Alinaitwe et al (2005) found that employees in the field only work effectively for 3.5
hours of an 8-hour shift and spend only 20% of time on direct value-adding activities.

2.2. Managing site equipment:

The Construction Industry Institute states that material and equipment currently comprise
50-60% of construction project costs (Materials Management Task Force, 2007). In addition,
lack of suitable equipment is considered one of the major causes of construction delays.
Good equipment management begins at the time the equipment is purchased/hired.
Purchasing/hiring the proper equipment that matches the need of assigned tasks, while
achieving the lowest costs, is necessary to attain suitable equipment management. Proper
record keeping provides information for planning maintenance/ replacement, ensuring that
they occur at the proper time. Managing equipment includes preventative maintenance,
planning maintenance, and replacement activities (O’Brien et al 2007).

2.3. Communication:

Good communication is necessary to efficiently complete a project. Some of the


more commonly used forms of work site communication include two-way radios, mobile
phones and mobile wireless internet. Lack of communication can cause delays due to
mistakes causing rework, lack of information causing downtime, and misinterpretation. Other
common problems associated with communication on construction projects include
understanding the chain of command and continuously communicating about the project and
foreseeing potential problems in the future. This can be avoided by holding regular
project management team meetings (Cingoranelli, 2007). As stated in the Project
Management Institute’s Standard (PMI, 2009), about 90% of project manager time is spent in
communication.

2.4. Work schedules:

When there are early delays in projects, compression of the overall time frame for later activities
is often used to compensate interruptions and to complete assigned tasks on schedule. From
a professional scheduling perspective, schedule compression may be possible without
accelerating individual work activities by utilizing float in project schedules; however in
many projects, schedules are not fully resource loaded. As a consequence, an updated
schedule reflecting delays may show the project finishing on time without shortening
individual activities (National Electrical Contractors Association, 1983).

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 8/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 525 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 9/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 10/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

2.5. Working tasks types:

To accomplish acceptable productivity, every member of a crew requires adequate space


to perform tasks without being affected by other crew members (space constraint). When
more labourers are allotted to perform particular tasks, in a fixed amount of space, it is
probable that interference may occur, thus decreasing productivity. Additionally, when
multiple trades are assigned to work in the same area, the probability of interference rises and
productivity may be reduced. Interference among the various crews and labourers is due to
mismanagement on construction sites. For example, a steel-fixing crew has to wait before
fixing reinforcement bars if the carpenter’s formwork is incomplete. Types of activities and
construction methods also influence labour productivity (Sanders and Thomas, 1991).

2.6. Safety measures:

Accidents have high impact on labour productivity. Various accident types occur at sites,
and some may cause fatal injuries and result in total work stoppage for a number of
days. An accident that causes an injured person to be hospitalized results in a work decrease
of the crew for which the injured employee worked. Small accidents resulting from
protruding nails and steel wires can stop work and, thus, decrease productivity (Sanders and
Thomas, 1991).

2.7. Quality control:

Inefficiency of equipment, unskilled labourers and poor quality of raw material are
factors which cause low productivity. The productivity rate of inefficient equipment is
low. Old equipment is subject to a great number of breakdowns, and it takes a long time for
labourers to complete the work, thus reducing productivity. Poor-quality material used for
work is another reason for reducing productivity; also unskilled labourers causing rework,
which leads to low productivity.

2.8. Managerial factors:

Project manager skills and attitudes influence construction productivity. In many organizations,
productivity is low even though the latest technology and trained labour are made
available. Low productivity is often because of inefficient and immature management.
Advanced technology requires knowledgeable labourers who work under professionally
capable leaders.

2.9. Skilled labourers:

A lack of labour experience is the factor which negatively affects labour productivity and
proves that, to achieve good productivity, labour plays a significant role. Contractors
should have sufficiently skilled labourers employed to be productive. If skilled labour is
unavailable and a contractor is required to complete specific tasks with less-skilled
labour, it is likely that productivity will be negatively impacted. Lack of compensation
and increased labourer age negatively affect labour productivity because labour speed,
agility, and strength decline over time and reduce productivity (Heizer and Render, 1990).

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 11/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 526 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 12/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 13/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

2.10. Motivation:

Motivation is one of the important factors affecting construction labour productivity.


Motivation can best be accomplished when labourers’ personal ambitions are aligned with
organization strategic goals. Factors such as payment delays, a lack of a financial motivation
system, non-provision of proper transportation, and a lack of training sessions are grouped
in this topic (DeCenzo and Holoviak, 1990).

