Title Block: Drawing Number properly specified.

2 Title Block : Area code specified.

3 Title Block : Project Name and Number Specified.

4 Title Block : Plan or Section Specified

5 Title Block : For Plans, Elevation level specified.

6 Title Block : For Sections, Section Grid Numbers Specified.

7 Title Block : Revision Number Specified.

8 Sidebar : List of Equipments with Tag numbers and Equipemnt Description included in Side bar.

9 Sidebar : Top of foundation elevation specified for Pumps.

10 Sidebar : Bottmon Tanline elevation specified for Towers and Vertical Vessels.

11 Sidebar : Centreline elevations specified for Horizontal Vessels, Exchangers

12 Sidebar : List of all holds included

13 Sidebar : List of reference documents included

14 Sidebar : Key plan included with patterned area indicating location of this drawing.

15 Drawing : North direction specified along with prevailing wind direction.

16 Drawing : All applicable structural grids marked.

17 Drawing : All applicable structural components shown including small platforms, ladders etc.

18 Drawing : TOS elevation of all platforms specified.

19 Drawing : All equipment’s located in both EW and NS directions.

20 Drawing : All structural cutouts shown.

21 Drawing : Requirement for curb wall for chemical handling pumps, tanks in shown.

22 Drawing : Foundation elevation of pumps shown in elevation drawing.

23 Drawing : BTL Elevation of vertical vessels shown in elevation drawing.

24 Drawing : Centerline elevation of horizontal vessels and exchangers shown in elevation drawings.

25 Drawing : Operator and maintenance accessways marked.

26 Drawing : Davit requirements and drop zones marked.

27 Drawing : Floor cutouts to remove agitator assemblies if any marked.


28 Drawing : Monorails, Overhead travelling crane requirements shown.

29 Drawing : Staircase requirements shown.

30 Drawing : Location of Manholes shown (Orientation,Elevation).

31 Drawing : Equipment platforms and ladders shown.

32 Drawing : Ducting work if any is shown.

33 Drawing : Tube bundle removal area shown for Heat exchangers.

34 Drawing : Manhole cover swing area shown.

35 Drawing : Maintenance area for plate heat exchanger, spiral heat exchanger is shown.

36 Drawing : Locaton of ×xed saddle for horizontal shell and tube heat exachangers is shown.

37 Drawing : Pumps located in plan based on centre of their discharge.

Checklist: Equipment Layout Checking


SL
DESCRIPTION Y/N REMARKS
No
1 Title Block: Drawing Number properly specified.

2 Title Block: Area code specified.

3 Title Block: Project Name and Number Specified.

4 Title Block : Plan or Section Specified

5 Title Block: For Plans, Elevation level specified.

6 Title Block: For Sections, Section Grid Numbers Specified.

7 Title Block: Revision Number Specified.

8 Sidebar: List of Equipment’s with Tag numbers and Equipment


Description included in Side bar.
9 Sidebar: Top of foundation elevation specified for Pumps.

10 Sidebar: Bottom Tan line elevation specified for Towers and Vertical
Vessels.
11 Sidebar : Centerline elevations specified for Horizontal Vessels,
Exchangers
12 Sidebar : List of all holds included

13 Sidebar : List of reference documents included


14 Sidebar: Key plan included with patterned area indicating location of
this drawing.
15 Drawing: North direction specified along with prevailing wind
direction.
16 Drawing: All applicable structural grids marked.
17 Drawing : All applicable structural components shown including small
platforms, ladders etc.
18 Drawing: TOS elevation of all platforms specified.

19 Drawing: All equipment’s located in both EW and NS directions.

20 Drawing: All structural cutouts shown.

21 Drawing: Requirement for curb wall for chemical handling pumps,


tanks in shown.
22 Drawing: Foundation elevation of pumps shown in elevation drawing.

23 Drawing: BTL Elevation of vertical vessels shown in elevation drawing.

24 Drawing: Centerline elevation of horizontal vessels and exchangers


shown in elevation drawings.
25 Drawing: Operator and maintenance access ways marked.

26 Drawing: Davit requirements and drop zones marked.

27 Drawing: Floor cutouts to remove agitator assemblies if any marked.

28 Drawing: Monorails, Overhead travelling crane requirements shown.

29 Drawing: Staircase requirements shown.

30 Drawing: Location of Manholes shown (Orientation, Elevation).

31 Drawing: Equipment platforms and ladders shown.

32 Drawing: Ducting work if any is shown.

33 Drawing : Tube bundle removal area shown for Heat exchangers

34 Drawing: Manhole cover swing area shown.

35 Drawing: Maintenance area for plate heat exchanger, spiral heat


exchanger is shown.
36 Drawing: Location of fixed saddle for horizontal shell and tube heat
exchangers is shown.
37 Drawing: Pumps located in plan based on center of their discharge.