2.11. Scope changes:

Construction projects often have design, drawings and specification changes as work
proceeds. If drawings or specifications are unclear, productivity may decrease since labourers
in the field are uncertain about what needs to be done. As a result, tasks may be delayed,
or have to be completely stopped and postponed until there are clear instructions. There can
be a 30% loss of productivity when work changes are being performed (Thomas et al., 1999).
Work inspection by supervisors is an essential process before proceeding to subsequent
stages. For example, contractors cannot cast concrete before an inspection of formwork and
steel work, thus affecting labour productivity (Zakeri et al, 1996).

2.12. Availability of material/tools:

Productivity can be affected if required materials, tools, or construction equipment are


not available at the correct location and time. If the improper tools or equipment are
provided, productivity may be negatively affected (Alum and Lim, 1995; Guhathakurta and
Yates, 1993). The size of construction sites and material storage locations have a
significant impact on productivity especially in infrastructure projects where there are
often large space areas for work, and labourers spend time moving materials from
inappropriate storage locations, thus resulting in productivity loss (Sanders and Thomas,
1991).

2.13. Over planning and work methodology:

Improper scheduling of work, shortage of critical construction equipment or labour, may


result in loss of productivity. Improper planning of project-initiation procedures may lead
to lost labour productivity. Also, poor site layout can contribute to a loss of productivity.
According to the Association for the Advancement of Cost Engineering (AACE, 2004)
labourers may have to walk or drive long distances to lunch rooms, rest areas,
washrooms, entrances, and exits, affecting overall productivity.

2.14. External factors:

Various natural factors affecting equipment productivity collected from previous studies
are weather conditions and geographical conditions. Others factors such as fuel, water, and
minerals also affect productivity to a certain extent. Productivity is found to be highly
affected if the weather is too extreme (too cold, heavy rainfall, or too hot, as in the case of
this study in GCC countries).

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 14/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 527 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 15/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 16/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

3. Methodology
This research investigates important factors affecting equipment productivity in construction in
GCC countries. Understanding these factors is helpful for construction professionals who work
on all project phases, especially on the initial phase of construction planning, in order to
efficiently deliver project plans. The main goal of the research is to provide essential
information about factors affecting construction productivity. Factors which affect construction
productivity are a lack of required materials, disputes between the major parties, weather,
changes during construction, accidents, and other items. The research study aims to provide
knowledge of construction project-related factors that affect productivity. The data collection
instruments used in the research are a questionnaire survey, followed by interviews with
practitioners. The research passed through the following phases in figure 1:

Background of productivity

Review of literature/Issue identification

Design of questionnaire

Survey and data collection

Data analysis

Conclusion/Recommendations

Figure 1: research phases

The data collection process used in this research had the option of two basic methods:
questionnaires and personal interviews. A questionnaire was preferred as the best effective and
suitable data-collection technique for the study. The questionnaire was a self-administered tool
with web-design questions. A questionnaire in a web-survey format comparatively requires less
duration and saves cost for the researcher while permitting participants to respond to the
questionnaire at their convenience. However, for this approach the response rate is usually
lower as compared to face-to-face interviews. Data was collected for the literature review from
books, journals and articles. The population for the survey was employees from different
professions involved in construction in GCC countries.

3.1. Questionnaire and results

Participants were asked to indicate to what extent factors affect equipment productivity
on infrastructure sites in GCC. Responses were scored as 1 – not applicable; 2 – does not affect
it; 3 – somewhat affects it; 4 – directly affects it.

3.2. Survey and questionnaire revision

Face-to-face discussions were conducted with ten construction practitioners. This procedure
improved the formation of the web-survey. A total of 130 questionnaires, were sent by e-mail to
contractors, architects, owners, project managers, and project engineers of various construction

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 17/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 528 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 18/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 19/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

organizations. In addition conducted collection process with qualitative interviews with


construction professionals.

3.3. Questionnaire distribution

The target groups in this study were professionals from the construction industry. A list of
550 building-construction organizations was obtained from the Construction Week online the
GCC magazine. The sample size can be calculated with the following equation for a 94%
confidence level (AlShahri, M et al., 2001; Moore et al., 2003):

!"
n= !" (1)
!!
!

Where, n = total number of population, N = sample size from a finite population, n’ = sample
size from an infinite population= S2/V, S2 = the variance of the population elements and, V = a
standard error of the sampling population (usually, S= 0.5, and V = 0.06). n'= S2 / V2 = (0.5)2 +
(0.06)2 = 69.44, for N=550, n = 69.44 / [1 + (69.44 / 547)] = 62, to obtain 94% of confidence
level, it was calculated to send the questionnaire to minimum of 62 participants.

3.4. Data collected from the web survey

To successfully achieve the objective of the study, one of the most important phases is
collection of accurate data. Data collection is a procedure of collecting crucial data records
for a certain sample or population of observations (Bohrnstedt and Knoke, 1994). shows the
participant’s characteristics: The characteristics of participants involved in the survey were
tabulated in Table 1. The average work experience of the participants involved in
construction industry is 15 years with managerial level and majority belongs to control
debarment. This indicates reasonably a high work experience profile within GCC
construction industry.

Table 1: Characteristics of participants/ Company classification


Participants Questionnaire Responses Percentage of
distributed returned responses
Client 5 3 18.80%
Consultants 5 2 12.50%
Contractors 100 11 68.70%
Sub-contractors 5 0 00.00%
Suppliers 5 0 00.00%
Total 130 16 13.33%

3.5. Analysis method used

In order to facilitate the study, after the literature review and the focus interviews, a plan was
formulated for collecting field information and creating an evaluation process and numerical
values. It was necessary to provide straightforward communication to participants to ensure a
clear understanding of all the applicable definitions, procedures, and guidelines that were used
in collecting data.

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 20/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 529 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 21/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 22/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

3.5.1. Ranking

Ranking of the various factors according to their relative importance index (RII) for affect
ranges: (1 – Not applicable; 2 – Does not affect it; 3 – Somewhat affects it; 4 – Directly affects
it). RII for each factor as follows: !!!=ΣW/A*N, where W is the weighting given to each factor
by the participants (ranging from 1 to 4), A is the highest weight (i.e. 4 in this case), and N is
the total number of participants. For the interpretation of the !!! values, !!! is ranked from the
highest to the lowest.
3.5.2. Analysis

Table 2 illustrates RII a rankings of 29 common factors affecting productivity of equipment as


per previous studies, and factors were categorized into five major groups and were ranked. The
results show that clients, consultants, and contractors all agreed that the external group of
factors affecting productivity was the most influential. Resources factors were considered the
second most important factor affecting productivity in construction projects followed by Misc.,
Operators and communication.

Table 2: Top factors affecting equipment productivity in construction projects in GCC


Factors affecting construction equipment productivity at infrastructure sites RII RANK
1- Operators
Lack of experience 0.83 2
Disloyalty 0.73 6
Age 0.41 31
Personal problems 0.50 30
Absenteeism 0.70 10
2- External
Implementation of standards, government laws & regulation 0.83 3
Rework 0.84 1
Lack of Supervision 0.81 4
Permits delays from the authorities 0.73 6
Variations & design changes 0.61 23
Complex designs in drawings. Incomplete drawings 0.72 9
Payment delays 0.63 18
Lack of training 0.63 18
3- Communication
Misunderstanding between owner, contractor and designer 0.61 23
Disputes with owner/designer 0.64 16
4- Resources
Lack of required construction materials or/and price increase 0.73 6
Availability of required equipment 0.78 5
Poor site conditions or/and differing from plan 0.69 11
Differing from plan 0.61 23
Poor access within construction job site 0.61 23
Violations of safety laws 0.61 23
Insufficient lighting 0.61 18
Inadequate construction method 0.63 11
Inadequate transportation facilities for workers 0.69 23

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 23/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 530 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 24/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 25/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

Material storage location 0.58 29


5- Miscellaneous
Shortage of water and/or power supply 0.66 15
Working overtime 0.63 18
Power supply 0.63 18
Weather conditions 0.64 16
Accidents during construction 0.67 13
Project objective s are not well defined 0.67 13

4. Conclusion and Summary


This research provides study and knowledge of construction productivity and focus on factors
affecting equipment productivity in infrastructure construction projects in GCC countries. The
study sought the views of clients, consultants, and contractors on the outcome of infrastructure
projects especially public projects that influence economics. Prior knowledge of
labour/equipment productivity during construction can save cost and time. Investments for these
projects are very high and because of the complexity in construction, various factors can highly
affect overall productivity, thus projects can end up adding even more time and cost. The
research is intended to identify major common factors affecting equipment productivity in
infrastructure projects. This study investigates all possible factors through a structured
questionnaire administered in GCC countries. The survey results are subjected to analysis, and
the ranking of factors is calculated using Relative Importance Indices (RII). The study showed
that all the three groups-clients, consultants and contractors of participants generally agreed that
out of a total of 29 factors the top 10 influencing factors affecting equipment productivity
arranged in descending order of RII are:

• Rework
• Lack of experience
• Implementation of standards, government laws & regulation payment delays
• Lack of supervision
• Availability of required equipment
• Disloyalty
• Lack of required construction materials or/and price increase.
• Permits delays from authorities.
• Complex designs in drawings. Incomplete drawings

The results show that clients, consultants, and contractors all agreed that the external group of
factors affecting productivity was the most influential. Resources group of factors were
considered the second most important factor affecting productivity in construction projects
followed by miscellaneous, operators and communication factors. In addition, the study showed
10 factors that affection productivity of excavator in infrastructure projects, that the top
influencing factor affecting excavator productivity using RII is soil characteristics. From
previous studies, it has been shown that the nature of the construction industry, usually involves
the separation of design and construction functions. This has affected construction productivity
through delays in drawings, design changes, and following rework. Clients have sometimes
delayed projects because of their lack of suitable knowledge about construction procedures.
Moreover, being an outdoor industry, construction performance is significantly affected by
weather conditions. In addition to the factors discussed, health and safety regulations, and codes
of practices are other external factors influencing task operations and productivity. Factors

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 26/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 531 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 27/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 28/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

internal to construction companies include management inadequacy resulting in a waste of


resources and consequent losses in productivity; adoption of modern technology and training for
labourers would increase productivity. This research was carried out in infrastructure
construction projects in GCC. It may be that the issues of the key factors, the model developed
and the alternative solutions here can provide guidance to the other studies and researchers.
Concepts such as waste and value are not well understood by construction personnel. They often
do not realise that many activities they carry out, do not add value to work. Waste is not only
associated with waste of materials in the construction , but also other activities that do not add
value such as rework, waiting time and delays. These issues contribute to a reduction in the
value of construction productivity.

5. Recommendations
Construction projects are high risk and often lead to a disputes and claims as work progresses,
which then subsequently further affects progress. The environment within construction
organisations should be suitable to successfully complete projects. In construction, it is
necessary to identify potential problems in advance, in order to avoid and overcome possible
impacts on cost or project time. Detailed below are recommendations which were found to
improve equipment productivity on the infrastructure projects in GCC countries:

Material delivery schedules should be provided for projects and monitored closely by
contractors. Using suitable materials and tools also has a positive effect on tasks and thus,
better labour productivity can be achieved. Material should be stored at appropriate locations
and should be easily accessible. Project managers should provide suitable logistic plans at
the initial phase of projects. Good equipment management begins at the time the equipment
is purchased/hired. Purchasing/hiring the proper equipment that matches the need of
assigned tasks, while achieving lowest costs is necessary to attain suitable equipment
management. Proper record keeping provides information for planning maintenance/
replacement, ensuring that they occur at the proper time. Organizations should make sure
sites are safe and undertake continuous safety training. Various external and natural factor
risks should be considered in budget estimations to minimize delays due to closures and
material shortages. There should be suitable contingency budgets to cover increased costs of
material. Motivation and training systems, should be implemented to create competition
among the employees, thus achieving better productivity. Complex designs and incomplete
drawings should be avoided and care should be taken to avoid confusion among the various
construction agencies. Absenteeism at work site can be reduced with inclusion of
appropriate paid time off and vacations to all employees.

6. Future Research
Further research should focus on the holistic barriers of implementing models for managing site
resources (labour, equipment and materials) in addition to construction waste management, and
development of a universal implementation framework that can fit into any construction
environment and type. In the same vein, further work should be undertaken on applying the
research in other developing economies. Similarly, additional research should be made in the
adoption of lean construction tools and techniques within GCC countries such as Location
Based Management Systems (LBMS) and Last Planner Systems (LPS) (Abdelaal, et al., 2015).

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 29/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 532 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 30/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 31/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

References
AACE (2004) “Estimating Lost Labour Productivity in Construction Claims, Association for
the Advancement of Cost Engineering”, International Recommended Practice No. 25R-03,
2004.

Abdelaal M, Emam H and Farrell P (2015), “Improving work flow in construction projects in
GCC”, The 2nd International Conference on Buildings, Construction and Environmental
Engineering (BCEE2), Lebanon.

Abdelaal, M, Farrell P and Emam H (2014), “Factors affecting productivity in GCC


Construction Projects”. 1st International Conference of the CIB Middle East and North Africa
Research Network (CIB-MENA). Abu-Dhabi University. 14-16 December 2014

Adrian J (1987) “Construction Productivity Improvement”, New York, Elsevier.

Adrian J (1990) “Improving Construction Productivity Seminar”, Minneapolis, MN: AGC-The


Associated General Contractors of America.

Alarcon L F and Borcherding J D (1991) “Quantitative effects on construction productivity”,


The Construction Lawyer, American Bar Association.

Alinaitwe H, Mwakali J and Hansson B (2005) “Labour productivity in the building


construction, CIB 2006, W065/W055/W086 – Construction in the XXI century”, Local and
global challenges, Rome, Italy.

Al-Shahri M, Assaf S A, Atiyah S and AbdulAziz A (2001) “The management of construction


company overhead costs”, International Journal of Project Management.

Alum J and Lim E C (1995) “Construction productivity: Issues encountered by contractors in


Singapore”, International Journal of Project Management.

Alwi S (1995) The Relationship Between Rework and Work Supervision of Upper Structure in
The Reinforced Concrete Building Structure, Unpublished Master Thesis, University of
Indonesia, Jakarta.

Alwi S (2002). Non Value-Adding Activities in the Indonesian Construction Industry:


Variables and Causes, Unpublished Doctoral Thesis, Queensland University of Technology,
Brisbane – Australia.

Bohrnstedt G and Knoke, D (1994) “Statistics for Social Data Analysis (3rd Edition)”, F.E.
Peacock Publishers, Inc., Itaska IL.

Cingoranelli Dom. (2007) "Use Partnering to Improve Construction Productivity”.

Decenzo D and Holoviak S (1990) “Employee Benefits” Prentice Hall, City, New Jersey, 55- 56.

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 32/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 533 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 33/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 34/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

Ginther R S (1993) “The effect of work environment on labor performance, ME thesis”,


Pennsylvania State University, University Park, PA.

Guhathakurta S and Yates J (1993) “International labor productivity.” Journal of


Construction Engineering, 35(1), 15-25.

Harris F, Holt G, Kaming E and Olomolaiye P (1998) “Factors influencing craftsmen's


productivity in Indonesia.” International Journal of Project Management, 15(1), 21-30.

Heizer J and Render B (1990) “Production and Operations Management”, Strategic and
Tactical Decision. Prentice Hall, NJ.

Hinze J W (1999) “Construction Planning & Scheduling”, Prentice Hall, Upper Saddle River,
NJ.

Makulsawatudom A and Emsley M (2002) “Critical factors influencing construction


productivity in Thailand”, CIB 10th International Symposium on Construction Innovation and
Global Competitiveness, Cincinnati, OH.

Materials Management Task Force (2007) "Project Materials Management Handbook."


ConstructionIndustryInstitute.http://www.constructioninstitute.org/scriptcontent/more/sp4_m
ore.cfm.

National Electrical Contractors Association, (1983) “Rate of Manpower consumption in


Electrical Construction”, Electrical Construction Peak Workforce Report.

O’Brien J and Zilly, R (2007) “From Procurement to Maintenance and Service.”


http://www.builderspace.com/features/equipmentmanagement.html

Polta G and Arditi P (2005) “The JIT Management System in developing countries”,
Construction Management and Economics.

PMI (2008) “Communications area of knowledge, A Guide to the Project Management Body of
Knowledge (PMBOK® Guide)", Project Management Institute, Fourth Edition.

Sanders S R and Thomas H R (1991) “Factors affecting masonry productivity”, Journal of


Construction Engineering Management.

Stall M D ( 1983) “ Analyzing and improving productivity with computerized questionnaires


and delay surveys”, Project Management Institute Annual Seminar

Thomas H R and Kramer D F (1988) “The manual of construction productivity measurement


and performance evaluation”, Source Document 35, Construction Industry Institute, University
of Texas at Austin.

Thomas H R and Oloufa A (1995) “Labour productivity, disruptions, and the ripple effect”,
Cost Engineering.

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 35/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 534 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 36/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 37/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › Download full-text PDF


Download citation Share
31 References

Thomas H R, Riley D R, and Sanvido V E (1999) “Loss of labor productivity due to delivery
methods and weather”, Journal of Construction Engineering and Management.

Thomas H R and Sakarcan A S (1994) “Forecasting labour productivity using the factor
model”, Journal of Construction Engineering and Management, 120(1), 228-239.

Zakeri M, Olomolaiye P O, Holt G D and Harris F C (1996) “A Survey of Constraints on


Iranian Construction Operatives’ Productivity”, Journal of Construction Management and
Economics

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 38/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See all › 535 Download full-text PDF


Download citation Share
31 References

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 39/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

SeeCitations (0)
all › References (31) Download full-text PDF
Download citation Share
31 References

Improving Work Flow in Construction Projects in GCC Countries


Conference Paper Full-text available Oct 2015
Mohamed Abdelaal · Hassan Emam · Peter Farrell

View Show abstract

Project Materials Management


Chapter Jan 2013
Nolberto Munier

View Show abstract

Construction Productivity Improvement at a Construction Battalion Unit.


Article Nov 1995
Mary J. Helinski

View

Production/Operations Management
Article Apr 1976 · ACAD MANAGE REV
George J. Gore

View

Factors Affecting Productivity in GCC Construction Projects


Conference Paper Full-text available Dec 2014
Mohamed Abdelaal · Peter Farrell · Hassan Emam

View Show abstract

Critical Factors In uencing Construction Productivity in Thailand


Article
Arun Makulsawatudom · Margaret Emsley · Kuldej Sinthawanarong

View Show abstract

Show more

Recommendations
Discover more publications, questions and projects in Productivity

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 40/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See allProject
› Download full-text PDF
Download citation Share
31 References
Improving Work Flow in Construction Projects in GCC Countri
Mohamed Abdelaal · Hassan Emam · Peter Farrell
View project

Project

Optimising Project Controls for Construction


Hassan Emam
The aim of the research is to formulate an optimised integrated project controls process.

View project

Conference Paper

Factors Affecting Productivity in GCC Construction Projects


December 2014

Good project management in construction must continually pursue the ef cient utilization and allocation of labor, material and equipment. These elements are all
essential in the pursuit of the Gulf Cooperation Council’s (GCC) vision for the future. Improvement of labor productivity should be a major concern for control of
construction projects in Gulf Countries. Reducing demand for labor will... [Show full abstract]

Read more

Conference Paper

Improving Work Flow in Construction Projects in GCC Countries


October 2015

Productivity problems often lead to time and cost over-runs on construction projects. These problems manifest themselves in a lack of coordination, unidenti ed
scope leading to poor planning, lack of monitoring and control, unrealistic schedules, poor implementation, and incorrect resource allocation. There it is a concern
about how to best plan and control projects, and what is the optimised... [Show full abstract]

Read more

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 41/43
5/22/2018 Equipment Productivity in Infrastructure... (PDF Download Available)

See allConference
› Paper Download full-text PDF
Download citation Share
31 References
Causes of Delay on Large Infrastructure Projects in Qatar
September 2015

The construction industry is of high importance to the economy of most countries. However, it is notorious for projects overrunning time and cost. A plethora of
research has been conducted to de ne causes of delay in completing construction projects. These studies employed a wide variety of analytical methods to
statistically conclude the most precise ranking of causes of delay. Moreover, the... [Show full abstract]

Read more

Conference Paper

Causes of Delays on Large Building Projects in Qatar


October 2015

The construction industry is of high importance to the economy of most countries. However, it is notorious for projects overrunning time and cost. Several studies
have been conducted to de ne causes of delay in completing construction projects. This research has employed a wide variety of analytical methods to conclude
the most precise statistical ranking of causes of delay. Moreover, the... [Show full abstract]

Read more

Discover more

Data provided are for informational purposes only. Although carefully collected, accuracy cannot be guaranteed. Publisher conditions are provided by RoMEO. Differing provisions
from the publisher's actual policy or licence agreement may be applicable.

This publication is from a journal that may support self archiving. Learn more

Ad

Ad
About Support Business solutions

News Help center Recruiting


Company FAQ Advertising
Careers

Business IT Innovation Mgmt - View the Free


White Paper Now

go.oracle.com/Engineer... Visit Site

© ResearchGate 2018. All rights reserved. Imprint · Terms · Privacy

https://www.researchgate.net/publication/307541045_Equipment_Productivity_in_Infrastructure_Projects_in_GCC_Countries 42/43